Sec.  983.156  PHA acceptance of completed units.



    (a) PHA determination of completion. When the PHA has received owner 

notice that the housing is completed:

    (1) The PHA must inspect to determine if the housing has been 

completed in accordance with the Agreement, including compliance with 

the HQS and any additional requirement imposed by the PHA under the 

Agreement.

    (2) The PHA must determine if the owner has submitted all required 

evidence of completion.

    (3) If the work has not been completed in accordance with the 

Agreement, the PHA must not enter into the HAP contract.

    (b) Execution of HAP contract. If the PHA determines that the 

housing has been completed in accordance with the Agreement and that the 

owner has submitted all required evidence of completion, the PHA must 

submit the HAP contract for execution by the owner and must then execute 

the HAP contract.