Sec.  263.18  Program completion-time objectives.



    To provide a Program responsive to local needs, the following target 

(maximum) completion time objectives are established and should be used 

to the extent feasible, in scheduling work and programming funds. 

Shortening of these objectives is encouraged for specific studies and 

projects when appropriate. However, high standards of planning, design 

and construction are not to be sacrificed. Attainment of completion-time 

objectives through intensive management is to be a major concern for 

those elements and individuals given Program management responsibilities 

in Sec.  263.16 of this regulation.



             Program Authorities, Completion Times in Months

------------------------------------------------------------------------

                                       205, 107,               Emergency

                                       103, and   208 and 14   14 and 3

                                          111                     \1\

------------------------------------------------------------------------

(a) Completion of recon and                    2           1           2

 submission of funding request or

 negative report to OCE.............

(b) Completion of feasibility study           16           9      (\2\ )

 by reporting officer and

 preparation of DPR.................

(c) Review of DPR or recon report by           2           1          .5

 division engineer, (including

 provisions of Sec.   263.15(f))....

(d) Review of DPR or recon report by           2           1          .5

 OCE................................

(e) Completion of project                     18          12           3

 construction (including plans and

 specifications), after project

 approval...........................

                                     -----------------------------------

(f) Total completion-time objective.          40          24           6

------------------------------------------------------------------------

\1\ The decision to utilize a recon report or DPR for recommending a

  project under sec. 14 authority is delegated to the division engineer

  (Sec.   263.17(b)(3)).

\2\ Not applicable.