[Code of Federal Regulations]

[Title 14, Volume 3]

[Revised as of January 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 14CFR151.75]



[Page 111]

 

                     TITLE 14--AERONAUTICS AND SPACE

 

CHAPTER I--FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION 

                               (CONTINUED)

 

PART 151_FEDERAL AID TO AIRPORTS--Table of Contents

 

                 Subpart C_Project Programming Standards

 

Sec. 151.75  Preparation of site.



    (a) Grading, drainage, and associated items of site preparation are 

eligible for inclusion in a project, but only with respect to one 

landing strip at any airport, unless the airport qualifies for more than 

one runway, based on traffic volume or wind conditions (as outlined in 

Sec. 151.77) and the overall site preparation required for development 

in accordance with the airport layout plan. The complete clearance of 

runway clear zone areas is desirable, but, as a minimum, all 

obstructions as determined by Sec. 77.23 as applied to Sec. 77.27 (b) 

and (c) of this chapter must be removed. Grading in runway clear zones 

is eligible only to remove terrain that is an obstruction. The clear 

zone is not a graded overrun area. Specific site preparation for an 

airport terminal building is eligible on the same basis as the building 

itself. The site preparation cost is prorated based on eligible and 

ineligible building space. Appendix B of this part sets forth typical 

eligible and ineligible items of site preparation as covered by this 

section.

    (b) For the purposes of this section, eligible drainage work off the 

airport site includes drainage outfalls, drainage disposal, and 

interception ditches. If there is damage to adjacent property, its 

correction is an eligible item for inclusion in the project.



[Doc. No. 1329, 27 FR 12357, Dec. 13, 1962, as amended by Amdt. 151-7, 

30 FR 7484, June 8, 1965; Amdt. 151-8, 30 FR 8040, June 23, 1965]