[Code of Federal Regulations]

[Title 32, Volume 1]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 32CFR32.25]



[Page 158-160]

 

                       TITLE 32--NATIONAL DEFENSE

 

              CHAPTER I--OFFICE OF THE SECRETARY OF DEFENSE

 

PART 32_ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH 

INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT 

ORGANIZATIONS--Table of Contents

 

                    Subpart C_Post-Award Requirements

 

Sec.  32.25  Revision of budget and program plans.



    (a) The budget plan is the financial expression of the project or 

program as approved during the award process. It may include either the 

sum of the Federal and non-Federal shares, or only the Federal share, 

depending upon DoD Component requirements. It shall be related to 

performance for program evaluation purposes whenever appropriate.

    (b) Recipients are required to report deviations from budget and 

program



[[Page 159]]



plans, and request prior approvals for budget and program plan 

revisions, in accordance with this section.

    (c) For nonconstruction awards, recipients shall request prior 

approvals from the cognizant grants officer for one or more of the 

following program or budget related reasons.

    (1) Change in the scope or the objective of the project or program 

(even if there is no associated budget revision requiring prior written 

approval).

    (2) Change in a key person specified in the application or award 

document.

    (3) The absence for more than three months, or a 25 percent 

reduction in time devoted to the project, by the approved project 

director or principal investigator.

    (4) The need for additional Federal funding.

    (5) The transfer of amounts budgeted for indirect costs to absorb 

increases in direct costs, or vice versa, if approval is required by the 

DoD Component. DoD Components should require this prior approval only in 

exceptional circumstances. The requirement in each such case must be 

stated in the award document.

    (6) The inclusion, unless waived by the DoD Component, of costs that 

require prior approval in accordance with OMB Circular A-21,\5\ ``Cost 

Principles for Institutions of Higher Education,'' OMB Circular A-

122,\6\ ``Cost Principles for Non-Profit Organizations,'' or Appendix E 

to 45 CFR part 74, ``Principles for Determining Costs Applicable to 

Research and Development under Grants and Contracts with Hospitals,'' or 

48 CFR part 31, ``Contract Cost Principles and Procedures,'' as 

applicable. However, it should be noted that many of the prior approvals 

in these cost principles are appropriately waived only after 

consultation with the cognizant federal agency responsible for 

negotiating the recipient's indirect costs.

---------------------------------------------------------------------------



    \5\ See footnote 1 to Sec.  32.1(a).

    \6\ See footnote 1 to Sec.  32.1(a).

---------------------------------------------------------------------------



    (7) The transfer of funds allotted for training allowances (direct 

payment to trainees) to other categories of expense.

    (8) Unless described in the application and funded in the approved 

awards, the subaward, transfer or contracting out of any work under an 

award. This provision does not apply to the purchase of supplies, 

material, equipment or general support services.

    (9) If required by the DoD Component, the transfer of funds among 

direct cost categories that is described in paragraph (e) of this 

section.

    (d) (1) Except for requirements listed in paragraphs (c)(1) and 

(c)(4) of this section, OMB Circular A-110 authorizes DoD Components, at 

their option, to waive cost-related and administrative prior written 

approvals required by this part and OMB Circulars A-21 and A-122 (but 

see cautionary note at end of paragraph (c)(5) of this section).

    (2) The two prior approvals listed in paragraphs (d)(2)(i) and (ii) 

of this section are automatically waived unless the award document 

states otherwise. DoD Components should override this automatic waiver 

and require the prior approvals, especially for research awards, only in 

exceptional circumstances. Absent an override in the award terms and 

conditions, recipients need not obtain prior approvals before:

    (i) Incurring pre-award costs 90 calendar days prior to award 

(incurring pre-award costs more than 90 calendar days prior to award 

would still require the prior approval of the DoD Component). All pre-

award costs are incurred at the recipient's risk (i.e., the DoD 

Component is under no obligation to reimburse such costs if for any 

reason the recipient does not receive an award or if the award is less 

than anticipated and inadequate to cover such costs).

    (ii) Carrying forward unobligated balances to subsequent funding 

periods.

    (3) Under certain conditions, a DoD Component may authorize a 

recipient to initiate, without prior approval, a one-time, no-cost 

extension (i.e., an extension in the expiration date of an award that 

does not require additional Federal funds) for a period of up to twelve 

months, as long as the no-cost extension does not involve a change in 

the approved objectives or scope of the project. The conditions for 

waiving this prior approval requirement are that the DoD Component must:

    (i) Judge that the recipient's subsequently initiating a one-time, 

no-cost extension would not cause the DoD



[[Page 160]]



Component to fail to comply with DoD funding policies (for further 

information on the location of DoD funding policies, grants officers may 

refer to Appendix C to 32 CFR part 22).

    (ii) Require a recipient that wishes to initiate a one-time, no-cost 

extension to so notify the office that made the award at least 10 

calendar days before the original expiration date of the award.

    (e) The DoD Component may, at its option, restrict the transfer of 

funds among direct cost categories, functions and activities for awards 

in which the Federal share of the project exceeds $100,000 and the 

cumulative amount of such transfers exceeds or is expected to exceed 10 

percent of the total budget as last approved by the DoD Component. As a 

matter of DoD policy, requiring prior approvals for such transfers 

generally is not appropriate for grants to support research. No DoD 

Component shall permit a transfer that would cause any Federal 

appropriation or part thereof to be used for purposes other than those 

consistent with the original intent of the appropriation.

    (f) For construction awards, recipients shall request prior written 

approval promptly from grants officers for budget revisions whenever:

    (1) The revision results from changes in the scope or the objective 

of the project or program;

    (2) The need arises for additional Federal funds to complete the 

project; or

    (3) A revision is desired which involves specific costs for which 

prior written approval requirements may be imposed consistent with 

applicable OMB cost principles listed in Sec.  32.27.

    (g) When a DoD Component makes an award that provides support for 

both construction and nonconstruction work, the DoD Component may 

require the recipient to request prior approval from the grants officer 

before making any fund or budget transfers between the two types of work 

supported.

    (h) No other prior approval requirements for specific items may be 

imposed unless a deviation has been approved, in accordance with the 

deviation procedures in Sec.  32.4(c).

    (i) For both construction and nonconstruction awards, DoD Components 

shall require recipients to notify the grants officer in writing 

promptly whenever the amount of Federal authorized funds is expected to 

exceed the needs of the recipient for the project period by more than 

$5000 or five percent of the Federal award, whichever is greater. This 

notification shall not be required if an application for additional 

funding is submitted for a continuation award.

    (j) When requesting approval for budget revisions, recipients shall 

use the budget forms that were used in the application unless the grants 

officer indicates a letter of request suffices.

    (k) Within 30 calendar days from the date of receipt of the request 

for budget revisions, the grants officer shall review the request and 

notify the recipient whether the budget revisions have been approved. If 

the revision is still under consideration at the end of 30 calendar 

days, the grants officer shall inform the recipient in writing of the 

date when the recipient may expect the decision.