Sec. 2301.24  Final Federal payment.



    If the total allowable, allocable, and reasonable costs incurred in 

completing the planning or construction project are less than the total 

project award amount, the Agency shall reduce the amount of the final 

Federal share on a pro rata basis. If, however, the actual costs 

incurred in completing the project are more than the estimated total 

project costs, in no case will the final Federal funds paid exceed the 

grant award.