[Code of Federal Regulations]

[Title 33, Volume 3]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 33CFR222.6]



[Page 257-311]

 

                TITLE 33--NAVIGATION AND NAVIGABLE WATERS

 

 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 

                                 DEFENSE

 

PART 222_ENGINEERING AND DESIGN--Table of Contents

 

Sec.  222.6  National Program for Inspection of Non-Federal Dams.



    (a) Purpose. This regulation states objectives, assigns 

responsibilities and prescribes procedures for implementation of a 

National Program for Inspection of Non-Federal Dams.

    (b) Applicability. This regulation is applicable to all Divisions 

and Districts having Civil Works functions.

    (c) References. (1) The National Dam Inspection Act, Pub. L. 92-367, 

8 August 1972.

    (2) Freedom of Information Act, Pub. L. 87-487, 4 July 1967.

    (3) ER 500-1-1.

    (d) Authority. The National Dam Inspection Act, Public Law 92-367, 8 

August 1972 authorizes the Secretary of the Army, acting through the 

Chief of Engineers, to carry out a national program of inspection of 

non-Federal dams for the purpose of protecting human life and property.

    (e) Scope. The program provides for:

    (1) An update of the National Inventory of Dams.

    (2) Inspection of the following non-Federal dams (the indicated 

hazard potential categories are based upon the location of the dams 

relative to developed areas):

    (i) Dams which are in the high hazard potential category (located on 

Federal and non-Federal lands).

    (ii) Dams in the significant hazard potential category believed by 

the State to represent an immediate danger to the public safety due to 

the actual condition of the dam.

    (iii) Dams in the significant hazard potential category located on 

Federal lands.

    (iv) Specifically excluded from the national inspection program are:

    (A) Dams under the jurisdiction of the Bureau of Reclamation, the 

Tennessee Valley Authority, the International Boundary and Water 

Commission and the Corps of Engineers and

    (B) Dams which have been constructed pursuant to licenses issued 

under the authority of the Federal Power Act, and

    (C) Dams which have been inspected within the 12-month period 

immediately prior to the enactment of this act by a State agency and 

which the Governor of such State requests be excluded from inspection.

    (f) Objectives. The objectives of the program are:

    (1) To update the National Inventory of Dams by 30 September 1980.

    (2) To perform the initial technical inspection and evaluation of 

the non-Federal dams described in paragraph 222.8(e) of this section to 

identify conditions which constitute a danger to human life or property 

as a means of expediting the correction of hazardous conditions by non-

Federal interests. The inspection and evaluation is to be completed by 

30 September 1981.

    (3) To obtain additional information and experience that may be 

useful in determining if further Federal actions are necessary to assure 

national dam safety.

    (4) Encourage the States to establish effective dam safety programs 

for non-Federal dams by 30 September 1981 and assist the States in the 

development of the technical capability to carry out such a program.

    (g) Program execution--(1) Responsibilities. (i) The owner has the 

basic legal responsibility for potential hazards created by their 

dam(s). Phase II studies, as described in Chapter 4, Appendix D, and 

remedial actions are the owner's responsibility.

    (ii) The State has the basic responsibility for the protection of 

the life and property of its citizens. Once a dam has been determined to 

be unsafe, it is the State's responsibility to see that timely remedial 

actions are taken.

    (iii) The Corps of Engineers has the responsibility for executing 

the national program. The Federal program for inspection of dams does 

not modify the basic responsibilities of the States or dam owners. The 

Engineering Division of the Civil Works Directorate is responsible for 

overall program goals, guidance, technical criteria for inspections and 

inventory and headquarters level coordination with other agencies. The 

Water Resources Support Center (WRSC) located at Kingman Building, Fort 

Belvoir, Virginia 22060 is responsible for:

    (A) Program Coordination of both the inventory and inspection 

programs.



[[Page 258]]



    (B) Developing and defining functional tasks to achieve program 

objectives.

    (C) Determining resource requirements. (Budget)

    (D) Compiling and disseminating progress reports.

    (E) Monitoring and evaluating program progress and recommending 

corrective measures as needed.

    (F) Collecting and evaluating data pertaining to inspection reports, 

dam owners' responses to inspection report recommendations, attitudes 

and capabilities of State officials, State dam safety legislation, 

Architect-Engineer performance, etc., for defining a comprehensive 

national dam safety program.

    (G) Responding to Congressional, media, scientific and engineering 

organization and general public inquiries.



Division and District offices are responsible for executing the program 

at the State level. Assignment of Division reponsibilities for States is 

shown in Appendix A.

    (2) State participation. Where State capability exists, every effort 

should be made to encourage the State to execute the inspection program 

either with State personnel or with Architect-Engineer (A-E) contracts 

under State supervision. If the State does not have the capability to 

carry out the inspection program, the program will be managed by the 

Corps of Engineers utilizing Corps employees or contracts with A-E firm.

    (h) Update of National Inventory of Dams. (RCS-DAEN-CWE-17/OMB No. 

49-RO421)

    (1) The National Inventory of Dams should be updated and verified to 

include all Federal and non-Federal dams covered by the Act. Those dams 

are defined as all artificial barriers together with appurtenant works 

which impound or divert water and which: (1) Are twenty-five feet or 

more in height or (2) have an impounding capacity of fifty acre-feet or 

more. Barriers which are six feet or less in height, regardless of 

storage capacity or barriers which have a storage capacity at maximum 

water storage elevation of fifteen acre-feet or less regardless of 

height are not included.

    (2) Inventory data for all dams shall be provided in accordance with 

Appendix B.

    (3) The hazard potential classification shall be in accordance with 

paragraph 2.1.2 Hazard Potential of the Recommended Guideline for Safety 

Inspection of Dams (Appendix D to this section).



                                    Table 2--Hazard Potential Classification

----------------------------------------------------------------------------------------------------------------

                Category                          Urban development                      Economic loss

----------------------------------------------------------------------------------------------------------------

Low....................................  No permanent structure for human     Minimal (Undeveloped to occasional

                                          habitation.                          structures or agriculture).

Significant............................  No urban development and no more     Appreciable (Notable agriculture,

                                          than a small number of habitable     industry or structures).

                                          structures.

High...................................  Urban development with more than a   Excessive (Extensive community,

                                          small number of habitable            industry or agriculture).

                                          structures.

----------------------------------------------------------------------------------------------------------------



    (4) As in the original development of the inventory, the States 

should be encouraged to participate in the work of completing, verifying 

and updating the inventory. Also, when available, personnel of other 

appropriate Federal agencies should be utilized for the inventory work 

on a reimbursable basis. Work in any State may be accomplished:

    (i) Under State supervision utilizing State personnel or Architect-

Engineers contracts.

    (ii) Under Corps supervision utilizing Corps employees, employees of 

other Federal agencies or Architect-Engineer contracts.

    (5) A minimum staff should be assigned in Districts and Divisions to 

administer and monitor the inventory activities. Generally, the work 

should be accomplished by architect-engineers or other Federal agency 

personnel under State or Corps supervision. Corps personnel should 

participate in the inventory only to the extent needed to assure that 

accurate data are collected.



[[Page 259]]



    (6) The National Inventory of Dams computerized data base in stored 

on the Boeing Computer Services (BCS) EKS computer system in Seattle, 

Washington. The data base uses Data Base Management System 2000 and is 

accessible for query by all Corps offices.

    (7) Appendix B indicates details on accessing and updating inventory 

data.

    (8) Appendix I describes the procedure for using NASA Land Satellite 

(LANDSAT) Multispectral Scanner data along with NASA's Surface Water 

Detection and Mapping (DAM) computer program to assist in updating and 

verifying and National Inventory of Dams.

    (9) All inventory data for dams will be completed and verified 

utilizing all available sources of information (including LANDSAT 

overlay maps) and will include site visitation if required. It is the 

responsibility of the District Engineer to insure that the inventory of 

each State within his area of responsibility is accurate and contains 

the information required by the General Instructions for completing the 

forms for each Federal and non-Federal dam.

    (i) [Reserved]

    (j) Inspection Program. (RCS-DAEN-CWE-17 and OMB No. 49-RO421)

    (1) Scheduling of inspections. The Governor of each State or his 

designee will continue to be involved in the selection and scheduling of 

the dams to be inspected. Priority will be given to inspection of those 

dams considered to offer the greatest potential threat to public safety.

    (i) No inspection of a dam should be initiated until the hazard 

potential classification of the dam has been verified to the 

satisfaction of the Corps. Dams in the significant hazard category 

should be inspected only if requested by the State and only then if the 

State can provide information to show that the dam has deficiencies that 

pose an immediate danger to the public safety. Guidance for the 

selection of significant category non-Federal dams on Federal lands will 

be given in the near future.

    (ii) Selection for inspection of non-Federal dams located on Federal 

lands or non-Federal dams designed and constructed under the 

jurisdiction of some Federal agency, should be coordinated with the 

responsible Federal agency. The appropriate State or regional 

representative of the Federal agency also should be contacted to obtain 

all available data on the dam. Representatives of the agency may 

participate in the inspection if they desire and should be given the 

opportunity to review and comment on the findings and recommendations in 

the inspection report prior to submission to the Governor and the dam 

owner. Examples of such dams are: non-Federal dams built on lands 

managed by National Forest Service, Bureau of Land Management, Fish and 

Wildlife Service, etc.; non-Federal dams designed and constructed by the 

Soil Conservation Service of the U.S. Department of Agriculture; high 

hazard mine tailings and coal mine waste dams under the jurisdiction of 

the Mine Safety and Health Administration, Department of Labor.

    (iii) Indian-owned dams on trust lands are considered to be non-

Federal dams. All dams in the high hazard potential category will be 

inspected. Privately-owned dams located on Indian lands are to be 

included in the program, however BIA-owned dams on Indian lands are 

Federal dams and are exempt.

    (2) Procedures. The Division Engineer is responsible for the quality 

of inspections and reports prepared by the District Engineer. Close 

liaison between the District Engineer and the State agency or A-E firm 

responsible for the inspections will be required in order to obtain a 

dependable result. To avoid undesirable delays in the evaluation of 

safety of individual dams, contracts with A-E's or agreements with 

States which are managing the program will provide that reports be 

completed and furnished to the District Engineer within a specified time 

after completion of the on-site inspection of the dam.

    (i) Inspection guidelines. The inspection should be conducted in 

accordance with the Recommended Guidelines for Safety Inspection of Dams 

(Appendix D to this section). Expanded Guidance for Hydrologic and 

Hydraulic Assessment of Dams is provided in Appendix C. The criteria in 

the recommended guidelines are screening criteria to be used only



[[Page 260]]



for initial determinations of the adequacy of the dam. Conditions found 

during the investigation which do not meet the guideline recommendations 

should be assessed as to their importance from the standpoint of the 

degree of risk involved.

    (ii) Coordinators. Experience has shown that coordination and 

communications among technical disciplines, Public Affairs Office, 

emergency officials, training officers, operations personnel, State 

representatives and A-E firms has been best in those districts where one 

person was delegated the responsiblity for coordinating the actions of 

all involved elements. Each district should evaluate its overall 

coordination procedures to insure that all involved elements have the 

best possible access to necessary data.

    (iii) Field investigations should be carried out in a systematic 

manner. A detailed checklist or inspection form should be developed and 

used for each dam inspection and appended to the inspection report. The 

size of the field inspection team should be as small as practicable, 

generally consisting of only one representative of each required 

discipline in order to control the costs of the inspection without 

sacrificing the quality of the inspection. The inspection team for the 

smaller less complex dams should be limited to two or three 

representatives from appropriate technical areas with additional 

specialists used only as special conditions warrant. The larger more 

complex projects may require inspection teams of three or four 

specialists. Performance of overly detailed and precise surveys and 

mapping should be avoided. Necessary measurement of spillway, dam 

slopes, etc. can generally be made with measuring tapes and hand levels.

    (iv) Additional engineering studies. Dam inspections should be 

limited to Phase I investigations as outlined in Chapter 3 of Appendix 

D. However, if recommended by the investigating engineer and approved by 

the District Engineer, some additional inexpensive investigations may be 

performed when a reasonable judgment on the safety of the dam cannot be 

made without additional investigation. Any further Phase II 

investigation needed to prove or disprove the findings of the District 

Engineer or to devise remedial measures to correct deficiencies are the 

responsibility of the owner and will not be undertaken by the Corps of 

Engineers.

    (v) Assessment of the investigation. (A) The findings of the visual 

inspection and review of existing engineering data for a dam shall be 

assessed to determine its general condition. Dams assessed to be in 

generally good condition should be so described in the inspection 

report. Deficiencies found in a dam should be described and assessed as 

to the degree of risk they present. The degree of risk should consider 

only loss of life and/or property damage resulting from flooding due to 

dam failure. Loss of project benefits i.e., municipal water supply, 

etc., should not be considered. If deficiencies are assessed to be of 

such a nature that, if not corrected, they could result in the failure 

of the dam with subsequent loss of life and/or substantial property 

damage, the dam should be assessed as ``Unsafe.'' If the probable 

failure of an ``Unsafe'' dam is judged to be imminent and immediate 

action is required to reduce or eliminate the hazard, the ``unsafe'' 

condition of the dam should be considered an ``emergency.'' If the 

probable failure is judged not to be imminent, the ``unsafe'' condition 

should be considered a ``non-emergency.''

    (B) Adequacy of spillway. The ``Recommended Guidelines for Safety 

Inspection of Dams,'' Appendix D, provide current, acceptable inspection 

standards for spillway capacity. Any spillway capacity that does not 

meet the criteria in the ``Guidelines'' is considered inadequate. When a 

spillway's capacity is so deficient that it is seriously inadequate, the 

project must be considered unsafe. If all of the following conditions 

prevail, the Governor of the State shall be informed that such project 

is unsafe:

    (1) There is high hazard to loss of life from large flows downstream 

of the dam.

    (2) Dam failure resulting from overtopping would significantly 

increase the hazard to loss of life downstream from the dam over that 

which would exist just before overtopping failure.



[[Page 261]]



    (3) The spillway is not capable of passing one-half of the probable 

maximum flood without overtopping the dam and causing failure.



Classification of dams with seriously inadequate spillways as ``unsafe, 

non-emergency'' is generally a proper designation of the urgency of the 

unsafe condition. However, there may be cases where the spillway 

capacity is unusually small and the consequences of dam overtopping and 

failure would be catastrophic. In such cases, the unsafe dam should be 

classified as an emergency situation.

    (vi) All inspection reports will receive one level of independent 

review by the Corps. If the reports are prepared by the Corps, the 

independent review may be performed internally within the district 

office. However, in cases which involve significant economic, social or 

political impacts and technical uncertainties in evaluating the dams, 

advice may be obtained from the staffs of the Division Engineer and the 

Office, Chief of Engineers.

    (3) Reports--(i) Preparation. A written report on the condition of 

each dam should be prepared as soon as possible after the completion of 

the field inspection and assessment. A suggested report format is 

attached as Appendix E. It is important that the inspection report be 

completed in a timely manner. For inspections being done by Corps 

employees, it is suggested that once an inspection team has been 

assigned to a dam inspection it be allowed to complete the inspection 

and report without interruption by other work.

    (ii) Review and approval. The coordinating engineer should determine 

which disciplines should review the report and establish a procedure to 

accomplish the review in a timely manner. A review panel, made up of the 

appropriate Division and Branch Chiefs has worked well in some 

districts. Use of a review panel should be seriously considered by all 

districts. All inspection reports shall be approved by the District 

Engineer who will maintain a complete file of final approved reports. 

Any State or Federal agency having jurisdiction over the dam or the land 

on which the dam is built should be given the opportunity to review and 

comment on the report prior to submission to the Governor or dam owner. 

The District Engineer will transmit final approved reports to the 

Governor of the State and the dam owner (or the Governor only, when 

requested in writing by State officials). If the report is initially 

furnished to the Governor only, a period of up to ten days may be 

allowed before the report is furnished to the dam owner. If the Governor 

or the owner indicates additional technical information is available 

that might affect the assessment of the dam's condition, the District 

Engineer will furnish the proposed final report to the Governor and the 

owner and establish a definite time period for comments to be furnished 

to the District Engineer prior to report approval.

    (iii) In general the Governor will be responsible for public release 

of an inspection report and for initiating any public Statements. 

However, an approved report must be treated as any other document 

subject to release upon request under the Freedom of Information Act. 

The letters of transmittal to the Governor and owner should indicate 

that under the provisions of the Freedom of Information Act, the 

documents will be subject to release upon request after receipt by the 

Governor. Proposed final reports will be considered as internal working 

papers not subject to release under the Freedom of Information Act. 

Corps personnel, A-E contractor personnel and others working under 

supervision of the Corps will be cautioned to avoid public statements 

about the condition of the dam until after the District Engineer has 

approved the report. The Corps will respond fully to inquiries after the 

Governor has received the approved report or been notified of an unsafe 

dam. An information copy of the report should be sent to the District 

office normally having jurisdiction if other than the District 

responsible for the inspection.

    (iv) Follow-up action. A Federal investment of the magnitude 

anticipated for this inspection program makes it desirable that a 

reporting system be established to keep the District Engineer abreast of 

the implementation of the recommendations in the inspection reports. The 

letters of transmittal to the Governor and owner will request that



[[Page 262]]



the District Engineer be informed of the actions taken on the 

recommendations in the inspection reports. However, the National Dam 

Inspection Act only authorizes the initial inspection of certain dams; 

therefore, once a report is completed no reinspection will be 

undertaken.

    (4) Unsafe dams. The investigating engineer will be required to 

immediately notify the District Engineer when a dam is assessed as being 

unsafe. He will also indicate if probable failure of the unsafe dam is 

judged to be imminent and immediate action is required to reduce or 

eliminate the threat. The District Engineer will evaluate the findings 

of the investigating team and will immediately notify the Governor and 

the owner if the findings are Unsafe Non-Emergency or Unsafe-Emergency. 

The appropriate State agency and the Corps of Engineers officials having 

emergency operation responsibility for the area in which the dam is 

located will also be notified. The information provided in the unsafe 

dam notice shall be as indicated in Appendix F. Any emergency procedures 

or remedial actions deemed necessary by the District Engineer will be 

recommended to the Governor who has the responsibility for any 

corrective actions. As provided in ER 500-1-1, Corps assistance under 

Pub. L. 84-99 ``Advance Measures,'' may be made available to complement 

the owner's and Governor's action under certain conditions and subject 

to the approval of the Director of Civil Works. The District Engineer's 

Emergency Operation Officer will coordinate the advance measures request 

in accordance with existing procedures. Coordination will be maintained 

between the District responsible for emergency action under Pub. L. 84-

90 and the District responsible for the inspection.

    (5) Emergency action plans. An emergency action plan should be 

available for every dam in the high and significant hazard category. 

Such plans should outline actions to be taken by the operator to 

minimize downstream effects of an emergency and should include an 

effective warning system. If an emergency action plan has not been 

developed, the inspection report should recommend that the owner develop 

such an action plan. However, the Corps has no authority to require an 

emergency action plan.

    (k) Progress reports. Progress reports should be submitted monthly 

by the Division Engineer to WRSC. The reports shall include progress 

through the last Saturday of the month and should be mailed by the 

following Monday. The reports shall contain the information and be 

typewritten in the format shown in Appendix G. Copies of Unsafe Dam Data 

Sheets will be submitted with the progress report. Copies of the 

completed inspection report for Dams in the Unsafe-Emergency category 

will be submitted also. (RCS-DAEN-CWE-19)

    (l) Contracts--(1) Corps of Engineers supervision. Contracts for 

performing inventory and inspection activities under supervision of the 

Corps of Engineers shall be Fixed-Price Architect Engineer Contracts for 

Services. A sample scope of work setting forth requirements is provided 

in Appendix H. Experience has shown that costs for individual dam 

inspection have been lower when multiple inspections are included in one 

contract. Therefore, each A-E contract should include multiple dam 

inspections where practicable. Corps participation in A-E inspections 

should be held to a minimum. Corps representatives should participate in 

only enough A-E inspections to assure the equality of the inspections.

    (2) State supervision. Contracts with States for performing 

inventory and inspection activities under State supervision may be 

either a Cost-Reimbursement type A-E Contract for Services or a Fixed-

Price type contract. The selection of Architect-Engineers by the State 

should require approval of the Corps of Engineers Contracting Officer. 

The negotiated price for A-E services under cost-reimbursement type 

contracts with States will also require approval by the Contracting 

Officer. Contracts with States should require timely submission of the 

inspection reports to the District Engineer for review and approval. The 

contract provisions should also prevent public release of or public 

comment on the inspection report until the District Engineer has 

reviewed and approved the report. Corps



[[Page 263]]



of Engineers participation in State inspections should be limited to 

occasional selected inspections to assure the quality of the State 

program.

    (m) Training. As indicated in paragraph (f) of this section, one 

objective of the inspection program for non-Federal Dams is to prepare 

the States to provide effective dam safety programs. In many States this 

will require training of personnel of State agencies in the technical 

aspects of dam inspections. The Office, Chief of Engineers is studying 

the need for and content of a comprehensive Corps-sponsored training 

program in dam inspection technology. Pending the possible adoption of 

such a comprehensive plan, division and district Engineers are 

encouraged to take advantage of suitable opportunities to provide needed 

training in dam safety activities to qualified employees of State 

agencies and, when appropriate, to employees of architect-engineer firms 

engaged in the program. The following general considerations should be 

observed in providing such training:

    (1) Priority must be placed on inspection of dams and updating the 

national dam inventory; hence, diversion of resources to training 

activities should not deter or delay these principle program functions.

    (2) Salaries, per diem and travel expenses relating to training 

activities of State employees will be a State expense. There will be no 

tuition charge for State employees.

    (3) Architect-Engineer firms will be required to pay expenses and 

tuition costs for their employees participating in Corps-sponsored 

training activities.

    (4) Corps-sponsored training will require that each trainee is a 

qualified engineer or geologist and will concentrate on engineering 

technology related directly to dam safety. (This may require screening 

of proposed candidates for training.)

    (5) Under this program, the Corps will not sponsor training that is 

intended primarily to satisfy requirements for a degree.

    (6) Training by participation in actual dam inspections and/or 

management of the inspection program should be encouraged.



             Appendix A to Sec.  222.6--Division Assignments



    To facilitate better coordination with the States, the Division 

Engineers are responsible for the dam inspection program by States as 

follows:



New England Division: Maine, Rhode Island, Connecticut, Vermont, New 

Hampshire, Massachusetts

North Atlantic Division: New York, New Jersey, Pennsylvania, Delaware, 

Maryland, Virginia, District of Columbia

Ohio River Division: West Virginia, Ohio, Kentucky, Tennessee, Indiana

South Atlantic Division: North Carolina, South Carolina, Georgia, 

Florida, Alabama, Puerto Rico, Virgin Islands

Lower Mississippi Valley Division: Mississippi, Louisiana, Missouri

North Central Division: Michigan, Wisconsin, Illinois, Minnesota, Iowa

Southwestern Division: Arkansas, Oklahoma, Texas, New Mexico

Missouri River Division: Kansas, Nebraska, South Dakota, North Dakota, 

Wyoming, Colorado

North Pacific Division: Oregon, Idaho, Montana, Washington, Alaska

South Pacific Division: Utah, California, Arizona, Nevada

Pacific Ocean Division: Hawaii, Trust Territories, American Samoa



              Appendix B to Sec.  222.6--Inventory of Dams



                 (RCS-DAEN-CWE-17 and OMB No. 49-RO421)



    1. The updating of the inventory will include the completion of all 

items of data for all dams now included in the inventory, verification 

of the data now included in the inventory, and inclusion of complete 

data for all appropriate existing dams not previously listed. Data 

completion, verification and updating will be scheduled over a three 

year period.

    2. The inventory data will be recorded on Engineering Form 4474 and 

4474A (Exhibit 2). The general instructions for completing the forms are 

printed on the back of the forms. Parts I and II of the forms are to be 

fully completed. The instruction for completing Item 29, Line 5, Para. 

II (Engr Form 4474A) is revised to conform identically with the hazard 

potential classification contained in the recommended guidelines for 

safety inspection of dams. Additional data has been added to designate 

Corps districts in which the dam is located, Federal agency owned dams, 

Corps owned dams, Federal agency regulated dams, dams constructed with 

technical or financial assistance of the U.S. Soil Conservation Service, 

and privately owned dams located on Federal property.

    3. All inventory data will be verified utilizing all available 

sources of information and will include site visitation if required.



[[Page 264]]



    4. The Inventory Data Base is stored on the Boeing Computer Services 

(BCS) EKS System in Seattle, Washington. The data is available to all 

Corps offices for queries using Data Base Management System 2000 (S2K).

    a. To access the National Data Base log on BCS and type the 

following:



GET,DAMS/UN=CECELB



CALL,DAMS



    b. For current information and changes to the National Inventory 

Data Base, type:



OLD,HOTDAM/UN=CEC1AT



LIST



    5. The inventory update data will be furnished and the National Data 

Base will be updated on a monthly basis. The monthly submission will 

cover all dams whose inventory data were completed since the last 

report. The update data will be loaded directly onto the Boeing Computer 

by the field office.

    a. The procedure for loading the data on the Boeing Computer can be 

printed by accessing the Boeing Computer and listing the information 

file ``HOTDAM.'' (See paragraph 4b. above.)

    b. It is the responsibility of the submitting office to edit the 

data prior to furnishing it for the update. Editing will be accomplished 

by processing the data using the Inventory Edit Computer program 

developed by the Kansas City District. This procedure is described in 

the ``HOTDAM'' file.

    6. Federal agencies will be uniformly designated by major and minor 

abbreviations according to the following list whenever applicable to 

Items 46 through 53. Abbreviations are to be left justified within the 

field with one blank separating major and minor abbreviations.



------------------------------------------------------------------------

                                             Major            Minor

------------------------------------------------------------------------

a. International Boundary and Water     IBWC

 Commission.

b. U.S. Department of Agriculture:

  (1) Soil Conservation Service.......  USDA             SCS

  (2) Forest Service..................  USDA             FS

c. U.S. Department of Energy Federal    DOE              FERC

 Energy Regulatory Commission.

d. Tennessee Valley Authority.........  TVA

e. U.S. Department of Interior:

  (1) Bureau of Sport Fisheries and     DOI              BSFW

   Wildlife.

  (2) Geological Survey...............  DOI              GS

  (3) Bureau of Land Management.......  DOI              BLM

  (4) Bureau of Reclamation...........  DOI              USBR

  (5) Bureau of Indian Affairs........  DOI              BIA

f. U.S. Department of Labor: (1) Mine   DOL              MSHA

 Safety and Health Administration.

g. Corps of Engineers:

  (1) Lower Mississippi Valley

   Division:

    (a) Memphis District..............  DAEN             LMM

    (b) New Orleans District..........  DAEN             LMN

    (c) St. Louis District............  DAEN             LMS

    (d) Vicksburg District............  DAEN             LMK

  (2) Missouri River Division:

    (a) Kansas City District..........  DAEN             MRK

    (b) Omaha District................  DAEN             MRO

  (3) New England Division............  DAEN             NED

  (4) North Atlantic Division:........

    (a) Baltimore District............  DAEN             NAB

    (b) New York District.............  DAEN             NAN

    (c) Norfolk District..............  DAEN             NAO

    (d) Philadelphia District.........  DAEN             NAP

  (5) North Central Division:

    (a) Buffalo District..............  DAEN             NCB

    (b) Chicago District..............  DAEN             NCC

    (c) Detroit District..............  DAEN             NCE

    (d) Rock Island District..........  DAEN             NCR

    (e) St. Paul District.............  DAEN             NCS

  (6) North Pacific Division:

    (a) Alaska District...............  DAEN             NPA

    (b) Portland District.............  DAEN             NPP

    (c) Seattle District..............  DAEN             NPS

    (d) Walla Walla District..........  DAEN             NPW

  (7) Ohio River Division:

    (a) Huntington District...........  DAEN             ORH

    (b) Louisville District...........  DAEN             ORL

    (c) Nashville District............  DAEN             ORN

    (d) Pittsburgh District...........  DAEN             ORP

  (8) Pacific Ocean Division..........  DAEN             POD

  (9) South Atlantic Division:

    (a) Charleston District...........  DAEN             SAC

    (b) Jacksonville District.........  DAEN             SAJ

    (c) Mobile District...............  DAEN             SAM

    (d) Savannah District.............  DAEN             SAS

    (e) Wilmington District...........  DAEN             SAW

  (10) South Pacific Division:

    (a) Los Angeles District..........  DAEN             SPL

    (b) Sacramento District...........  DAEN             SPK

    (c) San Franciso District.........  DAEN             SPN

  (11) Southwestern Division:

    (a) Albuquerque District..........  DAEN             SWA

    (b) Fort Worth District...........  DAEN             SWF

    (c) Galveston District............  DAEN             SWG

    (d) Little Rock District..........  DAEN             SWL

    (e) Tulsa District................  DAEN             SWT

------------------------------------------------------------------------



    7. Procedures for Revising and Updating the Inventory of Dams Master 

File.

    a. To Change Correct or Add an Item. Submit a change card that 

contains the identification assigned to the dams (Columns 1 thru 7), the 

proper card code (Column 80) and only the item or items changed, 

corrected or added. Data on the master file is added or replaced on an 

item for item basis.

    b. To Delete an Item. Submit a change card that contains the 

identification assigned to the dam, (Columns 1 thru 7), the proper card 

code (Column 80), and an asterisk (*) in the left most column of the 

item or items to be deleted. More than one item can be changed, 

corrected, added on or deleted from the same card.

    c. To Delete the Entire Data for a Dam from the Master File. Submit 

a zero (0) card punched as follows:



Columns 1 thru 7--Item 1 identification assigned to the dam

Columns 8 thru 10--Item 2, Division Code

Columns 11 thru 16--The word DELETE

Columns 17 thru 79--Blank Spaces

Column 80--A zero



    8. Keypunch Instructions and Punched Card Formats.



[[Page 265]]



    a. Table 1 describes the character set to be used for keypunch cards 

of Engr. Forms 4474 and 4474A.

    b. Exhibit 1 is the EDPC keypunch instructions and punch card 

formats defining the data fields (Items) and card columns to be used in 

preparing punched cards in compliance with the requirements of this 

regulation.

    c. Exhibit 2 are prints of Engr. Forms 4474 and 4474A which are laid 

out in punch card format to facilitate punching cards directly from the 

completed forms.

[GRAPHIC] [TIFF OMITTED] TC31OC91.000





[[Page 266]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.001





[[Page 267]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.002





[[Page 268]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.003





[[Page 269]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.004





[[Page 270]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.005





[[Page 271]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.006





[[Page 272]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.007





[[Page 273]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.008





[[Page 274]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.009





[[Page 275]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.010





[[Page 276]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.011



 Appendix C to Sec.  222.6--Hydrologic and Hydraulic Assessment of Dams



    1. Phase I inspections are not intended to provide detailed 

hydrologic and hydraulic analyses of dam and reservoir capabilities. 

However, when such analyses are available, they should be evaluated for 

reliability and completeness. If a project's ability to pass the 

appropriate flood (see Table 3, page D-12 of Recommended Guidelines) can 

be determined from available information of a brief study, such an 

assessment should be made. It should be noted that hydrologic and 

hydraulic analyses connected with the Phase I inspections should be 

based on approximate methods or systematized computer programs that take 

minimal effort. The Hydrologic Engineering Center (HEC) has developed a 

special computer program for hydrologic and hydraulic analyses to be 

used with the Phase I inspection program. Other Field Operating Agencies 

have developed similar computer programs or generalized procedures which 

are acceptable for use. All such efforts should be completed with 

minimum resources.

    2. A finding that a dam will not safely pass the flood indicated in 

the Recommended Guidelines does not necessarily indicate that the dam 

should be classified as unsafe. The degree of inadequacy of the spillway 

to pass the appropriate flood and the probable adverse impacts of dam 

failure because of overtopping must be considered in making such 

classification. The following criteria have



[[Page 277]]



been selected which indicate when spillway capacity is so seriously 

inadequate that a project must be classified as unsafe. All of the 

following conditions must prevail before designating a dam unsafe:

    a. There is high hazard to loss of life from large flows downstream 

of the dam.

    b. Dam failure resulting from overtopping would significantly 

increase the hazard to loss of life downstream from the dam from that 

which would exist just before overtopping failure.

    c. The spillway is not capable of passing one-half of the probable 

maximum flood without overtopping the dam and causing failure.

    3. The above criteria are generally adequate for evaluating most 

non-Federal dams. However, in a few cases the increased hazard potential 

from overtopping and failure is so great as to result in catastrophic 

consequences. In such cases, the evaluation of condition 2c should 

utilize a flood more closely approximating the full probable maximum 

flood rather than one-half the flood. An example of such a situation 

would be a large dam immediately above a highly populated flood plain, 

with little likelihood of time for evacuation in the event of an 

emergency.

    4. Conditions 2a and 2b require an approximation of housing location 

in relation to flooded areas. Resources available in Phase I inspections 

do not permit detailed surveys or time-consuming studies to develop such 

relationships. Therefore, rough estimates will generally be made from 

data obtained during the inspection and from readily available maps and 

drawings. Brief computer routings such as the HEC-1 dam break analysis, 

using available data, are recommended in marginal cases. The HEC-1, dam 

break version, is available on the Boeing Computer Services or may be 

obtained from the Hydrologic Engineering Center, Davis, California. 

Available resources do not permit detailed studies or investigations to 

establish the amount of overtopping that would cause a dam to fail, as 

designated in condition 2c. Professional judgment and available 

information will have to be used in these determinations. When detailed 

investigations and studies are required to make a reasonable judgment of 

the conditions which designate an unsafe dam, the inspection report 

should recommend that such studies be the responsibility of the dam 

owner.

    5. During the inspection of a dam, consideration should be given to 

impacts on other dams located downstream from the project being 

inspected. When failure of a dam would be likely to cause failure of 

another dam(s) downstream, its designation as an unsafe dam could result 

in multiple impacts. Therefore, the information should be explicitly 

described in the inspection report. Such information may be vital to the 

priorities established by State Governors for dam improvements. 

Similarly, when the failure of an upstream dam (classified as unsafe) 

could cause failure of the dam being inspected, this information should 

be prominently displayed in the inspection report.

    6. The criteria established in paragraph 2 for designating unsafe 

dams because of seriously inadequate spillways are considered reasonable 

and prudent. They provide a consistent bases for declaring unsafe dams 

and also serve as an effective compromise between the Recommended 

Guidelines and unduly low standards suggested by special interests and 

individuals unfamiliar with flood hazard potential.

    7. The Hydrometeorological Branch (HMB) of the National Weather 

Service has reviewed some 500 experienced large storms in the United 

States. The purpose of the review was to ascertain the relative 

magnitude of experienced large storms to probable maximum precipitation 

(PMP) and their distribution throughout the country. Their review 

reveals that about 25 percent of the major storms have exceeded 50 

percent of the probable maximum precipitation for one or more 

combinations of area and duration. In fact some storms have very closely 

approximated the PMP values. Exhibits C-1 thru C-5 indicate locations 

where experienced storms have exceeded 50 percent of the PMP.

    8. There are several options to consider when selecting mitigation 

measures to avoid severe consequences of a dam failure from overtopping. 

The following measures may be required by a Governor when sufficient 

legal authority is available under State laws and a dam presents a 

serious threat to loss of life.

    a. Remove the dam.

    b. Increase the height of dam and/or spillway size to pass the 

probable maximum flood without overtopping the dam.

    c. Purchase downstream land that would be adversely impacted by dam 

failure and restrict human occupancy.

    d. Enhance the stability of the dam to permit overtopping by the 

probable maximum flood without failure.

    e. Provide a highly reliable flood warning system (generally does 

not prevent damage but avoids loss of life).



[[Page 278]]







 Table 1--Storms With Rainfall =150% of PMP, U.S. East of the 105th Meridian (for 10 mi\2\, 6 Hours;

                                200 mi\2\, 24 Hours and/or 1,000 mi\2\, 48 Hours)

----------------------------------------------------------------------------------------------------------------

                                       Corps assignment             Storm center

          Storm date            Index       No. (if     ------------------------------------ Latitude  Longitude

                                 No.      available)           Town              State

----------------------------------------------------------------------------------------------------------------

July 26, 1819................       1  ................  Catskill........  NY..............  42[deg]1  73[deg]53

                                                                                               2[min]      [min]

Aug. 5, 1843.................       2  ................  Concordville....  PA..............  39[deg]5  75[deg]32

                                                                                               3[min]      [min]

Sept. 10-13, 1878............       3  OR 9-19.........  Jefferson.......  OH..............  41[deg]4  80[deg]46

                                                                                               5[min]      [min]

Sept. 20-24, 1882............       4  NA 1-3..........  Paterson........  NJ..............  40[deg]5  74[deg]10

                                                                                               5[min]      [min]

June 13-17, 1886.............       5  LMV 4-27........  Alexandria......  LA..............  31[deg]1  92[deg]33

                                                                                               9[min]      [min]

June 27-July 11, 1899........       6  GM 3-4..........  Turnersville....  TX..............  30[deg]5  96[deg]32

                                                                                               2[min]      [min]

Aug. 24-28, 1903.............       7  MR 1-10.........  Woodburn........  IA..............  40[deg]5  93[deg]35

                                                                                               7[min]      [min]

Oct. 7-11, 1903..............       8  GL 4-9..........  Paterson........  NJ..............  40[deg]5  74[deg]10

                                                                                               5[min]      [min]

July 18-23, 1909.............       9  UMV 1-11B.......  Ironwood........  MI..............  46[deg]2  90[deg]11

                                                                                               7[min]      [min]

July 18-23, 1909.............      10  UMV 1-11A.......  Beaulieu........  MN..............  47[deg]2  95[deg]48

                                                                                               1[min]      [min]

July 22-23, 1911.............      11  ................  Swede Home......  NB..............  40[deg]2  96[deg]54

                                                                                               2[min]      [min]

July 19-24, 1912.............      12  GL 2-29.........  Merrill.........  WI..............  45[deg]1  89[deg]41

                                                                                               1[min]      [min]

July 13-17, 1916.............      13  SA 2-9..........  Altapass........  NC..............  35[deg]3  82[deg]01

                                                                                               3[min]      [min]

Sept. 8-10, 1921.............      14  GM 4-12.........  Taylor..........  TX..............  30[deg]3  97[deg]18

                                                                                               5[min]      [min]

Oct. 4-11, 1924..............      15  SA 4-20.........  New Smyrna......  FL..............  29[deg]0  80[deg]55

                                                                                               7[min]      [min]

Sept. 17-19, 1926............      16  MR 4-24.........  Boyden..........  IA..............  43[deg]1  96[deg]00

                                                                                               2[min]      [min]

Mar. 11-16, 1929.............      17  UMV 2-20........  Elba............  AL..............  31[deg]2  86[deg]04

                                                                                               5[min]      [min]

June 30-July 2, 1932.........      18  GM 5-1..........  State Fish        TX..............  30[deg]0  99[deg]07

                                                          Hatchery.                            1[min]      [min]

Sept. 16-17, 1932............      19  ................  Ripogenus Dam...  ME..............  45[deg]5  69[deg]09

                                                                                               3[min]      [min]

July 22-27, 193..............      20  LMV 2-26........  Logansport......  LA..............  31[deg]5  94[deg]00

                                                                                               8[min]      [min]

Apr. 3-4 1934................      21  SW 2-11.........  Cheyenne........  OK..............  35[deg]3  99[deg]40

                                                                                               7[min]      [min]

May 30-31, 1935..............      22  MR 3-28A........  Cherry Creek....  CO..............  39[deg]1  104[deg]3

                                                                                               3[min]     2[min]

May 31, 1935.................      23  GM 5-20.........  Woodward........  TX..............  29[deg]2  99[deg]28

                                                                                               0[min]      [min]

July 6-10, 1935..............      24  NA 1-27.........  Hector..........  NY..............  42[deg]3  76[deg]53

                                                                                               0[min]      [min]

Sept. 2-6, 1935..............      25  SA 1-26.........  Easton..........  MD..............  38[deg]4  76[deg]01

                                                                                               6[min]      [min]

Sept. 14-18, 1936............      26  GM 5-7..........  Broome..........  TX..............  31[deg]4  100[deg]5

                                                                                               7[min]     0[min]

June 19-20, 1939.............      27  ................  Snyder..........  TX..............  32[deg]4  100[deg]5

                                                                                               4[min]     5[min]

July 4-5, 1939...............      28  ................  Simpson.........  KY..............  38[deg]1  83[deg]22

                                                                                               3[min]      [min]

Aug. 19, 1939................      29  NA 2-3..........  Manahawkin......  NJ..............  39[deg]4  74[deg]16

                                                                                               2[min]      [min]

June 3-4, 1940...............      30  MR 4-5..........  Grant Township..  NB..............  42[deg]0  96[deg]53

                                                                                               1[min]      [min]

Aug. 6-9, 1940...............      31  LMV 4-24........  Miller Isl......  LA..............  29[deg]4  92[deg]10

                                                                                               5[min]      [min]

Aug. 10-17, 1940.............      32  SA 5-19A........  Keysville.......  VA..............  37[deg]0  78[deg]30

                                                                                               3[min]      [min]

Sept. 1, 1940................      33  NA 2-4..........  Ewan............  NJ..............  39[deg]4  75[deg]12

                                                                                               2[min]      [min]

Sept. 2-6, 1940..............      34  SW 2-18.........  Hallet..........  OK..............  36[deg]1  96[deg]36

                                                                                               5[min]      [min]

Aug. 28-31, 1941.............      35  UMV 1-22........  Haywood.........  WI..............  46[deg]0  91[deg]28

                                                                                               0[min]      [min]

Oct. 17-22, 1941.............      36  SA 5-6..........  Trenton.........  FL..............  29[deg]4  82[deg]57

                                                                                               8[min]      [min]

July 17-18, 1942.............      37  OR 9-23.........  Smethport.......  PA..............  41[deg]5  78[deg]25

                                                                                               0[min]      [min]

Oct. 11-17, 1942.............      38  SA 1-28A........  Big Meadows.....  VA..............  38[deg]3  78[deg]26

                                                                                               1[min]      [min]

May 6-12, 1943...............      39  SW 2-20.........  Warner..........  OK..............  35[deg]2  95[deg]18

                                                                                               9[min]      [min]

May 12-20, 1943..............      40  SW 2-21.........  Nr. Mounds......  OK..............  35[deg]5  96[deg]04

                                                                                               2[min]      [min]

July 27-29, 1943.............      41  GM 5-21.........  Devers..........  TX..............  30[deg]0  94[deg]35

                                                                                               2[min]      [min]

Aug. 4-5, 1943...............      42  OR 3-30.........  Nr. Glenville...  WV..............  38[deg]5  80[deg]50

                                                                                               6[min]      [min]

June 10-13, 1944.............      43  MR 6-15.........  Nr. Stanton.....  NB..............  41[deg]5  97[deg]03

                                                                                               2[min]      [min]

Aug. 12-15, 1946.............      44  MR 7-2A.........  Cole Camp.......  MO..............  38[deg]4  93[deg]13

                                                                                               0[min]      [min]

Aug. 12-16, 1946.............      45  MR 7-2B.........  Nr. Collinsville  IL..............  38[deg]4  89[deg]59

                                                                                               0[min]      [min]

Sept. 26-27, 1946............      46  GM 5-24.........  Nr. San Antonio.  TX..............  29[deg]2  98[deg]29

                                                                                               0[min]      [min]

June 23-24, 1948.............      47  ................  Nr. Del Rio.....  TX..............  29[deg]2  100[deg]3

                                                                                               2[min]     7[min]

Sept. 3-7, 1950..............      48  SA 5-8..........  Yankeetown......  FL..............  29[deg]0  82[deg]42

                                                                                               3[min]      [min]

June 23-28, 1954.............      49  SW 3-22.........  Vic Pierce......  TX..............  30[deg]2  101[deg]2

                                                                                               2[min]     3[min]

Aug. 17-20, 1955.............      50  NA 2-22A........  Westfield.......  MA..............  42[deg]0  72[deg]45

                                                                                               7[min]      [min]

May 15-16, 1957..............      51  ................  Hennessey.......  OK..............  36[deg]0  97[deg]56

                                                                                               2[min]      [min]

June 14-15, 1957.............      52  ................  Nr. E. St. Louis  IL..............  38[deg]3  90[deg]24

                                                                                               7[min]      [min]

June 23-24, 1963.............      53  ................  David City......  NB..............  41[deg]1  97[deg]05

                                                                                               4[min]      [min]

June 13-20, 1965.............      54  ................  Holly...........  CO..............  37[deg]4  102[deg]2

                                                                                               3[min]     3[min]

June 24, 1966................      55  ................  Glenullin.......  ND..............  47[deg]2  101[deg]1

                                                                                               1[min]     9[min]

Aug. 12-13, 1966.............      56  ................  Nr. Greely......  NB..............  41[deg]3  98[deg]32

                                                                                               3[min]      [min]

Sept. 19-24, 1967............      57  SW 3-24.........  Falfurrias......  TX..............  27[deg]1  98[deg]12

                                                                                               6[min]      [min]

July 16-17, 1968.............      58  ................  Waterloo........  IA..............  42[deg]3  92[deg]19

                                                                                               0[min]      [min]

July 4-5, 1969...............      59  ................  Nr. Wooster.....  OH..............  40[deg]5  82[deg]00

                                                                                               0[min]      [min]

Aug. 19-20, 1969.............      60  NA 2-3..........  Nr. Tyro........  VA..............  37[deg]4  79[deg]00

                                                                                               9[min]      [min]

June 9, 1972.................      61  ................  Rapid City......  SD..............  44[deg]1  103[deg]3

                                                                                               2[min]     1[min]

June 19-23, 1972.............      62  ................  Zerbe...........  PA..............  40[deg]3  76[deg]31

                                                                                               7[min]      [min]

July 21-22, 1972.............      63  ................  Nr. Cushing.....  MN..............  46[deg]1  94[deg]30

                                                                                               0[min]      [min]

Sept. 10-12, 1972............      64  ................  Harlan..........  IA..............  41[deg]4  95[deg]15

                                                                                               3[min]      [min]

Oct. 10-11, 1973.............      65  ................  Enid............  OK..............  36[deg]2  97[deg]52

                                                                                               5[min]      [min]

----------------------------------------------------------------------------------------------------------------





[[Page 279]]





 Table 2--Storms With Rainfall =50% of PMP, U.S. West of Continental Divide (for 10 mi \2\ 6 Hours or

                              1,000 mi\2\ for One Duration Between 6 and 72 Hours)

----------------------------------------------------------------------------------------------------------------

                                                        Storm center                                    Duration

                                   Index -----------------------------------------                         for

           Storm date               No.                                            Latitude  Longitude    1,000

                                                  Town                State                               mi\2\

----------------------------------------------------------------------------------------------------------------

Aug. 11, 1890...................       1  Palmetto...........  NV................  37[deg]2  117[deg]4  ........

                                                                                     7[min]     2[min]

Aug. 12, 1891...................       2  Campo..............  CA................  32[deg]3  116[deg]2  ........

                                                                                     6[min]     8[min]

Aug. 28, 1898...................       3  Ft. Mohave.........  AZ................  35[deg]0  114[deg]3  ........

                                                                                     3[min]     6[min]

Oct. 4-6, 1911..................       4  Gladstone..........  CO................  37[deg]5  107[deg]3  ........

                                                                                     3[min]     9[min]

Dec. 29, 1913-Jan. 3, 1914......       5  ...................  CA................  39[deg]5  121[deg]2  ........

                                                                                     5[min]     5[min]

Feb. 17-22, 1914................       6  Colby Ranch........  CA................  34[deg]1  118[deg]0  ........

                                                                                     8[min]     7[min]

Feb. 20-25, 1917................       7  ...................  CA................  37[deg]3  119[deg]3  ........

                                                                                     5[min]     6[min]

Sept. 13, 1918..................       8  Red Bluff..........  CA................  40[deg]1  122[deg]1  ........

                                                                                     0[min]     4[min]

Feb. 26-Mar 4, 1938.............       9  ...................  CA................  34[deg]1  117[deg]1  ........

                                                                                     4[min]     1[min]

Mar. 30-Apr. 2, 1931............      10  ...................  ID................  46[deg]3  114[deg]5        24

                                                                                     0[min]     0[min]

Feb. 26, 1932...................      11  Big Four...........  WA................  48[deg]0  121[deg]3  ........

                                                                                     5[min]     0[min]

Nov. 21, 1933...................      12  Tatoosh Is.........  WA................  48[deg]2  124[deg]4  ........

                                                                                     3[min]     4[min]

Jan. 20-25, 1935................      13  ...................  WA................  47[deg]3  123[deg]3         6

                                                                                     0[min]     0[min]

Jan. 20-25, 1935................      14  ...................  WA................  47[deg]0  122[deg]0        72

                                                                                     0[min]     0[min]

Feb. 4-8, 1937..................      15  Cyamaca Dam........  CA................  33[deg]0  116[deg]3  ........

                                                                                     0[min]     5[min]

Dec. 9-12, 1937.................      16  ...................  CA................  38[deg]5  122[deg]4  ........

                                                                                     1[min]     3[min]

Feb. 27-Mar. 4, 1938............      17  ...................  AZ................  34[deg]5  111[deg]4        12

                                                                                     7[min]     4[min]

Jan. 19-24, 1943................      18  ...................  CA................  37[deg]3  119[deg]2        18

                                                                                     5[min]     5[min]

Jan. 19-24, 1943................      19  Hoegee's Camp......  CA................  34[deg]1  118[deg]0  ........

                                                                                     3[min]     2[min]

Jan. 30-Feb. 3, 1945............      20  ...................  CA................  37[deg]3  119[deg]3  ........

                                                                                     5[min]     0[min]

Dec. 27, 1945...................      21  Mt. Tamalpias......  CA................  37[deg]5  122[deg]3  ........

                                                                                     4[min]     4[min]

Nov. 13-21, 1950................      22  ...................  CA................  36[deg]3  118[deg]3        24

                                                                                     0[min]     0[min]

Aug. 25-30, 1951................      23  ...................  AZ................  34[deg]0  112[deg]2        72

                                                                                     7[min]     1[min]

July 19, 1955...................      24  Chiatovich Flat....  CA................  37[deg]4  118[deg]1  ........

                                                                                     4[min]     5[min]

Aug. 16, 1958...................      25  Morgan.............  UT................  41[deg]0  111[deg]3  ........

                                                                                     3[min]     8[min]

Sept. 18, 1959..................      26  Newton.............  CA................  40[deg]2  122[deg]1  ........

                                                                                     2[min]     2[min]

June 7-8, 1964..................      27  Nyack Ck...........  MT................  48[deg]3  113[deg]3        12

                                                                                     0[min]     8[min]

Sept. 3-7, 1970.................      28  ...................  UT................  37[deg]3  109[deg]0         6

                                                                                     8[min]     4[min]

Sept. 3-7, 1970.................      29  ...................  AZ................  33[deg]4  110[deg]5         6

                                                                                     9[min]     6[min]

June 7, 1972....................      30  Bakersfield........  CA................  35[deg]2  119[deg]0  ........

                                                                                     5[min]     3[min]

Dec. 9-12, 1937.................      31  ...................  CA................  39[deg]4  121[deg]3        48

                                                                                     5[min]     0[min]

----------------------------------------------------------------------------------------------------------------





[[Page 280]]



[GRAPHIC] [TIFF OMITTED] TC31OC91.012





[[Page 281]]



[GRAPHIC] [TIFF OMITTED] TC31OC91.013





[[Page 282]]



[GRAPHIC] [TIFF OMITTED] TC31OC91.014





[[Page 283]]



[GRAPHIC] [TIFF OMITTED] TC31OC91.015





[[Page 284]]



[GRAPHIC] [TIFF OMITTED] TC31OC91.016





[[Page 285]]



Appendix D to Sec.  222.6--Recommended Guidelines for Safety Inspection 

                                 of Dams



        Department of the Army--Office of the Chief of Engineers



                                 Preface



    The recommended guidelines for the safety inspection of dams were 

prepared to outline principal factors to be weighed in the determination 

of existing or potential hazards and to define the scope of activities 

to be undertaken in the safety inspection of dams. The establishment of 

rigid criteria or standards is not intended. Safety must be evaluated in 

the light of peculiarities and local conditions at a particular dam and 

in recognition of the many factors involved, some of which may not be 

precisely known. This can only be done by competent, experienced 

engineering judgment, which the guidelines are intended to supplement 

and not supplant. The guidelines are intended to be flexible, and the 

proper flexibility must be achieved through the employment of 

experienced engineering personnel.

    Conditions found during the investigation which do not meet 

guideline recommendations should be assessed by the investigator as to 

their import from the standpoint of the involved degree of risk. Many 

deviations will not compromise project safety and the investigator is 

expected to identify them in this manner if that is the case. Others 

will involve various degrees of risk, the proper evaluation of which 

will afford a basis for priority of subsequent attention and possible 

remedial action.

    The guidelines present procedures for investigating and evaluating 

existing conditions for the purpose of identifying deficiencies and 

hazardous conditions. The two phases of investigation outlined in the 

guidelines are expected to accomplish only this and do not encompass in 

scope the engineering which will be required to perform the design 

studies for corrective modification work.

    It is recognized that some States may have established or will adopt 

inspection criteria incongruous in some respects with these guidelines. 

In such instances assessments of project safety should recognize the 

State's requirements as well as guideline recommendations.

    The guidelines were developed with the help of several Federal 

agencies and many State agencies, professional engineering 

organizations, and private engineers. In reviewing two drafts of the 

guidelines they have contributed many helpful suggestions. Their 

contributions are deeply appreciated and have made it possible to evolve 

a document representing a consensus of the engineering fraternity. As 

experience is gained with use of the guidelines, suggestions for future 

revisions will be generated. All such suggestions should be directed to 

the Chief of Engineers, U.S. Army, DAEN-CWE-D, Washington, D.C. 20314.



          Recommended Guidelines for Safety Inspection of Dams



                            Table of Contents



                                 Preface



                         Chapter 1--Introduction



Para.

1.1 Purpose.

1.2 Applicability.

1.3 Authority.



                     Chapter 2--General Requirements



2.1 Classification of dams.

2.1.1 Size.

2.1.2 Hazard potential.

2.2 Selection of dams to be investigated.

2.3 Technical investigations.

2.4 Qualifications of investigators.

2.5 Reports.



                    Chapter 3--Phase I Investigation



3.1 Purpose.

3.2 Scope.

3.3 Engineering data.

3.4 Field inspections.

3.5 Evaluation of hydraulic and hydrologic features.

3.5.1 Design data.

3.5.2 Experience data.

3.6 Evaluation of structural stability.

3.6.1 Design and construction data.

3.6.2 Operating records.

3.6.3 Post contruction changes.

3.6.4 Seismic stability.



                    Chapter 4--Phase II Investigation



4.1 Purpose.

4.2 Scope.

4.3 Hydraulic and hydrologic analysis.

4.3.1 Maximum water surface based on SDF peak inflow.

4.3.1.1 Peak for 100-year flood.

4.3.1.2 Peak for PMF or fraction thereof.

4.3.2 Maximum water surface based on SDF hydrograph.

4.3.3 Acceptable procedures.

4.3.4 Freeboard allowances.

4.4 Stability investigations.

4.4.1 Foundation and material investigations.

4.4.2 Stability assessment.

4.4.2.1 Seismic stability.

4.4.2.2 Clay shale foundation.

4.4.3 Embankment dams.

4.4.3.1 Liquefaction.

4.4.3.2 Shear failure.

4.4.3.3 Loading conditions.

4.4.3.4 Safety factors.

4.4.3.5 Seepage failure.

4.4.3.6 Seepage analyses.



[[Page 286]]



4.4.4 Concrete dams and appurtenant structures.

4.4.4.1 Requirements for stability.

4.4.4.2 Loads.

4.4.4.3 Stresses.

4.4.4.4 Overturning.

4.4.4.5 Sliding.

4.4.4.5.1 Sliding resistance.

4.4.4.5.2 Downstream resistance.

4.4.4.5.3 Safety factor.



                           Chapter 5--Reports



5.1 General.

5.2 Preparation of report.

5.2.1 Phase I reports.

5.2.2 Phase II reports.



                                 Tables



Table

1 Size classification.

2 Hazard potential classification.

3 Hydrologic evaluation guidelines.

4 Factors of safety (embankment dams).



                                 Figures



Fig.

1 Seismic zone map of contiguous States.

2 Seismic zone map of California, Nevada and Arizona.

3 Seismic zone map of Alaska.

4 Seismic zone map of Hawaii.

5 Design envelope for Case I (Table 4).

6 Design envelope for Cases II and III (Table 4).



                               Appendixes



Appendix I to App. D--Engineering data

Appendix II to App. D--Inspection items

Appendix III to App. D--Pub. L. 92-367



                         Chapter 1--Introduction



    1.1. Purpose. This document provides recommended guidelines for the 

inspection and evaluation of dams to determine if they constitute 

hazards to human life or property.

    1.2. Applicability. The procedures and guidelines outlined in this 

document apply to the inspection and evaluation of all dams as defined 

in the National Dam Inspection Act, Public Law 92-367. Included in this 

program are all artificial barriers together with appurtenant works 

which impound or divert water and which (1) are twenty-five feet or more 

in height or (2) have an impounding capacity of fifty acre-feet or more. 

Not included are barriers which are six feet or less in height, 

regardless of storage capacity, or barriers which have a storage 

capacity at maximum water storage elevation of fifteen acre-feet or less 

regardless of height.

    1.3. Authority. The Dam Inspection Act, Public Law 92-367 (Appendix 

III), authorized the Secretary of the Army, through the Corps of 

Engineers, to initiate a program of safety inspection of dams throughout 

the United States. The Chief of Engineers issues these guidelines 

pursuant to that authority.



                     Chapter 2--General Requirements



    2.1. Classification of dams. Dams should be classified in accordance 

with size and hazard potential in order to formulate a priority basis 

for selecting dams to be included in the inspection program and also to 

provide compatibility between guideline requirements and involved risks. 

When possible the initial classifications should be based upon 

information listed in the National Inventory of Dams with respect to 

size, impoundment capacity and hazard potential. It may be necessary to 

reclassify dams when additional information becomes available.

    2.1.1. Size. The classification for size based on the height of the 

dam and storage capacity should be in accordance with Table 1. The 

height of the dam is established with respect to the maximum storage 

potential measured from the natural bed of the stream or watercourse at 

the downstream toe of the barrier, or if it is not across a stream or 

watercourse, the height from the lowest elevation of the outside limit 

of the barrier, to the maximum water storage elevation. For the purpose 

of determining project size, the maximum storage elevation may be 

considered equal to the top of dam elevation. Size classification may be 

determined by either storage or height, whichever gives the larger size 

category.



                      Table 1--Size Classification

------------------------------------------------------------------------

                                                Impoundment

            Category             ---------------------------------------

                                    Storage (ac-ft)       Height (ft)

------------------------------------------------------------------------

Small...........................  <1,000 and =50.             eq>=25.

Intermediate....................  =1,000   =40 and

                                   and <50,000.        <100.

Large...........................  =50,000  =100.

------------------------------------------------------------------------



    2.1.2. Hazard Potential. The classification for potential hazards 

should be in accordance with Table 2. The hazards pertain to potential 

loss of human life or property damage in the area downstream of the dam 

in event of failure or misoperation of the dam or appurtenant 

facilities. Dams conforming to criteria for the low hazard potential 

category generally will be located in rural or agricultural areas where 

failure may damage farm buildings, limited agricultural land, or 

township and country roads. Significant hazard potential category 

structures will be those located in predominantly rural or agricultural 

areas where failure may damage isolated homes, secondary highways or 

minor railroads or cause interruption of use or service of relatively 

important public utilities. Dams in the high hazard potential category 

will be those located where failure may cause serious damage to homes, 

extensive agricultural, industrial and commercial facilities, important 

public utilities, main highways, or railroads.



[[Page 287]]







                                    Table 2--Hazard Potential Classification

----------------------------------------------------------------------------------------------------------------

                                               Loss of life (extent of             Economic loss (extent of

                Category                             development)                        development)

----------------------------------------------------------------------------------------------------------------

Low....................................  None expected (No permanent          Minimal (Undeveloped to occasional

                                          structures for human habitation).    structures or agriculture).

Significant............................  Few (No urban developments and no    Appreciable (Notable agriculture,

                                          more than a small number of          industry or structures).

                                          inhabitable structures).

High...................................  More than few......................  Excessive (Extensive community,

                                                                               industry or agriculture).

----------------------------------------------------------------------------------------------------------------



    2.2. Selection of dams to be investigated. The selection of dams to 

be investigated should be based upon an assessment of existing 

developments in flood hazard areas. Those dams possessing a hazard 

potential classified high or significant as indicated in Table 2 should 

be given first and second priorities, respectively, in the inspection 

program. Inspection priorities within each category may be developed 

from a consideration of factors such as size classification and age of 

the dam, the population size in the downstream flood area, and potential 

developments anticipated in flood hazard areas.

    2.3. Technical Investigations. A detailed, systematic, technical 

inspection and evaluation should be made of each dam selected for 

investigation in which the hydraulic and hydrologic capabilities, 

structural stability and operational adequacy of project features are 

analyzed and evaluated to determine if the dam constitutes a danger to 

human life or property. The investigation should vary in scope and 

completeness depending upon the availability and suitability of 

engineering data, the validity of design assumptions and analyses and 

the condition of the dam. The minimum investigation will be designated 

Phase I, and an in-depth investigation designated Phase II should be 

made where deemed necessary. Phase I investigations should consist of a 

visual inspection of the dam, abutments and critical appurtenant 

structures, and a review of readily available engineering data. It is 

not intended to perform costly explorations or analyses during Phase I. 

Phase II investigations should consist of all additional engineering 

investigations and analyses found necessary by results of the Phase I 

investigation.

    2.4. Qualifications of investigators. The technical investigations 

should be conducted under the direction of licensed professional 

engineers experienced in the investigation, design, construction and 

operation of dams, applying the disciplines of hydrologic, hydraulic, 

soils and structural engineering and engineering geology. All field 

inspections should be conducted by qualified engineers, engineering 

geologists and other specialists, including experts on mechanical and 

electrical operation of gates and controls, knowledgeable in the 

investigation, design, construction and operation of dams.



                    Chapter 3--Phase I Investigation



    3.1. Purpose. The primary purpose of the Phase I investigation 

program is to identify expeditiously those dams which may pose hazards 

to human life or property.

    3.2. Scope. The Phase I investigation will develop an assessment of 

the general condition with respect to safety of the project based upon 

available data and a visual inspection, determine any need for emergency 

measures and conclude if additional studies, investigation and analyses 

are necessary and warranted. A review will be made of pertinent existing 

and available engineering data relative to the design, construction and 

operation of the dam and appurtenant structures, including electrical 

and mechanical operating equipment and measurements from inspection and 

performance instruments and devices; and a detailed systematic visual 

inspection will be performed of those features relating to the stability 

and operational adequacy of the project. Based upon findings of the 

review of engineering data and the visual inspection, an evaluation will 

be made of the general condition of the dam, including where possible 

the assessment of the hydraulic and hydrologic capabilities and the 

structural stability.

    3.3. Engineering data. To the extent feasible the engineering data 

listed in Appendix I relating to the design, construction and operation 

of the dam and appurtenant structures, should be collected from existing 

records and reviewed to aid in evaluating the adequacy of hydraulic and 

hydrologic capabilities and stability of the dam. Where the necessary 

engineering data are unavailable, inadequate or invalid, a listing 

should be made of those specific additional data deemed necessary by the 

engineer in charge of the investigation and included in the Phase I 

report.

    3.4. Field inspections. The field inspection of the dam, appurtenant 

stuctures, reservoir area, and downstream channel in the vicinity of the 

dam should be conducted in a systematic manner to minimize the 

possibility of any significant feature being overlooked. A detailed 

checklist should be developed and followed for each dam inspected to 

document



[[Page 288]]



the examination of each significant structural and hydraulic feature 

including electrical and mechanical equipment for operation of the 

control facilities that affect the safety of the dam.

    3.4.1. Particular attention should be given to detecting evidence of 

leakage, erosion, seepage, slope instability, undue settlement, 

displacement, tilting, cracking, deterioration, and improper functioning 

of drains and relief wells. The adequacy and quality of maintenance and 

operating procedures as they pertain to the safety of the dam and 

operation of the control facilities should also be assessed.

    3.4.2. Photographs and drawings should be used freely to record 

conditions in order to minimize descriptions.

    3.4.3. The field inspection should include appropriate features and 

items, including but not limited to those listed in Appendix II, which 

may influence the safety of the dam or indicate potential hazards to 

human life or property.

    3.5. Evaluation of hydraulic and hydrologic Features.

    3.5.1. Design data. Original hydraulic and hydrologic design 

assumptions obtained from the project records should be assessed to 

determine their acceptability in evaluating the safety of the dam. All 

constraints on water control such as blocked entrances, restrictions on 

operation of spillway and outlet gates, inadequate energy dissipators or 

restrictive channel conditions, significant reduction in reservoir 

capacity by sediment deposits and other factors should be considered in 

evaluating the validity of discharge ratings, storage capacity, 

hydrographs, routings and regulation plans. The discharge capacity and/

or storage capacity should be capable of safely handling the recommended 

spillway design flood for the size and hazard potential classification 

of the dam as indicated in Table 3. The hydraulic and hydrologic 

determinations for design as obtained from project records will be 

acceptable if conventional techniques similar to the procedures outlined 

in paragraph 4.3. were used in obtaining the data. When the project 

design flood actually used exceeds the recommended spillway design 

flood, from Table 3, the project design flood will be acceptable in 

evaluating the safety of the dam.



                Table 3--Hydrologic Evaluation Guidelines

                  [Recommended spillway design floods]

------------------------------------------------------------------------

                                                        Spillway design

             Hazard                      Size           flood (SDF) \1\

------------------------------------------------------------------------

Low.............................  Small.............  50 to 100-yr

                                                       frequency.

                                  Intermediate......  100-yr to \1/2\

                                                       PMF.

                                  Large.............  \1/2\ PMF to PMF.

Significant.....................  Small.............  100-yr to \1/2\

                                                       PMF.

                                  Intermediate......  \1/2\ PMF to PMF.

                                  Large.............  PMF.

High............................  Small.............  \1/2\ PMF to PMF.

                                  Intermediate......  PMF.

                                  Large.............  PMF.

------------------------------------------------------------------------

\1\ The recommended design floods in this column represent the magnitude

  of the spillway design flood (SDF), which is intended to represent the

  largest flood that need be considered in the evaluation of a given

  project, regardless of whether a spillway is provided; i.e., a given

  project should be capable of safely passing the appropriate SDF. Where

  a range of SDF is indicated, the magnitude that most closely relates

  to the involved risk should be selected.



1000-yr=100-Year Exceedence Interval. The flood magnitude expected to be 

exceeded, on the average, of once in 100 years. It may also be expressed 

as an exceedence frequency with a one-percent chance of being exceeded 

in any given year.

PMF=Probable Maximum Flood. The flood that may be expected from the most 

severe combination of critical meteorologic and hydrologic conditions 

that are reasonably possible in the region. The PMF is derived from 

probable maximum precipitation (PMP), which information is generally 

available from the National Weather Service, NOAA. Most Federal agencies 

apply reduction factors to the PMP when appropriate. Reductions may be 

applied because rainfall isohyetals are unlikely to conform to the exact 

shape of the drainage basin and/or the storm is not likely to center 

exactly over the drainage basin. In some cases local topography will 

cause changes from the generalized PMP values, therefore it may be 

advisable to contact Federal construction agencies to obtain the 

prevailing practice in specific areas.

    3.5.2. Experience data. In some cases where design data are lacking, 

an evaluation of overtopping potential may be based on watershed 

characteristics and rainfall and reservoir records. An estimate of the 

probable maximum flood may also be developed from a conservative, 

generalized comparison of the drainage area size and the magnitude of 

recently adopted probable maximum floods for damsites in comparable 

hydrologic regions. Where the review of such experience data indicates 

that the recommended spillway design flood would not cause overtopping 

additional hydraulic and hydrologic determinations will be unnecessary.

    3.6. Evaluation of structural stability. The Phase I evaluations of 

structural adequacy of project features are expected to be based 

principally on existing conditions as revealed by the visual inspection, 

together with available design and construction information and records 

of performance. The objectives are to determine the existence of 

conditions which are hazardous, or which with time might develop into 

safety hazards,



[[Page 289]]



and to formulate recommendations pertaining to the need for any 

additional studies, investigations, or analyses. The results of this 

phase of the inspection must rely very substantially upon the experience 

and judgment of the inspecting engineer.

    3.6.1. Design and construction data. The principal design 

assumptions and analyses obtained from the project records should be 

assessed. Original design and construction records should be used 

judiciously, recognizing the restricted applicability of such data as 

material strengths and permeabilities, geological factors and 

construction descriptions. Original stability studies and analyses 

should be acceptable if conventional techniques and procedures similar 

to those outlined in paragraph 4.4 were employed, provided that review 

of operational and performance data confirm that the original design 

assumptions were adequately conservative. The need for such analyses 

where either none exist or the originals are incomplete or 

unsatisfactory will be determined by the inspecting engineer based upon 

other factors such as condition of structures, prior maximum loadings 

and the hazard degree of the project. Design assumptions and analyses 

should include all applicable loads including earthquake and indicate 

the structure's capability to resist overturning, sliding and 

overstressing with adequate factors of safety. In general seepage and 

stability analyses comparable to the requirements of paragraph 4.4 

should be on record for all dams in the high hazard category and large 

dams in the significant hazard category. This requirement for other dams 

will be subject to the opinion of the inspecting engineer.

    3.6.2. Operating records. The performance of structures under prior 

maximum loading conditions should in some instances provide partial 

basis for stability evaluation. Satisfactory experience under loading 

conditions not expected to be exceeded in the future should generally be 

indicative of satisfactory stability, provided adverse changes in 

physical conditions have not occurred. Instrumentation observations of 

forces, pressures, loads, stresses, strains, displacements, deflections 

or other related conditions should also be utilized in the safety 

evaluation. Where such data indicate abnormal behavior, unsafe movement 

or deflections, or loadings which adversely affect the stability or 

functioning of the structure, prompt reporting of such circumstances is 

required without the delay for preparation of the official inspection 

report.

    3.6.3. Post construction changes. Data should be collected on 

changes which have occurred since project construction that might 

influence the safety of the dam such as road cuts, quarries, mining and 

groundwater changes.

    3.6.4. Seismic stability. An assessment should be made of the 

potential vulnerability of the dam to seismic events and a 

recommendation developed with regard to the need for additional seismic 

investigation. In general, projects located in Seismic Zones 0, 1 and 2 

may be assumed to present no hazard from earthquake provided static 

stability conditions are satisfactory and conventional safety margins 

exist. Dams in Zones 3 and 4 should, as a minimum, have on record 

suitable analyses made by conventional equivalent static load methods. 

The seismic zones together with appropriate coefficients for use in such 

analyses are shown in Figures 1 through 4. Boundary lines are 

approximate and in the event of doubt about the proper zone, the higher 

zone should be used. All high hazard category dams in Zone 4 and high 

hazard dams of the hydraulic fill type in Zone 3 should have a stability 

assessment based upon knowledge of regional and local geology, 

engineering seismology, in situ properties of materials and appropriate 

dynamic analytical and testing procedures. The assessment should include 

the possibility of physical displacement of the structures due to 

movements along active faults. Departure from this general guidance 

should be made whenever in the judgment of the investigating engineer 

different seismic stability requirements are warranted because of local 

geological conditions or other reasons.



                    Chapter 4--Phase II Investigation



    4.1. Purpose. The Phase II investigation will be supplementary to 

Phase I and should be conducted when the results of the Phase I 

investigation indicate the need for additional in-depth studies, 

investigations or analyses.

    4.2. Scope. The Phase II investigation should include all additional 

studies, investigations and analyses necessary to evaluate the safety of 

the dam. Included, as required, will be additional visual inspections, 

measurements, foundation exploration and testing, materials testing, 

hydraulic and hydrologic analysis and structural stability analyses.

    4.3. Hydraulic and hydrologic analysis. Hydraulic and hydrologic 

capabilities should be determined using the following criteria and 

procedures. Depending on the project characteristics, either the 

spillway design flood peak inflow or the spillway design flood 

hydrograph should be the basis for determining the maximum water surface 

elevation and maximum outflow. If the operation or failure of upstream 

water control projects would have significant impact on peak flow or 

hydrograph analyses, the impact should be assessed.

    4.3.1. Maximum water surface based on SDF peak inflow. When the 

total project discharge capability at maximum pool exceeds the peak 

inflow of the recommended SDF, and



[[Page 290]]



operational constraints would not prevent such a release at controlled 

projects, a reservoir routing is not required. The maximum discharge 

should be assumed equal to the peak inflow of the spillway design flood. 

Flood volume is not controlling in this situation and surcharge storage 

is either absent or is significant only to the extent that it provides 

the head necessary to develop the release capability required.

    4.3.1.1. Peak for 100-year flood. When the 100-year flood is 

applicable under the provisions of Table 3 and data are available, the 

spillway design flood peak inflow may be determined by use of ``A 

Uniform Technique for Determining Flood Frequencies,'' Water Resources 

Council (WRC), Hydrology Committee, Bulletin 15, December 1967. Flow 

frequency information from regional analysis is generally preferred over 

single station results when available and appropriate. Rainfall-runoff 

techniques may be necessary when there are inadequate runoff data 

available to make a reasonable estimate of flow frequency.

    4.3.1.2. Peak for PMF or fraction thereof. When either the Probable 

Maximum Flood peak or a fraction thereof is applicable under the 

provisions of Table 3, the unit hydrograph--infiltration loss technique 

is generally the most expeditious method of computing the spillway 

design flood peak for most projects. This technique is discussed in the 

following paragraph.

    4.3.2. Maximum water surface based on SDF hydrograph. Both peak and 

volume are required in this analysis. Where surcharge storage is 

significant, or where there is insufficient discharge capability at 

maximum pool to pass the peak inflow of the SDF, considering all 

possible operational constraints, a flood hydrograph is required. When 

there are upstream hazard areas that would be imperiled by fast rising 

reservoirs levels, SDF hydrographs should be routed to ascertain 

available time for warning and escape. Determination of probable maximum 

precipitation or 100-year precipitation, which ever is applicable, and 

unit hydrographs or runoff models will be required, followed by the 

determination of the PMF or 100-year flood. Conservative loss rates 

(significantly reduced by antecedent rainfall conditions where 

appropriate) should be estimated for computing the rainfall excess to be 

utilized with unit hydrographs. Rainfall values are usually arranged 

with gradually ascending and descending rates with the maximum rate late 

in the storm. When applicable, conservatively high snowmelt runoff rates 

and appropriate releases from upstream projects should be assumed. The 

PMP may be obtained from National Weather Service (NWS) publications 

such as Hydrometeorological Report (HMR) 33. Special NWS publications 

for particular areas should be used when available. Rainfall for the 

100-year frequency flood can be obtained from the NWS publication 

``Rainfall Frequency Atlas of the United States,'' Technical Paper No. 

40; Atlas 2, ``Precipitation Frequency Atlas of Western United States;'' 

or other NWS publications. The maximum water surface elevation and 

spillway design flood outflow are then determined by routing the inflow 

hydrograph through the reservoir surcharge storage, assuming a starting 

water surface at the bottom of surcharge storage, or lower when 

appropriate. For projects where the bottom of surcharge space is not 

distinct, or the flood control storage space (exclusive of surcharge) is 

appreciable, it may be appropriate to select starting water surface 

elevations below the top of the flood control storage for routings. 

Conservatively high starting levels should be estimated on the basis of 

hydrometeorological conditions reasonably characteristic for the region 

and flood release capability of the project. Necessary adjustment of 

reservoir storage capacity due to existing or future sediment or other 

encroachment may be approximated when accurate determination of 

deposition is not practicable.

    4.3.3. Acceptable procedures. Techniques for performing hydraulic 

and hydrologic analyses are generally available from publications 

prepared by Federal agencies involved in water resources development or 

textbooks written by the academic community. Some of these procedures 

are rather sophisticated and require expensive computational equipment 

and large data banks. While results of such procedures are generally 

more reliable than simplified methods, their use is generally not 

warranted in studies connected with this program unless they can be 

performed quickly and inexpensively. There may be situations where the 

more complex techniques have to be employed to obtain reliable results; 

however, these cases will be exceptions rather than the rule. Whenever 

the acceptability of procedures is in question, the advice of competent 

experts should be sought. Such expertise is generally available in the 

Corps of Engineers, Bureau of Reclamation and Soil Conservation Service. 

Many other agencies, educational facilities and private consultants can 

also provide expert advice. Regardless of where such expertise is based, 

the qualification of those individuals offering to provide it should be 

carefully examined and evaluated.

    4.3.4. Freeboard allowances. Guidelines on specific minimum 

freeboard allowances are not considered appropriate because of the many 

factors involved in such determinations. The investigator will have to 

assess the critical parameters for each project and develop its minimum 

requirement. Many projects are reasonably safe without freeboard 

allowance because they are designed for overtopping, or other factors 

minimize possible overtopping. Conversely,



[[Page 291]]



freeboard allowances of several feet may be necessary to provide a safe 

condition. Parameters that should be considered include the duration of 

high water levels in the reservoir during the design flood; the 

effective wind fetch and reservoir depth available to support wave 

generation; the probability of high wind speed occurring from a critical 

direction; the potential wave runup on the dam based on roughness and 

slope; and the ability of the dam to resist erosion from overtopping 

waves.

    4.4 Stability investigations. The Phase II stability investigations 

should be compatible with the guidelines of this paragraph.

    4.4.1 Foundation and material investigations. The scope of the 

foundation and materials investigation should be limited to obtaining 

the information required to analyze the structural stability and to 

investigate any suspected condition which would adversely affect the 

safety of the dam. Such investigations may include borings to obtain 

concrete, embankment, soil foundation, and bedrock samples; testing 

specimens from these samples to determine the strength and elastic 

parameters of the materials, including the soft seams, joints, fault 

gouge and expansive clays or other critical materials in the foundation; 

determining the character of the bedrock including joints, bedding 

planes, fractures, faults, voids and caverns, and other geological 

irregularities; and installing instruments for determining movements, 

strains, suspected excessive internal seepage pressures, seepage 

gradients and uplift forces. Special investigations may be necessary 

where suspect rock types such as limestone, gypsum, salt, basalt, 

claystone, shales or others are involved in foundations or abutments in 

order to determine the extent of cavities, piping or other deficiencies 

in the rock foundation. A concrete core drilling program should be 

undertaken only when the existence of significant structural cracks is 

suspected or the general qualitative condition of the concrete is in 

doubt. The tests of materials will be necessary only where such data are 

lacking or are outdated.

    4.4.2. Stability assessment. Stability assessments should utilize in 

situ properties of the structure and its foundation and pertinent 

geologic information. Geologic information that should be considered 

includes groundwater and seepage conditions; lithology, stratigraphy, 

and geologic details disclosed by borings, ``as-built'' records, and 

geologic interpretation; maximum past overburden at site as deduced from 

geologic evidence; bedding, folding and faulting; joints and joint 

systems; weathering; slickensides, and field evidence relating to 

slides, faults, movements and earthquake activity. Foundations may 

present problems where they contain adversely oriented joints, 

slickensides or fissured material, faults, seams of soft materials, or 

weak layers. Such defects and excess pore water pressures may contribute 

to instability. Special tests may be necessary to determine physical 

properties of particular materials. The results of stability analyses 

afford a means of evaluating the structure's existing resistance to 

failure and also the effects of any proposed modifications. Results of 

stability analyses should be reviewed for compatibility with performance 

experience when possible.

    4.4.2.1. Seismic stability. The inertial forces for use in the 

conventional equivalent static force method of analysis should be 

obtained by multiplying the weight by the seismic coefficient and should 

be applied as a horizontal force at the center of gravity of the section 

or element. The seismic coefficients suggested for use with such 

analyses are listed in Figures 1 through 4. Seismic stability 

investigations for all high hazard category dams located in Seismic Zone 

4 and high hazard dams of the hydraulic fill type in Zone 3 should 

include suitable dynamic procedures and analyses. Dynamic analyses for 

other dams and higher seismic coefficients are appropriate if in the 

judgment of the investigating engineer they are warranted because of 

proximity to active faults or other reasons. Seismic stability 

investigations should utilize ``state-of-the-art'' procedures involving 

seismological and geological studies to establish earthquake parameters 

for use in dynamic stability analyses and, where appropriate, the 

dynamic testing of materials. Stability analyses may be based upon 

either time-history or response spectra techniques. The results of 

dynamic analyses should be assessed on the basis of whether or not the 

dam would have sufficient residual integrity to retain the reservoir 

during and after the greatest or most adverse earthquake which might 

occur near the project location.

    4.4.2.2. Clay shale foundation. Clay shale is a highly 

overconsolidated sedimentary rock comprised predominantly of clay 

minerals, with little or no cementation. Foundations of clay shales 

require special measures in stability investigations. Clay shales, 

particularly those containing montmorillonite, may be highly susceptible 

to expansion and consequent loss of strength upon unloading. The shear 

strength and the resistance to deformation of clay shales may be quite 

low and high pore water pressures may develop under increase in load. 

The presence of slickensides in clay shales is usually an indication of 

low shear strength. Prediction of field behavior of clay shales should 

not be based solely on results of conventional laboratory tests since 

they may be misleading. The use of peak shear strengths for clay shales 

in stability analyses may be unconservative because of nonuniform stress 

distribution and possible progressive failures. Thus the available shear 

resistance may be less than if the peak shear strength



[[Page 292]]



were mobilized simultaneously along the entire failure surface. In such 

cases, either greater safety factors or residual shear strength should 

be used.

    4.4.3. Embankment dams.

    4.4.3.1. Liquefaction. The phenomenon of liquefaction of loose, 

saturated sands and silts may occur when such materials are subjected to 

shear deformation or earthquake shocks. The possibility of liquefaction 

must presently be evaluated on the basis of empirical knowledge 

supplemented by special laboratory tests and engineering judgment. The 

possiblitity of liquefaction in sands diminishes as the relative density 

increases above approximately 70 percent. Hydraulic fill dams in Seismic 

Zones 3 and 4 should receive particular attention since such dams are 

susceptible to liquefaction under earthquake shocks.

    4.4.3.2. Shear failure. Shear failure is one in which a portion of 

an embankment or of an embankment and foundation moves by sliding or 

rotating relative to the remainder of the mass. It is conventionally 

represented as occurring along a surface and is so assumed in stability 

analyses, although shearing may occur in a zone of substantial 

thickness. The circular arc or the sliding wedge method of analyzing 

stability, as pertinent, should be used. The circular arc method is 

generally applicable to essentially homogeneous embankments and to soil 

foundations consisting of thick deposits of fine-grained soil containing 

no layers significantly weaker than other strata in the foundation. The 

wedge method is generally applicable to rockfill dams and to earth dams 

on foundations containing weak layers. Other methods of analysis such as 

those employing complex shear surfaces may be appropriate depending on 

the soil and rock in the dam and foundation. Such methods should be in 

reputable usage in the engineering profession.

    4.4.3.3. Loading conditions. The loading conditions for which the 

embankment structures should be investigated are (I) Sudden drawdown 

from spillway crest elevation or top of gates, (II) Partial pool, (III) 

Steady state seepage from spillway crest elevation or top of gate 

elevation, and (IV) Earthquake. Cases I and II apply to upstream slopes 

only; slopes; and Case IV applies to both upstream and downstream Case 

III applies to downstream slopes. A summary of suggested strengths and 

safety factors are shown in Table 4.



                                          Table 4--Factors of Safety\1\

----------------------------------------------------------------------------------------------------------------

                                           Factor

       Case and loading condition            of         Shear \2\ strength                   Remarks

                                           safety

----------------------------------------------------------------------------------------------------------------

I Sudden drawdown from spillway crest or  \3\ 1.2  Minimum composite of R and   Within the drawdown zone

 top of gates to minimum drawdown                   S shear strengths. See       submerged unit weights of

 elevation.                                         Figure 5.                    materials are used for

                                                                                 computing forces resisting

                                                                                 sliding and saturated unit

                                                                                 weights are used for computing

                                                                                 forces contributing to sliding.

II Partial pool with assumed horizontal       1.5  R+S/2 for RS........   of R and

                                                                                 S shear strengths. See Figure

                                                                                 6.

III Steady seepage from spillway crest        1.5  Same as Case II............

 or top of gates with Kh/Kv=9 assumed\4\.

IV Earthquake (Cases II and III with          1.0  (\5\ ).....................  See Figures 1 through 4 for

 seismic loading).                                                               Seismic Coefficients.

----------------------------------------------------------------------------------------------------------------

\1\ Not applicable to embankments on clay shale foundation. Experience has indicated special problems in

  determination of design shear strengths for clay shale foundations and acceptable safety factors should be

  compatible with the confidence level in shear strength assumptions.

\2\ Other strength assumptions may be used if in common usage in the engineering profession.

\3\ The safety factor should not be less than 1.5 when drawdown rate and pore water pressure developed from flow

  nets are used in stability analyses.

\4\ Kh/Kv is the ratio of horizontal to vertical permeability. A minimum of 9 is suggested for use in compacted

  embankments and alluvial sediments.

\5\ Use shear strength for case analyzed without earthquake. It is not necessary to analyze sudden drawdown for

  earthquake loading. Shear strength tests are classified according to the controlled drainage conditions

  maintained during the test. R tests are those in which specimen drainage is allowed during consolidation (or

  swelling) under initial stress conditions, but specimen drainage is not allowed during application of shearing

  stresses. S tests allow full drainage during initial stress application and shearing is at a slow rate so that

  complete specimen drainage is permitted during the complete test.



    4.4.3.4. Safety factors. Safety factors for embankment dam stability 

studies should be based on the ratio of available shear strength to 

developed shear strength, SD :

[GRAPHIC] [TIFF OMITTED] TC15NO91.000



Where:



C=Cohesion

[phis]=Angle of internal friction

[sigma]=Normal stress



    The factors of safety listed in Table 4 are recommended as minimum 

acceptable. Final accepted factors of safety should depend upon the 

degree of confidence the investigating engineer has in the engineering 

data



[[Page 293]]



available to him. The consequences of a failure with respect to human 

life and property damage are important considerations in establishing 

factors of safety for specific investigations.

    4.4.3.5. Seepage failure. A critical uncontrolled underseepage or 

through seepage condition that develops during a rising pool can quickly 

reduce a structure which was stable under previous conditions, to a 

total structural failure. The visually confirmed seepage conditions to 

be avoided are (1) the exit of the phreatic surface on the downstream 

slope of the dam and (2) development of hydrostatic heads sufficient to 

create in the area downstream of the dam sand boils that erode materials 

by the phenomenon known as ``piping'' and (3) localized concentrations 

of seepage along conduits or through pervious zones. The dams most 

susceptible to seepage problems are those built of or on pervious 

materials of uniform fine particle size, with no provisions for an 

internal drainage zone and/or no underseepage controls.

    4.4.3.6. Seepage analyses. Review and modifications to original 

seepage design analyses should consider conditions observed in the field 

inspection and piezometer instrumentation. A seepage analysis should 

consider the permeability ratios resulting from natural deposition and 

from compaction placement of materials with appropriate variation 

between horizontal and vertical permeability. An underseepage analysis 

of the embankment should provide a critical gradient factor of safety 

for the maximum head condition of not less than 1.5 in the area 

downstream of the embankment.

[GRAPHIC] [TIFF OMITTED] TC15NO91.001



Where:



ic=Critical gradient

i=Design gradient

H=Uplift head at downstream toe of dam measured above tailwater

Hc=The critical uplift

Db=The thickness of the top impervious blanket at the 

downstream toe of the dam

[gamma]m=The estimated saturated unit weight of the material 

in the top impervious blanket

[gamma]w=The unit weight of water



    Where a factor of safety less than 1.5 is obtained the provision of 

an underseepage control system is indicated. The factor of safety of 1.5 

is a recommended minimum and may be adjusted by the responsible engineer 

based on the competence of the engineering data.

    4.4.4. Concrete dams and appurtenant structures.

    4.4.4.1. Requirements for stability. Concrete dams and structures 

appurtenant to embankment dams should be capable of resisting 

overturning, sliding and overstressing with adequate factors of safety 

for normal and maximum loading conditions.

    4.4.4.2. Loads. Loadings to be considered in stability analyses 

include the water load on the upstream face of the dam; the weight of 

the structure; internal hydrostatic pressures (uplift) within the body 

of the dam, at the base of the dam and within the foundation; earth and 

silt loads; ice pressure, seismic and thermal loads, and other loads as 

applicable. Where tailwater or backwater exists on the downstream side 

of the structure it should be considered, and assumed uplift pressures 

should be compatible with drainage provisions and uplift measurements if 

available. Where applicable, ice pressure should be applied to the 

contact surface of the structure of normal pool elevation. A unit 

pressure of not more than 5,000 pounds per square foot should be used. 

Normally, ice thickness should not be assumed greater than two feet. 

Earthquake forces should consist of the inertial forces due to the 

horizontal acceleration of the dam itself and hydrodynamic forces 

resulting from the reaction of the reservoir water against the 

structure. Dynamic water pressures for use in a conventional methods of 

analysis may be computed by means of the ``Westergaard Formula'' using 

the parabolic approximation (H.M. Westergaard, ``Water Pressures on Dams 

During Earthquakes,'' Trans., ASCE, Vol 98, 1933, pages 418-433), or 

similar method.

    4.4.4.3. Stresses. The analysis of concrete stresses should be based 

on in situ properties of the concrete and foundation. Computed maximum 

compressive stresses for normal operating conditions in the order of \1/

3\ or less of in situ strengths should be satisfactory. Tensile stresses 

in unreinforced concrete should be acceptable only in locations where 

cracks will not adversely affect the overall performance and stability 

of the structure. Foundation stresses should be such as to provide 

adequate safety against failure of the foundation material under all 

loading conditions.

    4.4.4.4. Overturning. A gravity structure should be capable of 

resisting all overturning forces. It can be considered safe against 

overturning if the resultant of all combinations of horizontal and 

vertical forces, excluding earthquake forces, acting above any 

horizontal plane through the structure or at its base is located within 

the middle third of the section. When earthquake is included the 

resultant should fall within the limits of the plane or base, and 

foundation pressures must be acceptable. When these requirements for 

location of the resultant are not satisfied the investigating engineer 

should assess the importance to stability of the deviations.

    4.4.4.5. Sliding. Sliding of concrete gravity structures and of 

abutment and foundation rock masses for all types of concrete dams



[[Page 294]]



should be evaluated by the shear-friction resistance concept. The 

available sliding resistance is compared with the driving force which 

tends to induce sliding to arrive at a sliding stability safety factor. 

The investigation should be made along all potential sliding paths. The 

critical path is that plane or combination of planes which offers the 

least resistance.

    4.4.4.5.1. Sliding resistance. Sliding resistance is a function of 

the unit shearing strength at no normal load (cohesion) and the angle of 

friction on a potential failure surface. It is determined by computing 

the maximum horizontal driving force which could be resisted along the 

sliding path under investigation. The following general formula is 

obtained from the principles of statics and may be derived by resolving 

forces parallel and perpendicular to the sliding plane:

[GRAPHIC] [TIFF OMITTED] TC15NO91.002



Where:



RR=Sliding Resistance (maximum horizontal driving force which 

can be resisted by the critical path)

[phis]=Angle of internal friction of foundation material or, where 

applicable, angle of sliding friction

V=Summation of vertical forces (including uplift)

c=Unit shearing strength at zero normal loading along potential failure 

plane

A=Area of potential failure plane developing unit shear strength ``c''

[alpha]=Angle between inclined plane and horizontal (positive for uphill 

sliding)



    For sliding downhill the angle [alpha] is negative and Equation (1) 

becomes:

[GRAPHIC] [TIFF OMITTED] TC15NO91.003



    When the plane of investigation is horizontal, and the angle [alpha] 

is zero and Equation (1) reduced to the following:

[GRAPHIC] [TIFF OMITTED] TC15NO91.004



    4.4.4.5.2. Downstream esistance. When the base of a concrete 

structure is embedded in rock or the potential failure plane lies below 

the base, the passive resistance of the downstream layer of rock may 

sometimes be utilized for sliding resistance. Rock that may be subjected 

to high velocity water scouring should not be used. The magnitude of the 

downstream resistance is the lesser of (a) the shearing resistance along 

the continuation of the potential sliding plane until it daylights or 

(b) the resistance available from the downstream rock wedge along an 

inclined plane. The theoretical resistance offered by the passive wedge 

can be computed by a formula equivalent to formula (3):

[GRAPHIC] [TIFF OMITTED] TC15NO91.005



Where:



Pp=Passive resistance of rock wedge

W=Weight (buoyant weight if applicable) of downstream rock wedge above 

inclined plane of resistance, plus any superimposed loads

[phis]=Angle of internal friction or, if applicable, angle of sliding 

friction

[alpha]=Angle between inclined failure plane and horizontal

c=Unit shearing strength at zero normal load along failure plane

A=Area of inclined plane of resistance



    When considering cross-bed shear through a relatively shallow, 

competent rock strut, without adverse jointing or faulting, W and 

[alpha] may be taken at zero and 45[deg], respectively, and an estimate 

of passive wedge resistance



[[Page 295]]



per unit width obtained by the following equation:

[GRAPHIC] [TIFF OMITTED] TC15NO91.006



Where:



D=Thickness of the rock strut



    4.4.4.5.3. Safety factor. The shear-friction safety factor is 

obtained by dividing the resistance RR by H, the summation of 

horizontal service loads to be applied to the structure:

[GRAPHIC] [TIFF OMITTED] TC15NO91.007



    When the downstream passive wedge contributes to the sliding 

resistance, the shear friction safety factor formula becomes:

[GRAPHIC] [TIFF OMITTED] TC15NO91.008



    The above direct superimposition of passive wedge resistance is 

valid only if shearing rigidities of the foundation components are 

similar. Also, the compressive strength and buckling resistance of the 

downstream rock layer must be sufficient to develop the wedge 

resistance. For example, a foundation with closely spaced, near 

horizontal, relatively weak seams might not contain sufficient buckling 

strength to develop the magnitude of wedge resistance computed from the 

cross-bed shear strength. In this case wedge resistance should not be 

assumed without resorting to special treatment (such as installing 

foundation anchors). Computed sliding safety factors approximating 3 or 

more for all loading conditions without earthquake, and 1.5 including 

earthquake, should indicate satisfactory stability, depending upon the 

reliability of the strength parameters used in the analyses. In some 

cases when the results of comprehensive foundation studies are 

available, smaller safety factors may be acceptable. The selection of 

shear strength parameters should be fully substantiated. The bases for 

any assumptions; the results of applicable testing, studies and 

investigations; and all pre-existing, pertinent data should be reported 

and evaluated.



                           Chapter 5--Reports



    5.1. General. This chapter outlines the procedures for reporting the 

results of the technical investigations. Hazardous conditions should be 

reported immediately upon detection to the owner of the dam, the 

Governor of the State in which the dam is located and the appropriate 

regulatory agency without delay for preparation of the formal report.

    5.2. Preparation of report. A formal report should be prepared for 

each dam investigated for submission to the regulatory agency and the 

owner of the dam. Each report should contain the information indicated 

in the following paragraphs. The signature and registration 

identification of the professional engineer who directed the 

investigation and who was responsible for evaluation of the dam should 

be included in the report.

    5.2.1. Phase I reports. Phase I reports should contain the following 

information:

    5.2.1.1. Description of dam including regional vicinity map showing 

location and plans, elevations and sections showing the essential 

project features and the size and hazard potential classifications.

    5.2.1.2. Summary of existing engineering data, including geologic 

maps and information.

    5.2.1.3. Results of the visual inspection of each project feature 

including photographs and drawings to minimize descriptions.

    5.2.1.4. Evaluation of operational adequacy of the reservoir 

regulation plan and maintenance of the dam and operating facilities and 

features that pertain to the safety of the dam.

    5.2.1.5. Description of any warning system in effect.

    5.2.1.6. Evaluation of the hydraulic and hydrologic assumptions and 

structural stability.

    5.2.1.7. An assessment of the general condition of the dam with 

respect to safety based upon the findings of the visual inspection and 

review of engineering data. Where data on the original design indicate 

significant departure from or non-conformance with guidelines contained 

herein, the engineer-in-charge of the investigation will give his 

opinion of the significance, with regard to safety, of such factors. Any 

additional studies, investigations and analyses considered essential to 

assessment of the safety of the dam should be listed, together with an 

opinion about the urgency of such additional work.

    5.2.1.8. Indicate alternative possible remedial measures or 

revisions in operating and maintenance procedures which may (subject to 

further evaluation) correct deficiencies and hazardous conditions found 

during the investigation.

    5.2.2. Phase II reports. Phase II reports should describe the 

detailed investigations and should supplement Phase I reports. They 

should contain the following information:

    5.2.2.1. Summary of additional engineering data obtained to 

determine the hydraulic and hydrologic capabilities and/or structural 

stability.

    5.2.2.2. Results of all additional studies, investigations, and 

analyses performed.

    5.2.2.3. Technical assessment of dam safety including deficiences 

and hazardous conditions found to exist.

    5.2.2.4. Indicate alternative possible remedial measures or revision 

in maintenance and operating procedures which may (subject



[[Page 296]]



to further evaluation) correct deficiencies and hazardous conditions 

found during the investigation.

[GRAPHIC] [TIFF OMITTED] TC31OC91.017





[[Page 297]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.018





[[Page 298]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.019





[[Page 299]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.020





[[Page 300]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.021



          Appendix I to App. D to Sec.  222.6--Engineering Data



    This appendix lists engineering data which should be collected from 

project records and, to the extent available, included in the



[[Page 301]]



Phase I investigation report. The list is intended to serve as a 

checklist and not to establish rigid data requirements. Such a 

compilation should also facilitate future inspections and 

investigations. Only data readily available will be included in Phase I 

reports, but data lacking and deemed necessary for an adequate safety 

evaluation should be identified.

    1. General Project Data.

    a. Regional Vicinity Map showing the location of the dam, the 

upstream drainage area and the downstream area subject to potential 

damage due to failure of the dam and misoperation or failure of the 

operating equipment.

    b. As-Built Drawings indicating plans, elevations and sections of 

the dam and appurtenant structures including the details of the 

discharge facilities such as outlet works, limited service and emergency 

spillways, flashboards, fuse plugs and operating equipment.

    2. Hydrologic and Hydraulic Data including the following:

    a. Drainage area and basin runoff characteristics (indicating 

pending changes).

    b. Elevation of top of conservation pool or normal upper retention 

water surface elevation, as applicable (base level of any flood 

impoundment).

    c. Storage capacity including dead or inactive storage, 

corresponding to top of conservation or normal upper retention level 

(cumulative, excluding flood control and surcharge storage).

    d. Elevation of the top of flood control pool.

    e. Storage capacity of flood control zone (incremental).

    f. Elevation of maximum design pool (corresponding to top of 

surcharge storage or spillway design flood).

    g. Storage capacity of surcharge zone (incremental, above top of 

flood control pool or, above normal upper retention level if flood 

control space not provided).

    h. Height of freeboard (distance between maximum design flood water 

surface and top of dam).

    i. Elevation of top of dam (lowest point of embankment or non-

overflow structure).

    j. Elevation of crest, type, width, crest length and location of 

spillways (number, size and type of gates if controlled).

    k. Type, location, entrance and exit inverts of outlet works and 

emergency drawdown facilities (number, size and shape of conduits and 

gates, including penstocks and sluices).

    l. Location, crest elevation, description of invert and abutments 

(concrete, rock, grass, earth) and length of limited service and 

emergency spillways.

    m. Location and dscription of flashboards and fuse plugs, including 

hydraulic head (pool elevation) and other conditions required for 

breaching, along with the assumed results of breaching.

    n. Location and top elevation of dikes and floodwalls (overflow and 

non-overflow) affected by reservoir. Include information on low reaches 

of reservoir rim.

    o. Type, location, observations and records of hydrometeorological 

gages appurtenant to the project.

    p. Maximum non-damaging discharge, or negligible damage rate, at 

potential damage locations downstream.

    3. Foundation Data and Geological Features including logs of 

borings, geological maps, profiles and cross sections, and reports of 

foundation treatment.

    4. Properties of Embankments and Foundation Materials including 

results of laboratory tests, field permeability tests, construction 

control tests, and assumed design properties for materials.

    5. Concrete Properties including the source and type of aggregate, 

cement used, mix design data and the results of testing during 

construction.

    6. Electrical and Mechanical Equipment type and rating of normal and 

emergency power supplies, hoists, cranes, valves and valve operator, 

control and alarm systems and other electrical and mechanical equipment 

and systems that could affect the safe operation of the dam.

    7. Construction History including diversion scheme, construction 

sequence, pertinent construction problems, alterations, modifications 

and maintenance repairs.

    8. Water Control Plan including regulation plan under normal 

conditions and during flood events or other emergency conditions. The 

availability of dam tenders, means of communication between dam tenders 

and authority supervising water control, and method of gate operation 

(manual, automatic, or remote control) should be included. Flood warning 

systems should be described in sufficient detail to enable assessment of 

their reduction in the flood hazard potential.

    9. Operation Record.

    a. Summary of past major flood events including any experiences that 

presented a serious threat to the safety of the project or to human life 

or property. The critical project feature, date and duration of event, 

causative factor, peak inflow and outflow, maximum elevation of water 

surface, wind and wave factors if significant, issuance of alert or 

evacuation warnings and adequacy of project feature involved should be 

included in the summary of past experience of serious threat to the 

safety of the project.

    b. Records of performance observations including instrumentation 

records.

    c. List of any known deficiencies that pose a threat to the safety 

of the dam or to human life or property.



[[Page 302]]



    d. History of previous failures or deficiencies and pending remedial 

measures for correcting known deficiencies and the schedule for 

accomplishing remedial measures should be indicated.

    10. Earthquake History including a summary of the seismic data of 

significant recorded earthquakes in the vicinity of the dam and 

information on major damage in the vicinity of the dam from both 

recorded and unrecorded earthquakes. Regional geologic maps and other 

documents showing fault locations should be collected.

    11. Inspection History including the results of the last safety 

inspection, the organization that performed the inspection, the date 

inspection performed and the authority for conducting the inspection.

    12. Principal Design Assumptions and Analyses.

    a. Hydrologic and Hydraulic Determinations.

    (1) Quantity, time and area distribution, and reference source of 

depth-area-duration data of spillway design storm precipitation (point 

precipitation if applicable).

    (2) Maximum design flood inflow hydrograph including loss rates 

(initial and average for design flood conditions) and time of runoff 

concentration of reservior watershed (peak inflow only when applicable).

    (3) Maximum design flood outflow hydrograph (maximum outflow only 

when applicable).

    (4) Discharge-frequency relationship, preferably at damsite, 

including estimated frequency of spillway design flood for small dams, 

when appropriate.

    (5) Reservior area and storage capacity versus water surface 

elevation (table or curves).

    (6) Rating curves (free flow and partial gate openings) for all 

discharge facilities contributing to the maximum design flood outflow 

hydrograph. Also a composite-rating of all contributing facilities, if 

appropriate.

    (7) Tailwater rating curve immediately below damsite including 

elevation corresponding to maximum design flood discharge and 

approximate nondamaging channel capacity.

    (8) Hydrologic map of watershed above damsite including reservior 

area, watercourse, elevation contours, and principal stream-flow and 

precipitation gaging stations.

    b. Stability and Stress Analysis of the dam, spillway and 

appurtenant structures and features including the assumed properties of 

materials and all pertinent applied loads.

    c. Seepage and Settlement Analyses. The determination of 

distribution, direction and magnitude of seepage forces and the design 

and construction measures for their control. Settlement estimates and 

steps adopted to compensate for total settlement and to minimize 

differential settlements.



         Appendix II to App. D to Sec.  222.6--Inspection Items



    This appendix provides guidance for performing field inspections and 

may serve as the basis for developing a detailed checklist for each dam.

    1. Concrete Structures in General.

    a. Concrete Surfaces. The condition of the concrete surfaces should 

be examined to evaluate the deterioration and continuing serviceability 

of the concrete. Descriptions of concrete conditions should conform with 

the appendix to ``Guide for Making a Condition Survey of Concrete in 

Service,'' American Concrete Institute (ACI) Journal, Proceedings Vol. 

65, No. 11, November 1968, page 905-918.

    b. Structural Cracking. Concrete structures should be examined for 

structural cracking resulting from overstress due to applied loads, 

shrinkage and temperature effects or differential movements.

    c. Movement--Horizontal and Vertical Alignment. Concrete structures 

should be examined for evidence of any abnormal settlements, heaving, 

deflections, or lateral movements.

    d. Junctions. The conditions at the junctions of the structure with 

abutments or embankments should be determined.

    e. Drains--Foundation, Joint, Face. All drains should be examined to 

determine that they are capable of performing their design function.

    f. Water Passages. All water passages and other concrete surfaces 

subject to running water should be examined for erosion, cavitation, 

obstructions, leakage or significant structural cracks.

    g. Seepage or Leakage. The faces, abutments and toes of the concrete 

structures should be examined for evidence of seepage or abnormal 

leakage, and records of flow of downstream springs reviewed for 

variation with reservoir pool level. The sources of seepage should be 

determined if possible.

    h. Monolith Joints--Construction Joints. All monolith and 

construction joints should be examined to determine the condition of the 

joint and filler material, any movement of joints, or any indication of 

distress or leakage.

    i. Foundation. Foundation should be examined for damage or possible 

undermining of the downstream toe.

    j. Abutments. The abutments should be examined for sign of 

instability or excessive weathering.

    2. Embankment Structures.

    a. Settlement. The embankments and downstream toe areas should be 

examined for any evidence of localized or overall settlement, 

depressions or sink holes.

    b. Slope Stability. Embankment slopes should be examined for 

irregularities in



[[Page 303]]



alignment and variances from smooth uniform slopes, unusual changes from 

original crest alignment and elevation, evidence of movement at or 

beyond the toe, and surface cracks which indicate movement.

    c. Seepage. The downstream face of abutments, embankment slopes and 

toes, embankment--structure contacts, and the downstream valley areas 

should be examined for evidence of existing or past seepage. The sources 

of seepage should be investigated to determine cause and potential 

severity to dam safety under all operating conditions. The presence of 

animal burrows and tree growth on slopes which might cause detrimental 

seepage should be examined.

    d. Drainage Systems. All drainage systems should be examined to 

determine whether the systems can freely pass discharge and that the 

discharge water is not carrying embankment or foundation material. 

Systems used to monitor drainage should be examined to assure they are 

operational and functioning properly.

    e. Slope Protection. The slope protection should be examined for 

erosion-formed gullies and wave-formed notches and benches that have 

reduced the embankment cross-section or exposed less wave resistant 

materials. The adequacy of slope protection against waves, currents, and 

surface runoff that may occur at the site should be evaluated. The 

condition of vegetative cover should be evaluated where pertinent.

    3. Spillway Structures. Examination should be made of the structures 

and features including bulkheads, flashboards, and fuse plugs of all 

service and auxiliary spillways which serve as principal or emergency 

spillways for any condition which may impose operational constraints on 

the functioning of the spillway.

    a. Control Gates and Operating Machinery. The structural members, 

connections, hoists, cables and operating machinery and the adequacy of 

normal and emergency power supplies should be examined and tested to 

determine the structural integrity and verify the operational adequacy 

of the equipment. Where cranes are intended to be used for handling 

gates and bulkheads, the availability, capacity and condition of the 

cranes and lifting beams should be investigated. Operation of control 

systems and protective and alarm devices such as limit switches, sump 

high water alarms and drainage pumps should be investigated.

    b. Unlined Saddle Spillways. Unlined saddle spillways should be 

examined for evidence of erosion and any conditions which may impose 

constraints on the functioning of the spillway. The ability of the 

spillway to resist erosion due to operation and the potential hazard to 

the safety of the dam from such operation should be determined.

    c. Approach and Outlet Channels. The approach and outlet channels 

should be examined for any conditions which may impose constraints on 

the functioning of the spillway and present a potential hazard to the 

safety of the dam.

    d. Stilling Basin (Energy Dissipators). Stilling basins including 

baffles, flip buckets or other energy dissipators should be examined for 

any conditions which may pose constraints on the ability of the stilling 

basin to prevent downstream scour or erosion which may create or present 

a potential hazard to the safety of the dam. The existing condition of 

the channel downstream of the stilling basin should be determined.

    4. Outlet Works. The outlet works examination should include all 

structures and features designed to release reservoir water below the 

spillway crest through or around the dam.

    a. Intake Structure. The structure and all features should be 

examined for any conditions which may impose operational constraints on 

the outlet works. Entrances to intake structure should be examined for 

conditions such as silt or debris accumulation which may reduce the 

discharge capabilities of the outlet works.

    b. Operating and Emergency Control Gates. The structural members, 

connections, guides, hoists, cables and operating machinery including 

the adequacy of normal and emergency power supplies should be examined 

and tested to determine the structural integrity and verify the 

operational adequacy of the operating and emergency gates, valves, 

bulkheads, and other equipment.

    c. Conduits, Sluices, Water Passages, Etc. The interior surfaces of 

conduits should be examined for erosion, corrosion, cavitation, cracks, 

joint separation and leakage at cracks or joints.

    d. Stilling Basin (Energy Dissipator). The stilling basin or other 

energy dissipator should be examined for conditions which may impose any 

constraints on the ability of the stilling basin to prevent downstream 

scour or erosion which may create or present a potential hazard to the 

safety of the dam. The existing condition of the channel downstream of 

the stilling basin should be determined by soundings.

    e. Approach and Outlet Channels. The approach and outlet channels 

should be examined for any conditions which may impose constraints on 

the functioning of the discharge facilities of the outlet works, or 

present a hazard to the safety of the dam.

    f. Drawdown Facilities. Facilities provided for drawdown of the 

reservoir to avert impending failure of the dam or to facilitate repairs 

in the event of stability or foundation problems should be examined for 

any conditions which may impose constraints on their functioning as 

planned.

    5. Safety and Performance Instrumentation. Instruments which have 

been installed to measure behavior of the structures should be



[[Page 304]]



examined for proper functioning. The available records and readings of 

installed instruments should be reviewed to detect any unusual 

performance of the instruments or evidence of unusual performance or 

distress of the structure. The adequacy of the installed instrumentation 

to measure the performance and safety of the dam should be determined.

    a. Headwater and Tailwater Gages. The existing records of the 

headwater and tailwater gages should be examined to determine the 

relationship between other instrumentation measurements such as stream 

flow, uplift pressures, alignment, and drainage system discharge with 

the upper and lower water surface elevations.

    b. Horizontal and Vertical Alignment Instrumentation (Concrete 

Structures). The existing records of alignment and elevation surveys and 

measurements from inclinometers, inverted plumb bobs, gage points across 

cracks and joints, or other devices should be examined to determine any 

change from the original position of the structures.

    c. Horizontal and Vertical Movement, Consolidation, and Pore-Water 

Pressure Instrumentation (Embankment Structures). The existing records 

of measurements from settlement plates or gages, surface reference 

marks, slope indicators and other devices should be examined to 

determine the movement history of the embankment. Existing piezometer 

measurements should be examined to determine if the pore-water pressures 

in the embankment and foundation would under given conditions impair the 

safety of the dam.

    d. Uplift Instrumentation. The existing records of uplift 

measurements should be examined to determine if the uplift pressures for 

the maximum pool would impair the safety of the dam.

    e. Drainage System Instrumentation. The existing records of 

measurements of the drainage system flow should be examined to establish 

the normal relationship between pool elevations and discharge quantities 

and any changes that have occurred in this relationship during the 

history of the project.

    f. Seismic Instrumentation. The existing records of seismic 

instrumentation should be examined to determine the seismic activity in 

the area and the response of the structures of past earthquakes.

    6. Reservoir. The following features of the reservoir should be 

examined to determine to what extent the water impounded by the dam 

would constitute a danger to the safety of the dam or a hazard to human 

life or property.

    a. Shore line. The land forms around the reservoir should be 

examined for indications of major active or inactive landslide areas and 

to determine susceptibility of bedrock stratigraphy to massive 

landslides of sufficient magnitude to significantly reduce reservoir 

capacity or create waves that might overtop the dam.

    b. Sedimentation. The reservoir and drainage area should be examined 

for excessive sedimentation or recent developments in the drainage basin 

which could cause a sudden increase in sediment load thereby reducing 

the reservoir capacity with attendant increase in maximum outflow and 

maximum pool elevation.

    c. Potential Upstream Hazard Areas. The reservoir area should be 

examined for features subject to potential backwater flooding resulting 

in loss of human life or property at reservoir levels up to the maximum 

water storage capacity including any surcharge storage.

    d. Watershed Runoff Potential. The drainage basin should be examined 

for any extensive alterations to the surface of the drainage basin such 

as changed agriculture practices, timber clearing, railroad or highway 

construction or real estate developments that might extensively affect 

the runoff characteristics. Upstream projects that could have impact on 

the safety of the dam should be identified.

    7. Downstream Channel. The channel immediately downstream of the dam 

should be examined for conditions which might impose any constraints on 

the operation of the dam or present any hazards to the safety of the 

dam. Development of the potential flooded area downstream of the dam 

should be assessed for compatibility with the hazard classification.

    8. Operation and Maintenance Features.

    a. Reservoir Regulation Plan. The actual practices in regulating the 

reservoir and discharges under normal and emergency conditions should be 

examined to determine if they comply with the designed reservoir 

regulation plan and to assure that they do not constitute a danger to 

the safety of the dam or to human life or property.

    b. Maintenance. The maintenance of the operating facilities and 

features that pertain to the safety of the dam should be examined to 

determine the adequacy and quality of the maintenance procedures 

followed in maintaining the dam and facilities in safe operating 

condition.



[[Page 305]]



[GRAPHIC] [TIFF OMITTED] TC31OC91.022





[[Page 306]]





[GRAPHIC] [TIFF OMITTED] TC31OC91.023



              Appendix E to Sec.  222.6--Suggested Outline



Inspection Report--National Dam Inspection Program (RCS-DAEN-CWE-17 and 

                            OMB No. 49-R0421)



Title Sheet



    Name of Dam

    ID Number from Inventory

    State, County and River or Stream where dam is located

    Owner

    Size and Hazard Classification

    Names of Inspectors

    Names of Review Board

    Approval Signature of District Engineer



                            Table of Contents



                           General Assessment



    Give brief assessment of general condition of dam with respect to 

safety, including a listing of deficiencies, and recommendations 

indicating degree of urgency.



                             1. Introduction



    a. Authority

    b. Purpose and Scope of Inspection



                         2. Project Information



    a. Site Information

    b. Description of Structures--Dam, Outlet, Spillway and other 

principal features.

    c. Purpose of Dam

    d. Design, Construction and Operating History



                           3. Field Inspection



    Briefly describe physical condition of the dam and appurtenant 

structures as they were observed during the field inspection. (If field 

inspection form is appended, only present summary.) Describe operational 

procedures, including any warning system, condition of operating 

equipment, and provision for emergency procedures. Describe any 

pertinent observations of the reservoir area and downstream channel 

adjacent to dam.



[[Page 307]]



                              4. Evaluation



    a. Structural and Geotechnical

    (1) General

    (2) Embankment and/or Foundation Condition

    (3) Stability--Briefly discuss pertinent information such as design, 

construction and operating records. Assess stability under maximum 

loading on basis of the record data, together with observations of field 

inspection and results of any additional, brief calculations performed 

by inspectors. If additional, detailed stability analyses are considered 

necessary, recommend that the owner engage a qualified engineer or firm 

to provide the analysis.

    b. Hydrologic and Hydraulic

    (1) Spillway Adequacy--Briefly describe pertinent record information 

such as hydrologic and hydraulic design data, flood of record, and 

previous analyses. Describe any hydraulic and hydrologic analyses made 

for this inspection. Present conclusion with respect to adequacy of 

spillway to pass the recommended spillway design flood without 

overtopping dam. If overtopping would occur, and if available from the 

type of analysis used, give maximum depth over top of dam and duration 

of overtopping, assuming the dam does not fail. Also indicate the 

largest flood, as a percentage of the probable maximum flood which can 

be passed without overtopping.

    (2) Effects of overtopping--If dam is overtopped by the recommended 

spillway design flood, provide assessment as to whether or not dam would 

likely fail, and if, in case of failure, the hazard to loss of life 

downstream of the dam would be substantially increased over that which 

would exist without failure. If information upon which to base a 

reasonable assessment is insufficient, so state and describe the needed 

data, and recommend that the necessary studies be performed by engineers 

engaged by the owner.

    c. Operation and Maintenance

    Assess operating equipment and procedures, emergency power for gate 

operation, and Emergency Action Plan. Assess quality of maintenance as 

it pertains to dam safety.



                             5. Conclusions



    Provide conclusions on condition of dam and list all deficiencies. 

If dam is considered unsafe, so state and give reason.



                           6. Recommendations



    List all recommended actions, including additional studies, 

installation of new surveillance procedures and devices, development of 

Emergency Action Plans, and remedial work. Recommend that a qualified 

engineering firm be retained to accomplish any recommended additional 

investigations and studies and also to design and supervise remedial 

works.



                               Appendixes



    a. Inspection Checklist (if available)

    b. Other Illustrations as follows:

    (1) Include a map showing location of the dam. Usually a portion of 

a USGS quadrangle sheet can be used which will show the topography of 

the area, location of the dam, exent of the lake and drainage basin, and 

perhaps indicate the downstream development.

    (2) If available, include a plan and section of the dam.

    (3) General photographs of the dam and downstream channel should be 

included.

    (4) Color photographs of deficiencies should be included. These 

should be held to the minimum required to illustrate the deficiencies.

    (5) Available engineering data including Hydrologic/Hydraulic 

calculation and physical test results that might be available.



                        Appendix F to Sec.  222.6



 Instructions for Unsafe Dam Data Sheet (RCS-DAEN-CWE-17 and OMB No. 49-

                                 R0421)



    The indicated information shall be provided in the format shown on 

Pg F-3 for each dam assessed to be unsafe during the reporting period. A 

separate data sheet should be provided for each unsafe dam. The 

information supplied should conform to the following.

    a. Name--Name of dam.

    b. Id. No.--Dam inventory identity number.

    c. Location--List state county, river or stream and nearest D/S city 

or town where the dam is located.

    d. Height--Maximum hydraulic height of dam.

    e. Maximum Impoundment Capacity--List the capacity of the reservior 

at maximum attainable water surface elevation including any surcharge 

loading.

    f. Type--Type of dam, i.e., earth, rockfill, gravity, combination 

earth-gravity, etc.

    g. Owner--Owner of dam.

    h. Date Governor Notified of Unsafe Condition--The date and method 

of notification, such as, by telegram, letter, report, etc.

    i. Condition of Dam Resulting in Unsafe Assessment--Brief 

description of the deficiencies discovered which resulted in the unsafe 

assessment.

    j. Description of Danger Involved--Downstream (D/S) hazard potential 

category and a brief description of the danger involved.

    k. Recommendations Given to Governor--Brief description of the 

actions recommended to Governor at time of notification of unsafe 

condition to eliminate or reduce the danger.

    l. Urgency Category--State whether the unsafe condition of the dam 

is an emergency or non-emergency situation. An emergency situation 

should be considered to exist if the failure of the dam is judged to be 

imminent



[[Page 308]]



and requires immediate action to eliminate or reduce the danger.

    m. Emergency Actions Taken--In case of an emergency situation, list 

the actions taken. For non-emergency situation, put NA for ``not 

applicable.''

    n. Remedial Action Taken--For non-emergency situations list remedial 

actions taken.

    o. Remarks--For other pertinent information.



 Format for Unsafe Dam Data Sheet (RCS-DAEN-CWE-17 and OMB No. 49-R0421



  National Program of Inspection of Non-Federal Dams--Unsafe Dam Data 

                                  Sheet



    a. Name:

    b. Type:

    c. Height:

    d. Id. No.

    e. Location:

     State: County:

     Nearest D/S City, Town or Village:

     River or Stream:

    f. Owner:

    g. Date Governor Notified of Unsafe Condition:

    h. Condition of Dam Resulting in Unsafe Assessment:

    i. Description of Danger Involved:

    j. Recommendations Given to Governor:

    k. Urgency Category:

    l. Emergency Actions Taken:

    m. Remarks:



                        Appendix G to Sec.  222.6



 National Program for Inspection of Non-Federal Dams--Monthly Progress 

                        Report (RCS-DAEN-CWE-19)



I. Instructions for Monthly Progress Report. The indicated information 

shall be provided in the format shown on page G-2.



    1. Division Reporting:

    2. Date:

    3. Information Required for Each State Regarding Total Number of 

Inspections Performed (AE Inspections included) (Cumulative):

    3.1. Number of Inspections Initiated by on-site inspection or the 

review of engineering data from project records. \1\

---------------------------------------------------------------------------



    \1\ Each of the initiated inspections reported should be planned for 

completion within a reasonable period of time (30 days.)

---------------------------------------------------------------------------



    3.2. Number of Inspections Competed (The number of inspection 

reports which have been submitted to the District Engineer for review 

and approval).

    3.3 Number of Dams Reported to the Governor as Unsafe. \2\

---------------------------------------------------------------------------



    \2\ An unsafe dam is defined as a dam with deficiencies of such a 

nature that if not corrected could result in the failure of the dam with 

subsequent loss of lives or substantial property damage.

---------------------------------------------------------------------------



    3.4. Number of Approved Inspection Reports Submitted to the 

Governor.

    4. Information Required for Each State Regarding Inspections 

Performed Under AE Contracts (Cumulative):

    4.1. Number of Dams Contracted for Inspection by AE's with State or 

Corps.

    4.2. Number of Inspections Initiated by AE's by on-site inspection 

or the review of engineering data from project records. \1\

---------------------------------------------------------------------------



    \1\ See footnote on previous page.

---------------------------------------------------------------------------



    4.3. Number of Inspections Completed by AE's (The number of 

inspection reports which have been submitted to the District Engineer 

for review and approval).

    4.4. Number of Approved Inspection Reports Prepared by AE's 

Submitted to the Governor.



II. Formation for Monthly Progress Report.



 National Program for Inspection of Non-Federal Dams--Monthly Progress 

                                 Report



    1. Division Reporting:

    2. Date:

    3. Information Required for Each State Regarding Total Number of 

Inspections Performed (Cumulative):



------------------------------------------------------------------------

                                                       Unsafe

                              Inspection  Inspection    Dams    Approved

            State              Initiated   Completed  Reported   Reports

                                 (3.1)       (3.2)      (3.3)     (3.4)

------------------------------------------------------------------------







                             ===========================================

Total.......................

------------------------------------------------------------------------



    4. Information Required for Each State Regarding Inspections 

Performed Under A/E Contracts (Cumulative):



----------------------------------------------------------------------------------------------------------------

                                                                      Dams

                                                                    Under A/      A/E          A/E         A/E

                               State                                    E     Inspections  Inspections   Reports

                                                                    Contract   Initiated    Completed   Approved

                                                                      (4.1)      (4.2)        (4.3)       (4.4)

----------------------------------------------------------------------------------------------------------------







                                                                   =============================================

Totals............................................................

----------------------------------------------------------------------------------------------------------------



                        Appendix H to Sec.  222.6



  Suggested Scope of Work Contract for Architect-Engineer Services for 

         Safety Inspection of Dams Within the State of --------



    1. General Description of Scope of Work. The services to be rendered 

by the Architect-Engineer (AE) under the proposed contract



[[Page 309]]



shall include all engineering functions, hereinafter described, as 

needed to inspect the dams listed in Appendix A of this contract for the 

purpose of evaluating their risk of failure. A report which (a) 

describes the assessed condition of the dam, (b) provides conclusions as 

to which particular conditions could cause failure, (c) makes 

recommendations on remedial measures believed necessary, and (d) makes 

recommendations on whether and what type of future investigation should 

be conducted shall be provided for each inspected dam. The work shall 

proceed in accordance with Phase I of the Recommended Guidelines for 

Safety Inspection of Dams established by the Office of the Chief of 

Engineers (OCE) and the supplemented requirements listed in paragraph 3 

below. The OCE guidelines are listed in Appendix B of this contract.

    2. Information and Services To Be Furnished by the Government. The 

Contracting Officer will furnish the following information and services 

to the AE:

    a. All information pertaining to each dam to be inspected as 

contained in the National Inventory of Dams.

    b. Copies of recommended format for preparation of inspection 

report, engineering data check list and visual inspection check list.

    c. All available pertinent information pertaining to the Dam 

Inspection Program and previous investigations having a bearing on 

inspections to be performed under this contract.

    d. Right-of-entry for access to each dam site.

    3. Services To Be Rendered by the Architect-Engineer. The principal 

services, subject to the optional provisions of the contract, to be 

rendered by the AE are itemized below:

    a. Technical Investigations.

    (1) Engineering Data Collection. To the extent feasible, the 

engineering data listed in Appendix I of the OCE guidelines relating to 

the design, construction and operation of the dam and appurtenant 

structures, should be collected from existing records and reviewed to 

aid in evaluating the general condition of each dam, including an 

assessment of the hydraulic and hydrologic features and structural 

stability of the dam. Where the necessary engineering data are 

unavailable, inadequate or invalid, a listing shall be made of those 

specific additional data deemed necessary by the engineer in charge of 

the investigation and included in the inspection report. The engineering 

data checklist provided by the Contracting Officer shall be used as a 

guide to compile this data.

    (2) Field Inspections. The field inspection of each dam shall 

include examination of the items listed in Appendix II of the OCE 

guidelines, electrical and mechanical equipment for operation of the 

control facilities, reservoir area, downstream channel in the vicinity 

of the dam and any other significant feature to determine how these 

features affect the risk of failure of the dam. The inspection shall be 

conducted in a systematic manner to minimize the possibility of any 

significant feature being overlooked. The visual inspection checklist 

provided by the Contracting Officer shall be used as a guide to document 

the examination of each significant feature.

    Particular attention shall be given to detecting evidence of 

leakage, erosion, seepage, slope instability, undue settlement, 

displacement, tilting, cracking, deterioration, and improper functioning 

of drains and relief wells. The degree and quality of maintenance and 

regulating procedures for operation of the control facilities shall be 

assessed. The design and existing condition of such control facilities 

(i.e., spillway, outlet works, etc.) shall be evaluated. An assessment 

of the degree of siltation that is evident and its effect on the dam's 

reservoir shall be performed. Photographs and drawings should be used to 

record conditions in order to minimize written descriptions.

    (3) Engineering Analyses.

    (a) Evaluation of Hydraulic and Hydrologic (H&H) Features. 

Evaluation of the hydraulic and hydrological features of each dam shall 

be based on criteria set forth in the OCE guidelines. If it is 

determined that the available H&H data are insufficient, the Contracting 

Officer must be so informed and may exercise an option of requiring the 

AE to perform an overtopping analysis at additional agreed-upon 

compensation. The methodology to be used by the AE for this analysis 

will be based on the OCE guidelines and subject to the approval of the 

Contracting Officer.

    (b) Evaluation of Structural Stability. The evaluation of structural 

stability of each dam is to be based principally on existing conditions 

as revealed by the visual inspection, available design and construction 

information, and records of performance. The objectives are to determine 

the existence of conditions, identifiable by visual inspection or from 

records, which may pose a high risk of failure and to formulate 

recommendations pertaining to the need for any remedial improvements, 

additional studies, investigations, or analysis. The results of this 

phase of the inspection must rely substantially upon the experience and 

judgment of the inspecting engineer. Should it be determined that 

sufficient data are not available for a reasonable evaluation of the 

structural stability of a dam and appurtenances, the Contracting Officer 

should be informed which information is required prior to attempting to 

evaluate the risk of failure of the dam.

    (c) Evaluation of Operational Features. Where critical mechanical/

electrical operating equipment is used in controlling the



[[Page 310]]



reservoir of a dam, an evaluation of the operational characteristics of 

this equipment from the standpoint of risk of failure must be performed.

    (d) Evaluation of Reservoir Regulation Plan and Warning System. The 

operational characteristics of each dam's existing reservoir regulation 

plan and warning system in event of a threatened failure shall be 

investigated.

    b. Emergency Situations. The Contracting Officer must be immediately 

notified of any observed condition which is deemed to require immediate 

remedial action. After being notified, the Contracting Officer will 

contact the appropriate State personnel and will meet the AE at the site 

to determine the appropriate course of action. This will not relieve the 

AE of his responsibility to prepare a comprehensive inspection report at 

the earliest practicable date.

    c. Qualifications of Investigators. The technical investigations 

shall be conducted by licensed professional engineers with a minimum of 

five years experience after licensing in the investigation, design and 

contruction of earthfill, rockfill and concrete dams and/or in making 

risk of failure evaluations of completed dams. These engineers must be 

knowledgeable in the disciplines of hydrology, hydraulics, geotechnical, 

electrical, mechanical and structural engineering, as necessary. All 

field inspections should be conducted by engineers, engineering 

geologists and other specialists who are knowledgeable in the 

investigation, design, construction and operation of dams, including 

experts on mechanical and electrical operation of gates and controls, 

where needed.

    d. Preparation of Report. A formal report shall be prepared for each 

dam inspected for submission to the Contracting Officer. Each report 

should contain the information specified in OCE guidelines and any other 

pertinent information. The recommended format provided by the 

Contracting Officer shall be used to document each report. The signature 

and registration identification of the professional engineer who 

directed the investigation and who was responsible for evaluation of the 

dam should be included in the report.

    4. Supervision and Approval of Work. All work performed under this 

contract shall be subject to the review and approval of the Contracting 

Officer or his designee. Meetings will be held on a regular basis in the 

District office, during which the progress of inspections will be 

discussed and questions relating to inspection reports previously 

received by the Contracting Officer will be addressed. Reports will be 

revised as necessary when required by the Contracting Officer.

    5. Coordination. During the progress of work, the AE shall maintain 

liaison with the *-------- and other local authorities through the 

Contracting Officer as required to assure the orderly progression of the 

inspection. Copies of all correspondence with such authorities shall be 

provided to the Contracting Officer.

---------------------------------------------------------------------------



    * Note: Write in the designated State Authority.

---------------------------------------------------------------------------



    6. Submission of Report.

    a. Each inspection report will be submitted for review to the 

Contracting Officer. Reports will be revised as required by the 

Contracting Officer. After all revisions have been made, the original 

and ---- copies of each inspection report shall be submitted to the 

Contracting Officer.

    b. Text of all reports shall be typewritten and printed on both 

sides of 8x10\1/2\ paper. All notes, inspection 

forms, sketches or similar matter shall be legible, distinct and 

suitable for reproduction.

    7. Period of Services.

    a. All inspections and reports included under this contract shall be 

completed within ---- days from date of Notice to Proceed.

    b. If the option for performing an H&H analysis for any particular 

site is exercised, the AE shall complete such analysis within ---- days 

from date of Notice to Proceed. However, the overall completion time 

stated in paragraph 7a above shall not change.



                        Appendix I to Sec.  222.6



 Procedure for Using NASA Land Satellite Multispectral Scanner Data for 

        Verification and Updating the National Inventory of Dams



    1. Purpose. This appendix states the objective, defines the scope, 

prescribes procedures, and assigns responsibilities for using NASA Land 

Satellite (LANDSAT) Multispectral Scanner data along with NASA's Surface 

Water Detection And Mapping (DAM) Computer program to assist in 

verification and updating the National Inventory of Dams.

    2. Applicability. This appendix is applicable to all divisions and 

districts having Civil Works responsibilities except POD.

    3. Reference. NASA, DETECTION AND MAPPING PACKAGE, Users Manuals, 

Volumes 1, 2a, 2b, and 3 dated June 1976, published by the Johnson Space 

Center, Houston, Texas.

    4. Objectives. Provide a uniform method, nation-wide, to help insure 

that all dams subject to Public Law 92-367, 8 August 1972 are properly 

identified and located in the National Inventory of Dams.

    5. Scope. The computer printer overlay maps produced by the 

procedure described in reference 3b will be used by district and/or 

state or contractor personnel as a tool to assist in verification and 

updating of the National Inventory of Dams.



[[Page 311]]



    6. Exceptions. a. If a Division/District attempts the use of the 

procedure for a given region within their area of responsibility and 

finds the overlay maps cannot be used to assist in verification and 

updating the National Inventory of Dams, they may request an exception 

for a selected region. A selected region may include areas where 

conditions can reasonably be assumed to be the same as the region where 

the procedure was tried.

    b. Request for exceptions should be documented to include firm 

boundary definitions and appropriate justification to demonstrate why 

the procedure cannot be used. This request should be submitted to WRSC 

WASH DC 20314, through the normal engineering chain of command.

    c. Map overlays will be produced for all areas of the Continental 

United States even if they are not used in a few selected regions. This 

processing is required for a future Computer Water Body Change Detection 

system.

    7. Procedures. Acquisition of LANDSAT data, registration of 

satellite coordinates to earth latitude and longitude and computer 

processing to produce overlay maps will be accomplished by two Regional 

Centers. Nashville District and Seattle District have been designated as 

the Regional Centers, with each responsible for processing maps by state 

based on Divisional assignments in Appendix A. Regional Centers will 

support divisions as follows:



------------------------------------------------------------------------

              Regional Center                         Division

------------------------------------------------------------------------

Nashville District                          New England

                                            North Atlantic

                                            South Atlantic

                                            Ohio River

                                            Lower Mississippi Valley

                                            North Central



Seattle District                            Southwestern

                                            Missouri River

                                            North Pacific

                                            South Pacific

------------------------------------------------------------------------



    8. Responsibilities. a. The Water Resources Support Center at Fort 

Belvoir has overall responsibility for coordination and monitoring of 

this activity between NASA, Division Offices, and Regional Centers, and 

for providing Regional Center funding.

    b. Regional Centers are responsible for:

    (1) Acquiring proper LANDSAT data tape from EROS Data Center (Sioux 

Falls, South Dakota). Actual data scene selection will be coordinated 

with Division and/or District to insure proper consideration is given to 

local priorities and seasonal coverage.

    (2) Arranging computer processing support using NASA's DAM package.

    (3) Establishing proper control between satellite scanner-oriented 

coordinates and earth latitude/longitude.

    (4) Producing total coverage of map overlays at a scale of 1:24,000 

and/or smaller scales as required by Divisions and/or Districts.

    (5) Instructing District, State, or contractor personnel in the 

assembly and use of map overlays.

    c. Divisions/Districts are responsible for:

    (1) Designating one person from each Division and District as the 

point of contact with the Regional Center and provide this person's name 

and phone number to the Regional Center.

    (2) Providing the Regional Center with map coverage of their area of 

responsibility. This will include state indexes and 7\1/2\ minute 

quadrangle sheets (scale 1:24,000) where available.

    (3) Coordinating with the Regional Center in selecting LANDSAT data 

tapes.

    (4) Providing information to Regional Center on scale and priorities 

of desired computer produced map overlays.

    (5) Assembling computer print-outs into overlay maps, and using as 

appropriate to assist in verification and updating the National 

Inventory of Dams.

    9. Points of Contact. The points of contact in the Regional Centers 

for this program are as follows:



                   Name, Office Symbol, and Telephone



Jim Cook--DAEN-ORNED, (615) 251-7366; FTS 852-7366.

Jack Erlandson--DAEN-NPSEN, (206) 764-3535; FTS 399-3535.



[44 FR 55336, Sept. 26, 1979, as amended at 45 FR 18925, Mar. 24, 1980. 

Redesignated at 60 FR 19851, Apr. 21, 1995]