Sec. 9.306  Solicitation requirements.



    Solicitations containing a testing and approval requirement shall--

    (a) Provide, in the circumstance where the contractor is to be 

responsible for the first article approval testing--

    (1) The performance or other characteristics that the first article 

must meet for approval;

    (2) The detailed technical requirements for the tests that must be 

performed for approval; and

    (3) The necessary data that must be submitted to the Government in 

the first article approval test report.

    (b) Provide, in the circumstance where the Government is to be 

responsible for the first article approval testing--

    (1) The performance or other characteristics that the first article 

must meet for approval; and

    (2) The tests to which the first article will be subjected for 

approval.

    (c) Inform offerors that the requirement may be waived when supplies 

identical or similar to those called for have previously been delivered 

by the offeror and accepted by the Government (see 52.209-3(h) and 

52.209-4(i);

    (d) Permit the submission of alternative offers, one including 

testing and approval and the other excluding testing and approval (if 

eligible under 9.306(c));

    (e) State clearly the first article's relationship to the contract 

quantity (see paragraph (e) of the clause at 52.209-3, First Article 

Approval--Contractor Testing, or 52.209-4, First Article Approval--

Government Testing);

    (f) Contain a delivery schedule for the production quantity (see 

11.404). The delivery schedule may--

    (1) Be the same whether or not testing and approval is waived; or

    (2) Provide for earlier delivery when testing and approval is waived 

and the Government desires earlier delivery. In the latter case, any 

resulting difference in delivery schedules shall not be a factor in 

evaluation for award. The clause at 52.209-4, First Article Approval--



[[Page 159]]



Government Testing, shall contain the delivery schedule for the first 

article;

    (g) Provide for the submission of contract numbers, if any, to 

document the offeror's eligibility under 9.306(c);

    (h) State whether the approved first article will serve as a 

manufacturing standard; and

    (i) Include, when the Government is responsible for first article 

testing, the Government's estimated testing costs as a factor for use in 

evaluating offers (when appropriate).

    (j) Inform offerors that the prices for first articles and first 

article tests in relation to production quantities shall not be 

materially unbalanced (see 15.404-1(g)) if first article test items or 

tests are to be separately priced.



[48 FR 42142, Sept. 19, 1983, as amended at 54 FR 34753, Aug. 21, 1989; 

55 FR 25527, June 21, 1990; 60 FR 48237, Sept. 18, 1995; 62 FR 51270, 

Sept. 30, 1997]