Sec.  901.30  Indicator #5, annual inspection of units and systems.



    This indicator examines the percentage of units that a PHA inspects 

on an annual basis in order to determine short-term maintenance needs 

and long-term modernization needs. Implicit in this indicator is the 

adequacy of the PHA's inspection program in terms of the quality of a 

PHA's inspections, and how a PHA tracks both inspections and needed 

repairs. All occupied units are required to be inspected. This indicator 

has a weight of x1.

    (a) Units in the following categories are exempted and not included 

in the calculation of the total number of units, and the number and 

percentage of units inspected. Systems that are a part of individual 

dwelling units that are exempted, or a part of a building where all of 

the dwelling units in the building are exempted, are also exempted from 

the calculation of this indicator:

    (1) Occupied units where the PHA has made two documented attempts to 

inspect, but only if the PHA can document that appropriate legal action 

(up to and including eviction of the legal or illegal occupant(s)), has 

been taken under provisions of the lease to ensure that the unit can be 

subsequently inspected.

    (2) Units vacant for the full immediate past fiscal year for the 

following reasons, as defined at Sec.  901.5:

    (i) Vacant units undergoing modernization; and

    (ii) Vacant units that are documented to be uninhabitable for 

reasons beyond a PHA's control due to:

    (A) High/unsafe levels of hazardous/toxic materials;

    (B) By order of the local health department or a directive of the 

Environmental Protection Agency;

    (C) Natural disasters; and

    (D) Units kept vacant because they became structurally unsound.

    (b) Component 1, annual inspection of units. This component 

refers to an inspection using either the local housing and/or occupancy 

code, or HUD HQS if there is no local code or the local code is less 

stringent that HQS. This component has a weight of x1.



[[Page 243]]



    (1) Grade A: The PHA inspected 100% of its units and, if repairs 

were necessary for local code or HQS compliance, either completed the 

repairs during the inspection; issued work orders for the repairs; or 

referred similar work items to the current year's modernization program, 

or to next year's modernization program if there are less than three 

months remaining before the end of the PHA fiscal year when the 

inspection was completed.

    (2) Grade B: The PHA inspected less than 100% but at least 97% of 

its units and, if repairs were necessary for local code or HQS 

compliance, either completed the repairs during the inspection; issued 

work orders for the repairs; or referred similar work items to the 

current year's modernization program, or to next year's modernization 

program if there are less than three months remaining before the end of 

the PHA fiscal year when the inspection was completed.

    (3) Grade C: The PHA inspected less than 97% but at least 95% of its 

units and, if repairs were necessary for local code or HQS compliance, 

either completed the repairs during the inspection; issued work orders 

for the repairs; or referred similar work items to the current year's 

modernization program, or to next year's modernization program if there 

are less than three months remaining before the end of the PHA fiscal 

year when the inspection was completed.

    (4) Grade D: The PHA inspected less than 95% but at least 93% of its 

units and, if repairs were necessary for local code or HQS compliance, 

either completed the repairs during the inspection; issued work orders 

for the repairs; or referred similar work items to the current year's 

modernization program, or to next year's modernization program if there 

are less than three months remaining before the end of the PHA fiscal 

year when the inspection was completed.

    (5) Grade E: The PHA inspected less than 93% but at least 90% of its 

units and, if repairs were necessary for local code or HQS compliance, 

either completed the repairs during the inspection; issued work orders 

for the repairs; or referred similar work items to the current year's 

modernization program, or to next year's modernization program if there 

are less than three months remaining before the end of the PHA fiscal 

year when the inspection was completed.

    (6) Grade F: The PHA has failed to inspect at least 90% of its 

units; or failed to correct deficiencies during the inspection or issue 

work orders for the repairs; or failed to refer similar work items to 

the current year's modernization program, or to next year's 

modernization program if there are less than three months remaining 

before the end of the PHA fiscal year when the inspection was completed.

    (c) Component 2, annual inspection of systems. This 

component examines the inspection of buildings and sites according to 

the PHA's maintenance plan, including performing the required 

maintenance on structures and systems in accordance with manufacturer's 

specifications and established local/PHA standards, or issuing work 

orders for maintenance/repairs, or including identified deficiencies in 

this year's modernization program, or in next year's modernization 

program if there are less than three months remaining before the end of 

the PHA fiscal year when the inspection was performed. This component 

has a weight of x1.

    (1) Grade A: The PHA inspected all major systems at 100% of its 

buildings and sites, according to its maintenance plan. The inspection 

included performing the required maintenance on structures and systems 

in accordance with manufacturer's specifications and established local/

PHA standards, or issuing work orders for maintenance/repairs, or 

including identified deficiencies in the current year's modernization 

program, or in next year's modernization program if there are less than 

three months remaining before the end of the PHA fiscal year when the 

inspection was performed.

    (2) Grade B: The PHA inspected all major systems of at least a 

minimum of 90% but less than 100% of its buildings and sites, according 

to its maintenance plan. The inspection included performing the required 

maintenance



[[Page 244]]



on structures and systems in accordance with manufacturer's 

specifications and established local/PHA standards, or issuing work 

orders for maintenance/ repairs, or including identified deficiencies in 

the current year's modernization program, or in next year's 

modernization program if there are less than three months remaining 

before the end of the PHA fiscal year when the inspection was performed.

    (3) Grade C: The PHA inspected all major systems of at least a 

minimum of 80% but less than 90% of its buildings and sites, according 

to its maintenance plan. The inspection included performing the required 

maintenance on structures and systems in accordance with manufacturer's 

specifications and established local/PHA standards, or issuing work 

orders for maintenance/ repairs, or including identified deficiencies in 

the current year's modernization program, or in next year's 

modernization program if there are less than three months remaining 

before the end of the PHA fiscal year when the inspection was performed.

    (4) Grade D: The PHA inspected all major systems of at least a 

minimum of 70% but less than 80% of its buildings and sites, according 

to its maintenance plan. The inspection included performing the required 

maintenance on structures and systems in accordance with manufacturer's 

specifications and established local/PHA standards, or issuing work 

orders for maintenance/ repairs, or including identified deficiencies in 

the current year's modernization program, or in next year's 

modernization program if there are less than three months remaining 

before the end of the PHA fiscal year when the inspection was performed.

    (5) Grade E: The PHA inspected all major systems of at least a 

minimum of 60% but less than 70% of its buildings and sites, according 

to its maintenance plan. The inspection included performing the required 

maintenance on structures and systems in accordance with manufacturer's 

specifications and established local/PHA standards, or issuing work 

orders for maintenance/ repairs, or including identified deficiencies in 

the current year's modernization program, or in next year's 

modernization program if there are less than three months remaining 

before the end of the PHA fiscal year when the inspection was performed.

    (6) Grade F: The PHA failed to inspect all major systems of at least 

60% of its buildings and sites and perform the required maintenance on 

these systems in accordance with manufacturers specifications and 

established local/PHA standards, or did not issue work orders for 

maintenance/repairs, or did not include identified deficiencies in the 

current year's modernization program, or in next year's modernization 

program if there are less than three months remaining before the end of 

the PHA fiscal year when the inspection was performed.