            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM

 

                CHAPTER 1--FEDERAL ACQUISITION REGULATION

 

PART 49_TERMINATION OF CONTRACTS--Table of Contents

 

Subpart 49.2_Additional Principles for Fixed-Price Contracts Terminated 

                             for Convenience

 

49.206-2  Bases for settlement proposals.



    (a) Inventory basis. (1) Use of the inventory basis for settlement 

proposals is preferred. Under this basis, the contractor may propose 

only costs allocable to the terminated portion of the contract, and the 

settlement proposal must itemize separately--

    (i) Metals, raw materials, purchased parts, work in process, 

finished parts, components, dies, jigs, fixtures, and tooling, at 

purchase or manufacturing cost;

    (ii) Charges such as engineering costs, initial costs, and general 

administrative costs;

    (iii) Costs of settlements with subcontractors;

    (iv) Settlement expenses; and

    (v) Other proper charges.

    (2) An allowance for profit (49.202) or adjustment for loss 

(49.203(b)) must be made to complete the gross settlement proposal. All 

unliquidated advance and progress payments and all disposal and other 

credits known when the proposal is submitted must then be deducted.

    (3) This inventory basis is also appropriate for use under the 

following circumstances:



[[Page 938]]



    (i) The partial termination of a construction or related 

professional services contract.

    (ii) The partial or complete termination of supply orders under any 

terminated construction contract.

    (iii) The complete termination of a unit-price (as distinguished 

from a lump-sum) professional services contract.

    (b) Total cost basis. (1) When use of the inventory basis is not 

practicable or will unduly delay settlement, the total-cost basis (SF-

1436) may be used if approved in advance by the TCO as in the following 

examples:

    (i) If production has not commenced and the accumulated costs 

represent planning and preproduction or get ready expenses.

    (ii) If, under the contractor's accounting system, unit costs for 

work in process and finished products cannot readily be established.

    (iii) If the contract does not specify unit prices.

    (iv) If the termination is complete and involves a letter contract.

    (2) When the total-cost basis is used under a complete termination, 

the contractor must itemize all costs incurred under the contract up to 

the effective date of termination. The costs of settlements with 

subcontractors and applicable settlement expenses must also be added. An 

allowance for profit (49.202) or adjustment for loss (49.203(c)) must be 

made. The contract price for all end items delivered or to be delivered 

and accepted must be deducted. All unliquidated advance and progress 

payments and disposal and other credits known when the proposal is 

submitted must also be deducted.

    (3) When the total-cost basis is used under a partial termination, 

the settlement proposal shall not be submitted until completion of the 

continued portion of the contract. The settlement proposal must be 

prepared as in subparagraph (2) above, except that all costs incurred to 

the date of completion of the continued portion of the contract must be 

included.

    (4) If a construction contract or a lump-sum professional services 

contract is completely terminated, the contractor shall--

    (i) Use the total cost basis of settlement;

    (ii) Omit Line 10 ``Deduct-Finished Product Invoiced or to be 

Invoiced'' from Section II of Standard Form-1436) Settlement Proposal 

(Total Cost Basis); and

    (iii) Reduce the gross amount of the settlement by the total of all 

progress and other payments.

    (c) Other basis. Settlement proposals may not be submitted on any 

basis other than paragraph (a) or (b) above without the prior approval 

of the chief of the contracting or contract administration office.