[Code of Federal Regulations]

[Title 33, Volume 3]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 33CFR402.6]



[Page 694]

 

                TITLE 33--NAVIGATION AND NAVIGABLE WATERS

 

CHAPTER IV--SAINT LAWRENCE SEAWAY DEVELOPMENT CORPORATION, DEPARTMENT OF 

                             TRANSPORTATION

 

PART 402_TARIFF OF TOLLS--Table of Contents

 

Sec.  402.6  Post-clearance date operational surcharges.



    (a) Subject to paragraph (b) of this section, a vessel that reports 

for its final transit of the Seaway from a place set out in column 1 of 

Sec.  402.9 within a period after the clearance date established by the 

Manager and the Corporation set out in column 2 of Sec.  402.9 shall pay 

operational surcharges in the amount set out in column 3 of Sec.  402.9, 

prorated on a per-lock basis.

    (b) If surcharges are postponed for operational or climatic reasons, 

a vessel that reports for its final transit of the Seaway from a place 

set out in column 1 of Sec.  402.10 within a period after the clearance 

date established by the Manager and the Corporation set out in column 2 

of Sec.  402.10 shall pay operational surcharges in the amount set out 

in column 3 of Sec.  402.10, prorated on a per-lock basis.

    (c) A vessel that is authorized to transit the Seaway after the 

period of 96 hours after the clearance date established by the Manager 

and the Corporation shall pay, in addition to the operational surcharge, 

an amount equal to the incremental expenses incurred by the Manager to 

keep the Seaway open for the transit of the vessel.