Sec. 19.61  Termination.



    (a) Awards may be terminated in whole or in part only if the 

conditions in paragraph (a) (1), (2) or (3) of this section apply.

    (1) By the Federal awarding agency, if a recipient materially fails 

to comply with the terms and conditions of an award.

    (2) By the Federal awarding agency with the consent of the 

recipient, in which case the two parties shall agree upon the 

termination conditions, including the effective date and, in the case of 

partial termination, the portion to be terminated.

    (3) By the recipient upon sending to the Federal awarding agency 

written notification setting forth the reasons for such termination, the 

effective date, and, in the case of partial termination, the portion to 

be terminated. However, if the Federal awarding agency determines in the 

case of partial termination that the reduced or modified portion of the 

grant will not accomplish the purposes for which the grant was made, it 

may terminate the grant in its entirety under either paragraph (a) (1) 

or (2) of this section.

    (b) If costs are allowed under an award, the responsibilities of the 

recipient referred to in Sec. 19.71(a), including those for property 

management as applicable, shall be considered in the termination of the 

award, and provision shall be made for continuing responsibilities of 

the recipient after termination, as appropriate.