Sec.  385.21  Quality control.



    (a) The Corps of Engineers and the non-Federal sponsor shall prepare 

a quality control plan, in accordance with applicable Corps of Engineers 

regulations, for each product that will be produced by a Project 

Delivery Team. The quality control plan shall be included in the Project 

Management Plan and shall describe the procedures to be used to ensure 

compliance with technical and policy requirements during implementation.

    (b) During development of the Project Management Plan for each 

project, the Corps of Engineers and the non-Federal sponsor shall 

establish a Technical Review Team to conduct reviews to ensure that 

products are consistent with established criteria, guidance, procedures, 

and policy. The members of the Technical Review Team



[[Page 633]]



shall be independent of the Project Delivery Team and the project being 

reviewed, and should be knowledgeable of design criteria established for 

the Plan.

    (c) Technical review is intended to be a continuous process 

throughout project implementation. The Technical Review Team shall 

document its actions and recommendations and provide reports to the 

Project Delivery Team at designated points during the implementation 

process that shall be described in the quality control plan.