[Code of Federal Regulations]

[Title 33, Volume 3]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 33CFR263.27]



[Page 361-366]

 

                TITLE 33--NAVIGATION AND NAVIGABLE WATERS

 

 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 

                                 DEFENSE

 

PART 263_CONTINUING AUTHORITIES PROGRAMS--Table of Contents

 

                    Subpart D_Shore Protection Policy

 

Sec.  263.27  Authority for mitigation of shore damage attributable to 

navigation works (Section 111).



    (a) Legislative authority. Section 111 of the River and Harbor Act 

of 1968 (Pub. L. 90-483, approved August 13, 1968) states:



    The Secretary of the Army, acting through the Chief of Engineers is 

authorized to investigate, study, and construct projects for the 

prevention or mitigation of shore damages attributable to Federal 

navigation works. The cost of installing, operation and maintaining 

shall be borne entirely by the United States. No such projects shall be 

constructed without specific authorization by Congress if the estimated 

first cost exceeds $1,000,000.



    (b) Definitions--(1) Federal navigation works is defined as a 

project or feature thereof that has been specifically authorized by the 

Congress in a River and



[[Page 362]]



Harbor Act or authorized under the continuing authorities granted by 

section 201 or the Flood Control Act of 1965, or by section 107 of the 

River and Harbor Act of 1960, as amended. These shall include projects 

or project features built by others but which have been adopted as a 

Federal Navigation project.

    (2) Beach erosion control project is defined as a project that has 

been specifically authorized by the Congress in a River and Harbor Act 

or authorized under the continuing authorities granted by section 201 of 

the Flood Control Act of 1965 or by section 103 of the River and Harbor 

Act of 1962. This is considered to include the beach erosion control 

portion of combined beach erosion and hurricane protection projects.

    (3) Mitigation of shore damages is defined as the construction of 

works or procedures to reduce erosion-type damages by shoreline 

stabilization. The degree of mitigation is the reduction of erosion or 

accretion to the level which would be obtained without the influence of 

navigation works at the time navigation works were accepted as a Federal 

responsibility. It is not intended that shorelines be restored to 

historic dimensions, but only to lessen the damages by an action that 

can be justified, the entire costs of which are Federal regardless of 

shore ownership.

    (c) General policies. (1) This Act authorizes the study, 

construction and maintenance of work for prevention or mitigation of 

damages to both public and privately owned shores to the extent of the 

damages that can be directly identified and attributed to Federal 

navigation work located along the coastal and Great Lakes shorelines of 

the United States. This authority will not be used:

    (i) For construction of works for prevention or mitigation of shore 

damages such as those caused by river bank erosion or vessel generated 

wave wash.

    (ii) To modify navigation projects authorized, but not constructed, 

that contain features for prevention or mitigation of shore damages or 

to change the responsibility for maintenance or to modify portions of 

constructed navigation projects that contain features for prevention or 

mitigation of shore damages.

    (iii) For prevention or mitigation of shore damages caused by non-

Federal navigation projects.

    (iv) To construct, maintain, modify or change the cost sharing of 

authorized beach erosion or combined beach erosion and hurricane 

protection projects, or portions thereof, located adjacent to Federal 

navigation projects. Except, when it is determined that shore damage to 

a portion of an authorized beach erosion project is attributable to the 

navigation project, mitigation measures may be accomplished under this 

authority, only to the extent of damages that can be directly identified 

and attributed to the navigation project.

    (2) Where the erosion attributable to the Federal navigation project 

consists of only a portion of the total erosion problem in a specific 

area and cannot be considered as a separable reach for effective 

mitigation measures then a section 111 project cannot be considered for 

authorization unless,

    (i) There is an authorized beach erosion control or combined beach 

and hurricane protection project for the area with which the section 111 

mitigation measures could be combined to become effective, or

    (ii) A general study of the entire problem area is made and leads to 

the development of an authorized beach erosion control project, 

(specific authority must be obtained to conduct a general study of the 

entire problem area) or

    (iii) Local interests indicate a willingness to have the erosion 

problem outside the scope of section 111 remedied at local cost.

    (d) Cost limitations. Section 111 provides that the Chief of 

Engineers has authority to authorize projects for which the estimated 

first costs will not exceed $1,000,000. The first costs will be the cost 

of the initial preventive or mitigative measures only. The limitation on 

costs does not include the cost of project maintenance. The project must 

be planned as a complete unit and not broken into reaches or stages for 

cost limitation purposes.

    (e) Reports. The Recon Report required by Sec.  263.15(c)(1) will:



[[Page 363]]



    (1) Determine whether or not Federal navigation works are 

responsible for causing or contributing to the erosion problem.

    (2) Determine the extent of the area affected by the navigation 

works.

    (3) Determine total area experiencing significant erosion.

    (4) Determine the approximate percentage of the total erosion 

problem in a specific area that is attributable to the navigation works.

    (5) Recommend whether further study of the specific area affected by 

the Federal navigation works is justified and whether study of the 

entire area is desirable.

    (f) Evaluation of mitigation measures. The objective of section 111 

is to provide mitigation measures for shore damages attributable to 

Federal navigation projects, when equitable and in the public interest. 

All practicable alternatives, structural and non-structural should be 

identified and considered. Work recommended for construction should 

provide the most practicable and economical means of mitigating existing 

damages or the prevention of subsequent damages. Justification of 

mitigation measures should be made by comparing their costs with the 

values represented by the damages preventable. Any intangible values 

should be described and given due weight along with the tangible values 

in this justification. Exercise of the authority of section 111 to 

provide mitigation measures at Federal expense is not mandatory. A 

finding for or against its use should fully consider the pre-project 

conditions and the justification of incurring mitigation costs.

    (g) Criteria for a Favorable Recommendation. A recommendation 

favorable to adoption and construction of work to prevent or mitigate 

shore damage attributable to a Federal navigation project under the 

authority of section 111 of the River and Harbor Act of 1968 may be 

considered warranted when both of the following conditions exist:

    (1) The navigation project has been determined to be the cause of 

the damage.

    (2) Analysis based on sound engineering and economic principles 

clearly demonstrates the feasibility of the proposed work.

    (h) Cost sharing--(1) Construction. (i) If the work recommended in 

the report is confined to mitigation work only under section 111, i.e., 

erosion totally attributable to the navigation works, costs will be 100 

percent Federal.

    (ii) If the work recommended is a combination of mitigation under 

section 111 and restoration of beaches eroded due to other causes and 

there is no authorized beach erosion project, mitigation work under 

section 111 will be 100 percent Federal and the remaining work will be 

100 percent local.

    (iii) If the work recommended in the report is a combination of 

mitigation under section 111 and the restoration of beaches under an 

authorized beach erosion project or combination beach erosion-hurricane 

protection project, the mitigation work under section 111 will be 100 

percent Federal and the remainder in accordance with the cost sharing 

procedures as specified in project authorization documents.

    (2) Maintenance. (i) If the initial work is confined to mitigation 

under section 111, all maintenance costs are 100 percent Federal.

    (ii) If the work is a combination of mitigation under section 111 

and restoration of beaches eroded due to other causes, and there is no 

authorized beach erosion project, maintenance costs will be shared in 

the same proportion as recommended for initial construction, i.e., the 

section 111 portion will be 100 percent Federal and remaining work 100 

percent local.

    (iii) If the work is a combination of mitigation under section 111 

and an authorized beach erosion control project or combination beach 

erosion-hurricane protection project, the Federal maintenance cost for 

the mitigation work under section 111 will be in the same proportion as 

the damage attributed to the Federal navigation work is to the total 

damage. For the remaining work the cost sharing procedures of the 

authorized beach erosion or combined beach erosion-hurricane protection 

project will apply.

    (i) Local cooperation. (1) The law as written provided that the cost 

of installing, operating and maintaining projects under this authority 

shall be



[[Page 364]]



borne entirely by the United States; therefore there are no requirements 

for local cooperation. The cost of any lands, easements or rights-of-way 

required for construction or subsequent maintenance will be borne 

entirely by the United States.

    (2) Where section 111 projects are to be accomplished in conjunction 

with other works (Sec.  263.15(a)(2)) local interests will be required 

to furnish assurance of local cooperation similar to those required for 

regularly authorized projects for their assigned portion of the work.

    (3) Where section 111 projects are to be accomplished in conjunction 

with authorized projects, the requirements of local cooperation 

specified in the authorizing document or report will apply.



   Appendix A to Part 263--History of Program and Project Limitations 

                     Continuing Authorities Program



----------------------------------------------------------------------------------------------------------------

                                                                                       Federal cost     Annual

                Section/law                             Date               Public law   limitation     program

                                                                              No.       per project     limit

----------------------------------------------------------------------------------------------------------------

                                                    (1) Small Flood Control Project Authority (Sec. 205)

                                           ---------------------------------------------------------------------

Sec. 205 of 1948 FCA......................  June 30, 1948...............       80-858      $100,000   $2,000,000

Sec. 212 of 1950 FCA......................  May 17, 1950................       81-516       150,000    3,000,000

Public Law 685/84th Congress, 2d Sess.....  July 11, 1956...............       84-685       400,000   10,000,000

Sec. 205 of 1962 FCA......................  Oct. 23, 1962...............       87-874     1,000,000   25,000,000

Sec. 61 of WRDA of 1974...................  Mar. 7, 1974................       93-251           \1\   30,000,000

                                                                                          1,000,000

                                                                                                \3\

                                                                                          2,000,000

Sec. 133(6) WRDA of 1976..................  Oct. 22, 1976...............       94-587     2,000,000   30,000,000

                                                                                                \3\

                                                                                          3,000,000

                                           ---------------------------------------------------------------------

                                            (2) Authority for Snagging and Clearing for Flood Control (Sec. 208)

                                           ---------------------------------------------------------------------

Sec. 2 of 1937 FCA........................  Aug. 28, 1937...............       75-406       $25,000     $300,000

Sec. 13 of 1946 FCA.......................  July 24, 1946...............       79-526        50,000    1,000,000

Sec. 208 of 1954 FCA......................  Sept. 3, 1954...............       83-780       100,000    2,000,000

Sec. 26 of WRDA of 1974...................  Mar. 7, 1974................       93-251       250,000    5,000,000

                                           ---------------------------------------------------------------------

                                             (3) Authority for Emergency Streambank and Shoreline Protection of

                                                     Public Works and Nonprofit Public Services (Sec. 14)

                                           ---------------------------------------------------------------------

Sec. 14 of 1946 FCA.......................  July 24, 1946...............       79-526       $50,000   $1,000,000

Sec. 27 of WRDA of 1974...................  Mar. 7, 1974................       93-251       250,000   10,000,000

----------------------------------------------------------------------------------------------------------------

                                                      (4) Small Navigation Project Authority (Sec. 107)

                                           ---------------------------------------------------------------------

Sec. 107 of 1960 R. & H. Act..............  July 14, 1960...............       86-645      $200,000   $2,000,000

Sec. 310 of 1965 R. & H. Act..............  Oct. 27, 1965...............       89-298       500,000   10,000,000

Sec. 112 of 1970 R. & H. Act..............  Dec. 31, 1970...............       91-611     1,000,000   25,000,000

Sec. 133(a) of WRDA of 1976...............  Oct. 22, 1976...............       94-587     2,000,000   25,000,000

                                           ---------------------------------------------------------------------

                                               (5) Authority for Snagging and Clearing for Navigation (Sec. 3)

                                           ---------------------------------------------------------------------

Sec. 3 of 1945 R. & H. Act................  Mar. 2, 1945................        79-14          None     $300,000

                                           ---------------------------------------------------------------------

                                                (6) Small Beach Erosion Control Project Authority (Sec. 103)

                                           ---------------------------------------------------------------------

Sec. 103 of 1962 R. & H. Act..............  Oct. 23, 1962...............       87-874      $400,000   $3,000,000

Sec. 310 of 1965 R. & H. Act..............  Oct. 27, 1965...............       89-298       500,000   10,000,000

Sec. 112 of 1970 R. & H. Act..............  Dec. 31, 1970...............       91-611     1,000,000   25,000,000

                                           ---------------------------------------------------------------------

                                                (7) Authority for Mitigation of Shore Damages Attributable to

                                                                Navigation Projects (Sec. 111)

                                           ---------------------------------------------------------------------

Sec. 111 of 1968 R. & H. Act..............  Aug. 13, 1968...............       90-483           \2\         None

                                                                                         $1,000,000

----------------------------------------------------------------------------------------------------------------

\1\ Project cost may go to $2,000,000 if project is located in a major disaster area designated by the

  President.

\2\ A project exceeding $1 million will be transmitted to Congress for specific authorization.

\3\ Federal cost may go to higher amount if project is located in a major disaster area designated by the

  President.





[40 FR 51134, Nov. 3, 1975, as amended at 41 FR 56943, Dec. 30, 1976]



[[Page 365]]



Appendix B to Part 263--Application of Multiobjective Planning Framework 

                    to Continuing Authorities Program



    1. General. The planning process described in the ER 1105-2-200 

series of regulations including the implementation of Federal planning 

and evaluation criteria, are generally applicable to studies conducted 

under the Continuing Authorities Program. However, due to the limited 

scope of many of the plans and projects considered under this program, 

modification of the process is appropriate. Specific modification of the 

requirements of the planning criteria is not appropriate since the 

legislative and executive authorities setting forth these criteria do 

not differentiate between various types of level C implementation 

studies. Discretion must be employed by reporting officers and reviewers 

of Detailed Project Reports to insure that projects recommended for 

implementation by the Corps have been selected on the basis of 

information and analyses consistent with the WRC Principles and 

Standards, while at the same time keeping the requirements for 

information and analyses consistent with the scope of the study, 

solutions recommended, and the Program completion-time objectives 

outlined in Sec.  263.18 of this regulation.

    2. Plan Formulation Stages.

    a. Stage 1--Reconnaissance Study (Recon). As presented in para. 6c, 

a Reconnaissance will replace the Development of a Plan of Study as the 

primary element of Stage 1 planning. As a general rule, a Recon should 

be conducted by a study team consisting of an engineer, an economist, 

and an environmentalist. A one-to-two day field reconnaissance should be 

sufficient to analyze the need for a project, to develop sketch plans, 

discuss views and capabilities of local interests, and identify the 

economy of the potential project area and possible environmental issues 

that would need to be addressed if a feasibility study were to be 

conducted. Additional effort should pinpoint all data deficiencies, 

types of investigations required for the feasibility study, and the 

estimated cost of the study. The latter identification process can be 

developed as a Plan of Study for the feasibility study, if approved and 

funded. To accomplish the intended purpose of the Recon, within the time 

and cost objectives given in this regulation, reporting officers are not 

required to develop a specific project (except for emergency situations 

under Section 14 or 3 Authorities), but should only provide the 

information required to make a decision as to whether there is a Federal 

interest in conducting a feasibility study. Mature, seasoned judgment is 

a prime requisite.

    b. Stage 2--Development of Alternative Plans. While the ER 1105-2-

200 series of regulations provides for a three-stage development of 

plans, studies under Continuing Authorities may consolidate these two 

final stages (intermediate and detailed), into a single stage, if 

appropriate. This consolidation does not eliminate any of the planning 

tasks, as discussed in para 3 below, nor does it diminish the concept of 

screening a full array of alternatives including nonstructural measures, 

with increasing levels of detail in the assessment of impacts and 

evaluation as planning progresses to plan selection. The primary 

emphasis in making the consolidation of these two stages is that the 

plan selection is normally made on the basis of more limited data and 

analyses than appropriate for studies conducted under the Level C Survey 

Program or the Phase I AE&D Program.

    c. Stage 3--Development of Recommended Plan. The feasibility study 

under the Continuing Authorities Program will include the design of a 

recommended plan to the extent necessary to proceed directly from the 

Detailed Project Report to preparation of plans and specifications. 

While studies under the Level C Survey Program would complete plan 

formulation prior to accomplishing detailed project design, the nature 

of this Program necessitates a flexible design phase, wherein changes in 

scope of the selected plan, with accompanying changes in project impacts 

and evaluation, are to be expected and handled by planning personnel in 

order that the DPR will reflect a selected plan consistent with 

completed detailed design and a plan justified under the current Federal 

evaluation criteria for recommending Federal participation.

    3. Planning Tasks.

    a. Problem Identification. While planning under Continuing 

Authorities is to be on a multi-objective basis, the range of problems 

that can be addressed under a particular Program authority is more 

limited than normally considered in the conduct of studies specifically 

authorized by Congress. A good effort to focus the study on relevant 

problems should be made in the Recon phase of the study, while more 

intense efforts at data collection and definition of the problems and 

associated needs should be accomplished during Stage 2 planning.

    b. Formulation of Alternatives. There are no fundamental differences 

in the process of formulating alternatives under these Program 

authorities than in Level C Survey studies, with the exception that the 

array of alternatives will normally be more limited based on the 

discussion in para 3a above. The level of detail to which the 

alternatives are formulated, with associated assessments of impacts and 

evaluation of beneficial and adverse contributions, will vary greatly 

depending on the study authority. In some cases, alternatives will be 

screened and eliminated for various reasons without full development of 

a tentative plan which can be



[[Page 366]]



assessed and evaluated. Such screening is consistent with the nature of 

this Program; however, good judgment and interdisciplinary participation 

should be emphasized in such preliminary screenings. The guidance in the 

ER 1105-2-200 series of regulations with regard to consideration of non-

structural measures and formulation of NED and EQ plans, is fully 

applicable to studies conducted under this Program.

    c. Impact Assessment. There is no difference in the requirements for 

the assessment of impacts for studies conducted under Continuing 

Authorities and those under the Level C Survey Program. As in all 

studies, the extent to which information is obtained to adequately 

assess impacts of alternative plans is a matter of discretion of the 

reporting officer, bearing in mind the requirements of the National 

Environmental Policy Act of 1969 (NEPA) and Section 122, Public Law 91-

611.

    d. Evaluation. The processes, analyses and displays for evaluation 

of alternative plans as prescribed in the ER 1105-2-200 series of 

regulations are generally applicable to studies conducted under 

Continuing Authorities. Again, the level of detail, and not the process 

itself, is to be consistent with the study authority and the needs of 

the decision-making process.