Sec. 151.51  Performance of construction work: Sponsor force account.



    (a) Before undertaking any force account construction work, the 

sponsor (or any public agency acting as agent for the sponsor) must 

obtain the written consent of the Administrator through the Area 

Manager. In requesting that consent, the sponsor must submit--

    (1) Adequate plans and specifications showing the nature and extent 

of the construction work to be performed under that force account;

    (2) A schedule of the proposed construction and of the construction 

equipment that will be available for the project;

    (3) Assurance that adequate labor, material, equipment, engineering 

personnel, as well as supervisory and inspection personnel as required 

by Sec. 151.45(f), will be provided; and

    (4) A detailed estimate of the cost of the work, broken down for 

each class of costs involved, such as labor, materials, rental of 

equipment, and other pertinent items of cost.

    (b) [Reserved]



[Doc. No. 1329, 27 FR 12351, Dec. 13, 1962, as amended by Amdt. 151-17, 

31 FR 16525, Dec. 28, 1966; Amdt. 151-31, 34 FR 4885, Mar. 6, 1969]