[Code of Federal Regulations]

[Title 23, Volume 1]

[Revised as of April 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 23CFR630.1010]



[Page 145-149]

 

                           TITLE 23--HIGHWAYS

 

 CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION

 

PART 630_PRECONSTRUCTION PROCEDURES--Table of Contents

 

        Subpart J_Traffic Safety in Highway and Street Work Zones

 

Sec.  630.1010  Contents of the agency procedures.



    The agency's procedures shall include, but not necessarily be 

limited to the following:

    (a) Traffic control plan (TCP). (1) A traffic control plan is a plan 

for handling traffic through a specific highway or street work zone or 

project. These plans may range in scope from a very detailed TCP 

designed solely for a specific project, to a reference to standard 

plans, a section of the MUTCD, or a standard highway agency manual. The 

degree of detail in the TCP will depend on the project complexity and 

traffic interference with construction activity.

    (2) Traffic control plans shall be developed for all projects and be 

included in plans, specifications, and estimates (P.S. & E.'s) and shall 

be consistent with part VI of the MUTCD.

    (3) The scope of the TCP should be determined during planning and 

design phases of a project.

    (4) Provisions may be made to permit contractors to develop their 

own TCP's and use them if the highway agency and FHWA find that these 

plans are as good as or better than those provided in the P.S. & E.

    (5)(i) Two-lane, two-way operation on one roadway of a normally 

divided highway (TLTWO) shall be used only after careful consideration 

of other available methods of traffic control. Where the TLTWO is used, 

the TCP shall include provisions for the separation of opposing traffic 

except:

    (A) Where the TLTWO is located on an urban type street or arterial 

where operating speeds are low;

    (B) Where drivers entering the TLTWO can see the transition back to 

normal one-way operation on each roadway; or

    (C) Where FHWA approves nonuse of separation devices based on 

unusual circumstances.

    (ii) Center line striping, raised pavement markers, and 

complementary signing, either alone or in combination, are not 

considered acceptable for separation purposes.

    (b) Responsible person. The highway agency shall designate a 

qualified person at the project level who will have the primary 

responsibility and sufficient authority for assuring that the TCP and 

other safety aspects of the contract are effectively administered. While 

the project or resident engineer may have this responsibility, on large 

complex projects another person should be assigned at the project level 

to handle traffic control on a full-time basis.

    (c) Pay items. The P.S. & E. should include unit pay items for 

providing, installing, moving, replacing, maintaining, and cleaning 

traffic control devices required by the TCP. Suitable force account 

procedures may be utilized for traffic control items. Lump-sum method of 

payment should be used only to cover very small projects, projects of 

short duration, contingency, and general items. Payment for traffic 

control items as incidental to



[[Page 146]]



other items of work should be discouraged.

    (d) Training. All persons responsible for the development, design, 

implementation, and inspection of traffic control shall be adequately 

trained.

    (e) Process review and evaluation. (1) A review team consisting of 

appropriate highway agency personnel shall annually review randomly 

selected projects throughout its jurisdiction for the purpose of 

assessing the effectiveness of its procedures. The agency may elect to 

include an FHWA representative as a member of the team. The results of 

this review are to be forwarded to the FHWA Division Administrator for 

his review and approval of the highway agency's annual traffic safety 

effort.

    (2) Construction zone accidents and accident data shall be analyzed 

and used to continually correct deficiencies which are found to exist on 

individual projects, and to improve the content of future traffic 

control plans.



[43 FR 47140, Oct. 12, 1978, as amended at 47 FR 21780, May 20, 1982]



    Effective Date Note: At 69 FR 54569, Sept. 9, 2004, subpart J of 

part 630 was revised, effective Oct. 12, 2007. For the convenience of 

the user, the revised text is set forth as follows:



                 Subpart J_Work Zone Safety and Mobility



Sec.  630.1002  Purpose.



    Work zones directly impact the safety and mobility of road users and 

highway workers. These safety and mobility impacts are exacerbated by an 

aging highway infrastructure and growing congestion in many locations. 

Addressing these safety and mobility issues requires considerations that 

start early in project development and continue through project 

completion. Part 6 of the Manual On Uniform Traffic Control Devices 

(MUTCD) \1\ sets forth basic principles and prescribes standards for the 

design, application, installation, and maintenance of traffic control 

devices for highway and street construction, maintenance operation, and 

utility work. In addition to the provisions in the MUTCD, there are 

other actions that could be taken to further help mitigate the safety 

and mobility impacts of work zones. This subpart establishes 

requirements and provides guidance for systematically addressing the 

safety and mobility impacts of work zones, and developing strategies to 

help manage these impacts on all Federal-aid highway projects.

---------------------------------------------------------------------------



    \1\ The MUTCD is approved by the FHWA and recognized as the national 

standard for traffic control on all public roads. It is incorporated by 

reference into the Code of Federal Regulations at 23 CFR part 655. It is 

available on the FHWA's Web site at http://mutcd.fhwa.dot.gov and is 

available for inspection and copying at the FHWA Washington, DC 

Headquarters and all FHWA Division Offices as prescribed at 49 CFR part 

7.

---------------------------------------------------------------------------



Sec.  630.1004  Definitions and explanation of terms.



    As used in this subpart:

    Highway workers include, but are not limited to, personnel of the 

contractor, subcontractor, DOT, utilities, and law enforcement, 

performing work within the right-of-way of a transportation facility.

    Mobility is the ability to move from place to place and is 

significantly dependent on the availability of transportation facilities 

and on system operating conditions. With specific reference to work 

zones, mobility pertains to moving road users efficiently through or 

around a work zone area with a minimum delay compared to baseline travel 

when no work zone is present, while not compromising the safety of 

highway workers or road users. The commonly used performance measures 

for the assessment of mobility include delay, speed, travel time and 

queue lengths.

    Safety is a representation of the level of exposure to potential 

hazards for users of transportation facilities and highway workers. With 

specific reference to work zones, safety refers to minimizing potential 

hazards to road users in the vicinity of a work zone and highway workers 

at the work zone interface with traffic. The commonly used measures for 

highway safety are the number of crashes or the consequences of crashes 

(fatalities and injuries) at a given location or along a section of 

highway during a period of time. Highway worker safety in work zones 

refers to the safety of workers at the work zone interface with traffic 

and the impacts of the work zone design on worker safety. The number of 

worker fatalities and injuries at a given location or along a section of 

highway, during a period of time are commonly used measures for highway 

worker safety.

    Work zone \2\ is an area of a highway with construction, 

maintenance, or utility work activities. A work zone is typically marked 

by signs, channelizing devices, barriers, pavement markings, and/or work 

vehicles. It extends from the first warning sign or high-intensity 

rotating, flashing, oscillating, or strobe lights on a vehicle to the 

END ROAD



[[Page 147]]



WORK sign or the last temporary traffic control (TTC) device.

---------------------------------------------------------------------------



    \2\ MUTCD, Part 6, ``Temporary Traffic Control,'' Section 6C.02, 

``Temporary Traffic Control Zones.''

---------------------------------------------------------------------------



    Work zone crash \3\ means a traffic crash in which the first harmful 

event occurs within the boundaries of a work zone or on an approach to 

or exit from a work zone, resulting from an activity, behavior, or 

control related to the movement of the traffic units through the work 

zone. This includes crashes occurring on approach to, exiting from or 

adjacent to work zones that are related to the work zone.

---------------------------------------------------------------------------



    \3\ ``Model Minimum Uniform Crash Criteria Guideline'' (MMUCC), 2d 

Ed. (Electronic), 2003, produced by National Center for Statistics and 

Analysis, National Highway Traffic Safety Administration (NHTSA). 

Telephone 1-(800)-934-8517. Available at the URL: http://www-

nrd.nhtsa.dot.gov. The NHTSA, the FHWA, the Federal Motor Carrier Safety 

Administration (FMCSA), and the Governors Highway Safety Association 

(GHSA) sponsored the development of the MMUCC Guideline which recommends 

voluntary implementation of the 111 MMUCC data elements and serves as a 

reporting threshold that includes all persons (injured and uninjured) in 

crashes statewide involving death, personal injury, or property damage 

of $1,000 or more. The Guideline is a tool to strengthen existing State 

crash data systems.

---------------------------------------------------------------------------



    Work zone impacts refer to work zone-induced deviations from the 

normal range of transportation system safety and mobility. The extent of 

the work zone impacts may vary based on factors such as, road 

classification, area type (urban, suburban, and rural), traffic and 

travel characteristics, type of work being performed, time of day/night, 

and complexity of the project. These impacts may extend beyond the 

physical location of the work zone itself, and may occur on the roadway 

on which the work is being performed, as well as other highway 

corridors, other modes of transportation, and/or the regional 

transportation network.



Sec.  630.1006  Work zone safety and mobility policy.



    Each State shall implement a policy for the systematic consideration 

and management of work zone impacts on all Federal-aid highway projects. 

This policy shall address work zone impacts throughout the various 

stages of the project development and implementation process. This 

policy may take the form of processes, procedures, and/or guidance, and 

may vary based on the characteristics and expected work zone impacts of 

individual projects or classes of projects. The States should institute 

this policy using a multi-disciplinary team and in partnership with the 

FHWA. The States are encouraged to implement this policy for non-

Federal-aid projects as well.



Sec.  630.1008  State-level processes and procedures.



    (a) This section consists of State-level processes and procedures 

for States to implement and sustain their respective work zone safety 

and mobility policies. State-level processes and procedures, data and 

information resources, training, and periodic evaluation enable a 

systematic approach for addressing and managing the safety and mobility 

impacts of work zones.

    (b) Work zone assessment and management procedures. States should 

develop and implement systematic procedures to assess work zone impacts 

in project development, and to manage safety and mobility during project 

implementation. The scope of these procedures shall be based on the 

project characteristics.

    (c) Work zone data. States shall use field observations, available 

work zone crash data, and operational information to manage work zone 

impacts for specific projects during implementation. States shall 

continually pursue improvement of work zone safety and mobility by 

analyzing work zone crash and operational data from multiple projects to 

improve State processes and procedures. States should maintain elements 

of the data and information resources that are necessary to support 

these activities.

    (d) Training. States shall require that personnel involved in the 

development, design, implementation, operation, inspection, and 

enforcement of work zone related transportation management and traffic 

control be trained, appropriate to the job decisions each individual is 

required to make. States shall require periodic training updates that 

reflect changing industry practices and State processes and procedures.

    (e) Process review. In order to assess the effectiveness of work 

zone safety and mobility procedures, the States shall perform a process 

review at least every two years. This review may include the evaluation 

of work zone data at the State level, and/or review of randomly selected 

projects throughout their jurisdictions. Appropriate personnel who 

represent the project development stages and the different offices 

within the State, and the FHWA should participate in this review. Other 

non-State stakeholders may also be included in this review, as 

appropriate. The results of the review are intended to lead to 

improvements in work zone processes and procedures, data and information 

resources, and training programs so as to enhance efforts to address 

safety and mobility on current and future projects.



Sec.  630.1010  Significant projects.



    (a) A significant project is one that, alone or in combination with 

other concurrent projects nearby is anticipated to cause sustained work 

zone impacts (as defined in



[[Page 148]]



Sec.  630.1004) that are greater than what is considered tolerable based 

on State policy and/or engineering judgment.

    (b) The applicability of the provisions in Sec. Sec.  630.1012(b)(2) 

and 630.1012(b)(3) is dependent upon whether a project is determined to 

be significant. The State shall identify upcoming projects that are 

expected to be significant. This identification of significant projects 

should be done as early as possible in the project delivery and 

development process, and in cooperation with the FHWA. The State's work 

zone policy provisions, the project's characteristics, and the magnitude 

and extent of the anticipated work zone impacts should be considered 

when determining if a project is significant or not.

    (c) All Interstate system projects within the boundaries of a 

designated Transportation Management Area (TMA) that occupy a location 

for more than three days with either intermittent or continuous lane 

closures shall be considered as significant projects.

    (d) For an Interstate system project or categories of Interstate 

system projects that are classified as significant through the 

application of the provisions in Sec.  630.1010(c), but in the judgment 

of the State they do not cause sustained work zone impacts, the State 

may request from the FHWA, an exception to Sec. Sec.  630.1012(b)(2) and 

630.1012(b)(3). Exceptions to these provisions may be granted by the 

FHWA based on the State's ability to show that the specific Interstate 

system project or categories of Interstate system projects do not have 

sustained work zone impacts.



Sec.  630.1012  Project-level procedures.



    (a) This section provides guidance and establishes procedures for 

States to manage the work zone impacts of individual projects.

    (b) Transportation Management Plan (TMP). A TMP consists of 

strategies to manage the work zone impacts of a project. Its scope, 

content, and degree of detail may vary based upon the State's work zone 

policy, and the State's understanding of the expected work zone impacts 

of the project. For significant projects (as defined in Sec.  630.1010), 

the State shall develop a TMP that consists of a Temporary Traffic 

Control (TTC) plan and addresses both Transportation Operations (TO) and 

Public Information (PI) components. For individual projects or classes 

of projects that the State determines to have less than significant work 

zone impacts, the TMP may consist only of a TTC plan. States are 

encouraged to consider TO and PI issues for all projects.

    (1) A TTC plan describes TTC measures to be used for facilitating 

road users through a work zone or an incident area. The TTC plan plays a 

vital role in providing continuity of reasonably safe and efficient road 

user flow and highway worker safety when a work zone, incident, or other 

event temporarily disrupts normal road user flow. The TTC plan shall be 

consistent with the provisions under Part 6 of the MUTCD and with the 

work zone hardware recommendations in Chapter 9 of the American 

Association of State Highway and Transportation Officials (AASHTO) 

Roadside Design Guide. Chapter 9 of the AASHTO Roadside Design Guide: 

``Traffic Barriers, Traffic Control Devices, and Other Safety Features 

for Work Zones'' 2002, is incorporated by reference in accordance with 5 

U.S.C. 552(a) and 1 CFR part 51 and is on file at the National Archives 

and Record Administration (NARA). For information on the availability of 

this material at NARA call (202) 741-6030, or go to http://

www.archives.gov/federal--register/code--of--federal--regulations/ibr--

locations.html. The entire document is available for purchase from the 

American Association of State Highway and Transportation Officials 

(AASHTO), 444 North Capitol Street, NW., Suite 249, Washington, DC 20001 

or at the URL: http://www.aashto.org/bookstore. It is available for 

inspection from the FHWA Washington Headquarters and all Division 

Offices as listed in 49 CFR Part 7. In developing and implementing the 

TTC plan, pre-existing roadside safety hardware shall be maintained at 

an equivalent or better level than existed prior to project 

implementation. The scope of the TTC plan is determined by the project 

characteristics, and the traffic safety and control requirements 

identified by the State for that project. The TTC plan shall either be a 

reference to specific TTC elements in the MUTCD, approved standard TTC 

plans, State transportation department TTC manual, or be designed 

specifically for the project.

    (2) The TO component of the TMP shall include the identification of 

strategies that will be used to mitigate impacts of the work zone on the 

operation and management of the transportation system within the work 

zone impact area. Typical TO strategies may include, but are not limited 

to, demand management, corridor/network management, safety management 

and enforcement, and work zone traffic management. The scope of the TO 

component should be determined by the project characteristics, and the 

transportation operations and safety strategies identified by the State.

    (3) The PI component of the TMP shall include communications 

strategies that seek to inform affected road users, the general public, 

area residences and businesses, and appropriate public entities about 

the project, the expected work zone impacts, and the changing conditions 

on the project. This may include traveler information strategies. The 

scope of the PI component should be determined by the project 

characteristics and



[[Page 149]]



the public information and outreach strategies identified by the State. 

Public information should be provided through methods best suited for 

the project, and may include, but not be limited to, information on the 

project characteristics, expected impacts, closure details, and commuter 

alternatives.

    (4) States should develop and implement the TMP in sustained 

consultation with stakeholders (e.g., other transportation agencies, 

railroad agencies/operators, transit providers, freight movers, utility 

suppliers, police, fire, emergency medical services, schools, business 

communities, and regional transportation management centers).

    (c) The Plans, Specifications, and Estimates (PS&Es) shall include 

either a TMP or provisions for contractors to develop a TMP at the most 

appropriate project phase as applicable to the State's chosen 

contracting methodology for the project. A contractor developed TMP 

shall be subject to the approval of the State, and shall not be 

implemented before it is approved by the State.

    (d) The PS&Es shall include appropriate pay item provisions for 

implementing the TMP, either through method or performance based 

specifications.

    (1) For method-based specifications individual pay items, lump sum 

payment, or a combination thereof may be used.

    (2) For performance based specifications, applicable performance 

criteria and standards may be used (e.g., safety performance criteria 

such as number of crashes within the work zone; mobility performance 

criteria such as travel time through the work zone, delay, queue length, 

traffic volume; incident response and clearance criteria; work duration 

criteria).

    (e) Responsible persons. The State and the contractor shall each 

designate a trained person, as specified in Sec.  630.1008(d), at the 

project level who has the primary responsibility and sufficient 

authority for implementing the TMP and other safety and mobility aspects 

of the project.



Sec.  630.1014  Implementation.



    Each State shall work in partnership with the FHWA in the 

implementation of its policies and procedures to improve work zone 

safety and mobility. At a minimum, this shall involve an FHWA review of 

conformance of the State's policies and procedures with this regulation 

and reassessment of the State's implementation of its procedures at 

appropriate intervals. Each State is encouraged to address 

implementation of this regulation in its stewardship agreement with the 

FHWA.



Sec.  630.1016  Compliance date.



    States shall comply with all the provisions of this rule no later 

than October 12, 2007. For projects that are in the later stages of 

development at or about the compliance date, and if it is determined 

that the delivery of those projects would be significantly impacted as a 

result of this rule's provisions, States may request variances for those 

projects from the FHWA, on a project-by-project basis.