[Code of Federal Regulations]

[Title 14, Volume 3]

[Revised as of January 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 14CFR152.113]



[Page 133-134]

 

                     TITLE 14--AERONAUTICS AND SPACE

 

CHAPTER I--FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION 

                               (CONTINUED)

 

PART 152_AIRPORT AID PROGRAM--Table of Contents

 

      Subpart B_Eligibility Requirements and Application Procedures

 

Sec. 152.113  Application requirements: Airport planning.



    (a) Application for Federal assistance. An eligible sponsor or 

planning agency that desires to obtain Federal aid for eligible airport 

master planning or airport system planning must submit an application 

for Federal assistance, on a form and in a manner prescribed by the 

Administrator, to the appropriate FAA Airports District Office or 

Airports Field Office having jurisdiction over the area where the 

sponsor or planning agency is located or, where there is no such office, 

the Regional Office having that jurisdiction.

    (b) Unless otherwise authorized by the Administrator, the 

application required by paragraph (a) of this section must be 

accompanied by the following:

    (1) Any comments or statements required by appendix E, Procedures 

Implementing Office of Management and Budget Circular A-95, to this 

part.

    (2) Budget (project costs) information subdivided into the following 

functions, as appropriate, and the basis for computation of these costs:

    (i) Third party contracts.

    (ii) Sponsor force account costs.

    (iii) Administrative costs.

    (3) A program narrative describing the proposed planning project 

including--

    (i) The objective;

    (ii) The results and benefits expected;

    (iii) A Work Statement including--

    (A) A detailed description of each work element;

    (B) A list of each organization, consultant, and key individual who 

will work on the planning project, and the nature of the contribution of 

each; and

    (C) A proposed schedule of work accomplishment; and

    (iv) The geographic location of the airport or the boundaries of the 

planning area.

    (4) If the sponsor proposes to accomplish the project with its own 

forces or those of another public or planning agency--

    (i) An assurance that adequate, competent personnel are available to 

satisfactorily accomplish the proposed planning project, and

    (ii) A description of the qualifications of the key personnel.

    (5) If cosponsors are not willing to assume, jointly, and severally, 

the obligations imposed on them by this part and the grant agreement, a 

statement satisfactory to the Administrator indicating--

    (i) The responsibilities of each sponsor with respect to the 

accomplishment of the proposed project;

    (ii) The obligations each will assume to the United States; and

    (iii) The name of the sponsor or sponsors who will accept, receipt 

for, and disburse grant payments.

    (6) The assurances on Civil Rights required by Sec. 21.7 of the 

Regulations of the Office of the Secretary of Transportation (49 CFR 

21.7).

    (7) The applicable assurances required by appendix D of this part.

    (c) Additional documentation. The Administrator may request 

additional documentation as needed to support a



[[Page 134]]



master plan or system plan, or to comply with other Federal and local 

requirements as they pertain to the requested plan.



(Secs. 303, 307, 308, 312, and 313, Federal Aviation Act of 1958 (49 

U.S.C. 1344, 1348, 1349, 1353, and 1354); sec. 6(c), Dept. of 

Transportation Act (49 U.S.C. 1655(c)); Airport and Airway Development 

Act of 1970, as amended (49 U.S.C. 1701 et seq.); sec. 1.47(f)(1), 

Regulations of the Office of the Secretary of Transportation (49 CFR 

1.47(1)); OMB Circular A-95, Revised (41 FR 2052; Jan. 13, 1976))



[Doc. No. 19430, 45 FR 34784, May 22, 1980, as amended by Amdt. 152-13, 

46 FR 30809, June 11, 1981]