[Code of Federal Regulations]

[Title 33, Volume 3]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 33CFR330.6]



[Page 481-483]

 

                TITLE 33--NAVIGATION AND NAVIGABLE WATERS

 

 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 

                                 DEFENSE

 

PART 330_NATIONWIDE PERMIT PROGRAM--Table of Contents

 

Sec.  330.6  Authorization by nationwide permit.



    (a) Nationwide permit verification. (1) Nationwide permittees may, 

and in some cases must, request from a DE confirmation that an activity 

complies with the terms and conditions of an NWP. DEs should respond as 

promptly as practicable to such requests.

    (2) If the DE decides that an activity does not comply with the 

terms or conditions of an NWP, he will notify the person desiring to do 

the work and instruct him on the procedures to seek authorization under 

a regional general permit or individual permit.

    (3) If the DE decides that an activity does comply with the terms 

and conditions of an NWP, he will notify the nationwide permittee.

    (i) The DE may add conditions on a case-by-case basis to clarify 

compliance with the terms and conditions of an NWP or to ensure that the 

activity will have only minimal individual and cumulative adverse 

effects on the environment, and will not be contrary to the public 

interest.

    (ii) The DE's response will state that the verification is valid for 

a specific period of time (generally but no more than two years) unless 

the NWP authorization is modified, suspended, or



[[Page 482]]



revoked. The response should also include a statement that the 

verification will remain valid for the specified period of time, if 

during that time period, the NWP authorization is reissued without 

modification or the activity complies with any subsequent modification 

of the NWP authorization. Furthermore, the response should include a 

statement that the provisions of Sec.  330.6(b) will apply, if during 

that period of time, the NWP authorization expires, or is suspended or 

revoked, or is modified, such that the activity would no longer comply 

with the terms and conditions of an NWP. Finally, the response should 

include any known expiration date that would occur during the specified 

period of time. A period of time less than two years may be used if 

deemed appropriate.

    (iii) For activities where a state has denied 401 water quality 

certification and/or did not agree with the Corps consistency 

determination for an NWP the DE's response will state that the proposed 

activity meets the terms and conditions for authorization under the NWP 

with the exception of a state 401 water quality certification and/or CZM 

consistency concurrence. The response will also indicate the activity is 

denied without prejudice and cannot be authorized until the requirements 

of Sec. Sec.  330.4(c)(3), 330.4(c)(6), 330.4(d)(3), and 330.4(d)(6) are 

satisfied. The response will also indicate that work may only proceed 

subject to the terms and conditions of the state 401 water quality 

certification and/or CZM concurrence.

    (iv) Once the DE has provided such verification, he must use the 

procedures of 33 CFR 330.5 in order to modify, suspend, or revoke the 

authorization.

    (b) Expiration of nationwide permits. The Chief of Engineers will 

periodically review NWPs and their conditions and will decide to either 

modify, reissue, or revoke the permits. If an NWP is not modified or 

reissued within five years of its effective date, it automatically 

expires and becomes null and void. Activities which have commenced (i.e, 

are under construction) or are under contract to commence in reliance 

upon an NWP will remain authorized provided the activity is completed 

within twelve months of the date of an NWP's expiration, modification, 

or revocation, unless discretionary authority has been exercised on a 

case-by-case basis to modify, suspend, or revoke the authorization in 

accordance with 33 CFR 330.4(e) and 33 CFR 330.5 (c) or (d). Activities 

completed under the authorization of an NWP which was in effect at the 

time the activity was completed continue to be authorized by that NWP.

    (c) Multiple use of nationwide permits. Two or more different NWPs 

can be combined to authorize a ``single and complete project'' as 

defined at 33 CFR 330.2(i). However, the same NWP cannot be used more 

than once for a single and complete project.

    (d) Combining nationwide permits with individual permits. Subject to 

the following qualifications, portions of a larger project may proceed 

under the authority of the NWPs while the DE evaluates an individual 

permit application for other portions of the same project, but only if 

the portions of the project qualifying for NWP authorization would have 

independent utility and are able to function or meet their purpose 

independent of the total project. When the functioning or usefulness of 

a portion of the total project qualifying for an NWP is dependent on the 

remainder of the project, such that its construction and use would not 

be fully justified even if the Corps were to deny the individual permit, 

the NWP does not apply and all portions of the project must be evaluated 

as part of the individual permit process.

    (1) When a portion of a larger project is authorized to proceed 

under an NWP, it is with the understanding that its construction will in 

no way prejudice the decision on the individual permit for the rest of 

the project. Furthermore, the individual permit documentation must 

include an analysis of the impacts of the entire project, including 

related activities authorized by NWP.

    (2) NWPs do not apply, even if a portion of the project is not 

dependent on the rest of the project, when any portion of the project is 

subject to an enforcement action by the Corps or EPA.

    (e) After-the-fact authorizations. These authorizations often play 

an important part in the resolution of violations. In



[[Page 483]]



appropriate cases where the activity complies with the terms and 

conditions of an NWP, the DE can elect to use the NWP for resolution of 

an after-the-fact permit situation following a consideration of whether 

the violation being resolved was knowing or intentional and other 

indications of the need for a penalty. For example, where an 

unauthorized fill meets the terms and conditions of NWP 13, the DE can 

consider the appropriateness of allowing the residual fill to remain, in 

situations where said fill would normally have been permitted under NWP 

13. A knowing, intentional, willful violation should be the subject of 

an enforcement action leading to a penalty, rather than an after-the-

fact authorization. Use of after-the-fact NWP authorization must be 

consistent with the terms of the Army/EPA Memorandum of Agreement on 

Enforcement. Copies are available from each district engineer.