[Code of Federal Regulations]

[Title 33, Volume 3]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 33CFR230.23]



[Page 320]

 

                TITLE 33--NAVIGATION AND NAVIGABLE WATERS

 

 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 

                                 DEFENSE

 

PART 230_PROCEDURES FOR IMPLEMENTING NEPA--Table of Contents

 

Sec.  230.23  Predecision referrals.



    See 40 CFR part 1504. If the district commander determines that a 

predecision referral is appropriate, the case will be sent through 

division to reach CECW-RE not later than 15 days after the final EIS was 

filed with EPA. Corps actions referred to CEQ by another Federal agency 

shall be transmitted to CECW-RE for further guidance. See paragraph 19, 

33 CFR part 325, Appendix B, for guidance on predecision referrals 

affecting regulatory permit actions.