Sec. 1260.25  Change in principal investigator or scope.



                Change in Principal Investigator or Scope



                              October 2000



    The following guidance is provided as an amplification to prior 

approval requirements set forth at Sec. 1260.125(c):

    (a) The Recipient shall obtain the approval of the NASA Grant 

Officer for a change of



[[Page 286]]



the Principal Investigator, or for a significant absence of the 

Principal Investigator from the project, defined as a three month 

absence from the program or a 25 percent reduction in time devoted to 

the project. Significantly reduced availability of the services of the 

Principal Investigator(s) named in the grant instrument could be grounds 

for termination, unless alternative arrangements are made and approved 

in writing by the Grant Officer.

    (b) Prior written approval is required from NASA if there is to be a 

significant change in the objective or scope.