[Code of Federal Regulations]

[Title 23, Volume 1]

[Revised as of April 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 23CFR630.402]



[Page 143]

 

                           TITLE 23--HIGHWAYS

 

 CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION

 

PART 630_PRECONSTRUCTION PROCEDURES--Table of Contents

 

                       Subpart D_Geodetic Markers

 

Sec.  630.402  Policy.



    (a) Geodetic surveys along Federal-aid highway routes may be 

programmed as Federal-aid highway projects.

    (b) All geodetic survey work performed as a Federal-aid highway 

project will conform to National Ocean Survey (NOS) specifications. NOS 

will, as the representative of FHWA, be responsible for the inspection 

and verification of the work to ascertain that the specifications for 

the work have been met. Final project acceptance by FHWA will be 

predicated on a finding of acceptability by NOS.