[Code of Federal Regulations]

[Title 40, Volume 21]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 40CFR125.98]



[Page 359-363]

 

                   TITLE 40--PROTECTION OF ENVIRONMENT

 

         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)

 

PART 125_CRITERIA AND STANDARDS FOR THE NATIONAL POLLUTANT DISCHARGE 

ELIMINATION SYSTEM--Table of Contents

 

Subpart J_Requirements Applicable to Cooling Water Intake Structures for 

      Phase II Existing Facilities Under Section 316(b) of the Act

 

Sec.  125.98  As the Director, what must I do to comply with the 

requirements of this subpart?



    (a) Permit application. As the Director, you must review materials 

submitted by the applicant under 40 CFR 122.21(r) and Sec.  125.95 

before each permit renewal or reissuance.

    (1) You must review and comment on the Proposal for Information 

Collection submitted by the facility in accordance with Sec.  

125.95(a)(1). You are encouraged to provide comments expeditiously so 

that the permit applicant can make responsive modifications to its 

information gathering activities. If



[[Page 360]]



a facility submits a request in accordance with Sec.  125.95(a)(2)(ii) 

for an alternate schedule for submitting the information required in 

Sec.  125.95, you must approve a schedule that is as expeditious as 

practicable, but does not extend beyond January 7, 2008. If a facility 

submits a request in accordance with Sec.  125.95(a)(3) to reduce the 

information about their cooling water intake structures and the source 

waterbody required to be submitted in their permit application (other 

than with the first permit application after September 7, 2004), you 

must approve the request within 60 days if conditions at the facility 

and in the waterbody remain substantially unchanged since the previous 

application.

    (2) After receiving the permit application from the owner or 

operator of a Phase II existing facility, you must determine which of 

the requirements specified in Sec.  125.94 apply to the facility. In 

addition, you must review materials to determine compliance with the 

applicable requirements.

    (3) At each permit renewal, you must review the application 

materials and monitoring data to determine whether new or revised 

requirements for design and construction technologies, operational 

measures, or restoration measures should be included in the permit to 

meet the applicable performance standards in Sec.  125.94(b) or 

alternative site-specific requirements established pursuant to Sec.  

125.94(a)(5).

    (b) Permitting requirements. Section 316(b) requirements are 

implemented for a facility through an NPDES permit. As the Director, you 

must consider the information submitted by the Phase II existing 

facility in its permit application, and determine the appropriate 

requirements and conditions to include in the permit based on the 

compliance alternatives in Sec.  125.94(a). The following requirements 

must be included in each permit:

    (1) Cooling water intake structure requirements. The permit 

conditions must include the requirements that implement the applicable 

provisions of Sec.  125.94. You must evaluate the performance of the 

design and construction technologies, operational measures, and/or 

restoration measures proposed and implemented by the facility and 

require additional or different design and construction technologies, 

operational measure, and/or restoration measures, and/or improved 

operation and maintenance of existing technologies and measures, if 

needed to meet the applicable performance standards, restoration 

requirements, or alternative site-specific requirements. In determining 

compliance with the performance standards for facilities proposing to 

increase withdrawals of cooling water from a lake (other than a Great 

Lake) or a reservoir in Sec.  125.94(b)(3), you must consider 

anthropogenic factors (those not considered ``natural'') unrelated to 

the Phase II existing facility's cooling water intake structures that 

can influence the occurrence and location of a thermocline. These 

include source water inflows, other water withdrawals, managed water 

uses, wastewater discharges, and flow/level management practices (e.g., 

some reservoirs release water from deeper bottom layers). As the 

Director, you must coordinate with appropriate Federal, State, or Tribal 

fish and wildlife management agencies to determine if any disruption of 

the natural thermal stratification resulting from the proposed increased 

withdrawal of cooling water does not adversely affect the management of 

fisheries. Specifically:

    (i) You must review and approve the Design and Construction 

Technology Plan required in Sec.  125.95(b)(4) to evaluate the 

suitability and feasibility of the design and construction technology 

and/or operational measures proposed to meet the performance standards 

in Sec.  125.94(b) or site-specific requirements developed pursuant to 

Sec.  125.94(a)(5).

    (ii) If the facility proposes restoration measures in accordance 

with Sec.  125.94(c), you must review and approve the Restoration Plan 

required under Sec.  125.95(b)(5) to determine whether the proposed 

measures, alone or in combination with design and construction 

technologies and/or operational measures, will meet the requirements 

under Sec.  125.94(c).

    (iii) In each reissued permit, you must include a condition in the 

permit requiring the facility to reduce impingement mortality and 

entrainment (or to increase fish production, if applicable) commensurate 

with the efficacy



[[Page 361]]



at the facility of the installed design and construction technologies, 

operational measures, and/or restoration measures.

    (iv) If the facility implements design and construction technologies 

and/or operational measures and requests that compliance with the 

requirements in Sec.  125.94 be measured for the first permit term (or 

subsequent permit terms, if applicable) employing the Technology 

Installation and Operation Plan in accordance with Sec.  

125.95(b)(4)(ii), you must review the Technology Installation and 

Operation Plan to ensure it meets the requirements of Sec.  

125.95(b)(4)(ii). If the Technology Installation and Operation Plan 

meets the requirements of Sec.  125.95(b)(4)(ii), you must approve the 

Technology Installation and Operation Plan and require the facility to 

meet the terms of the plan including any revision to the plan that may 

be necessary if applicable performance standards or alternative site-

specific requirements are not being met. If the facility implements 

restoration measures and requests that compliance with the requirements 

in Sec.  125.94 be measured for the first permit term (or subsequent 

permit terms, if applicable) employing a Restoration Plan in accordance 

with Sec.  125.95(b)(5), you must review the Restoration Plan to ensure 

it meets the requirements of Sec.  125.95(b)(5). If the Restoration Plan 

meets the requirements of Sec.  125.95(b)(5), you must approve the plan 

and require the facility to meet the terms of the plan including any 

revision to the plan that may be necessary if applicable performance 

standards or site-specific requirements are not being met. In 

determining whether to approve a Technology Installation and Operation 

Plan or Restoration Plan, you must evaluate whether the design and 

construction technologies, operational measures, and/or restoration 

measures the facility has installed, or proposes to install, can 

reasonably be expected to meet the applicable performance standards in 

Sec.  125.94(b), restoration requirements in Sec.  125.94(c)(2), and/or 

alternative site-specific requirements established pursuant to Sec.  

125.94(a)(5), and whether the Technology Installation and Operation Plan 

and/or Restoration Plan complies with the applicable requirements of 

Sec.  125.95(b). In reviewing the Technology Installation and Operation 

Plan, you must approve any reasonable scheduling provisions that are 

designed to ensure that impacts to energy reliability and supply are 

minimized, in accordance with Sec.  125.95(b)(4)(ii)(A). If the facility 

does not request that compliance with the requirements in Sec.  125.94 

be measured employing a Technology Installation and Operation Plan and/

or Restoration Plan, or the facility has not been in compliance with the 

terms of its current Technology Installation and Operation Plan and/or 

Restoration Plan during the preceding permit term, you must require the 

facility to comply with the applicable performance standards in Sec.  

125.94(b), restoration requirement in Sec.  125.94(c)(2), and/or 

alternative site-specific requirements developed pursuant to Sec.  

125.94(a)(5). In considering a permit application, you must review the 

performance of the design and construction technologies, operational 

measures, and/or restoration measures implemented and require additional 

or different design and construction technologies, operational measures, 

and/or restoration measures, and/or improved operation and maintenance 

of existing technologies and measures, if needed to meet the applicable 

performance standards, restoration requirements, and/or alternative 

site-specific requirements.

    (v) You must review and approve the proposed Verification Monitoring 

Plan submitted under Sec.  125.95(b)(7) (for design and construction 

technologies) and/or monitoring provisions of the Restoration Plan 

submitted under Sec.  125.95(b)(5)(v) and require that the monitoring 

continue for a sufficient period of time to demonstrate whether the 

design and construction technology, operational measures, and/or 

restoration measures meet the applicable performance standards in Sec.  

125.94(b), restoration requirements in 125.94(c)(2) and/or site-specific 

requirements established pursuant to Sec.  125.94(a)(5).

    (vi) If a facility requests requirements based on a site-specific 

determination of best technology available for minimizing adverse 

environmental impact, you must review the application materials 

submitted under



[[Page 362]]



Sec.  125.95(b)(6) and any other information you may have, including 

quantitative and qualitative benefits, that would be relevant to a 

determination of whether alternative requirements are appropriate for 

the facility. If a facility submits a study to support entrainment 

survival at the facility, you must review and approve the results of 

that study. If you determine that alternative requirements are 

appropriate, you must make a site-specific determination of best 

technology available for minimizing adverse environmental impact in 

accordance with Sec.  125.94(a)(5). You, as the Director, may request 

revisions to the information submitted by the facility in accordance 

with Sec.  125.95(b)(6) if it does not provide an adequate basis for you 

to make this determination. Any alternative site-specific requirements 

established based on new and/or existing design and construction 

technologies, operational measures, and/or restoration measures, must 

achieve an efficacy that is, in your judgement, as close as practicable 

to the applicable performance standards of Sec.  125.94(b) without 

resulting in costs that are significantly greater than the costs 

considered by the Administrator for a like facility in establishing the 

applicable performance standards in Sec.  125.94(b), determined in 

accordance with Sec.  125.94(a)(5)(i)(A) through (F), or the benefits of 

complying with the applicable performance standards at the facility; and

    (vii) You must review the proposed methods for assessing success in 

meeting applicable performance standards and/or restoration requirements 

submitted by the facility under Sec.  125.95(b)(4)(ii)(D) and/or 

(b)(5)(v)(A), evaluate those and other available methods, and specify 

how assessment of success in meeting the performance standards and/or 

restoration requirements must be determined including the averaging 

period for determining the percent reduction in impingement mortality 

and entrainment and/or the production of fish and shellfish. Compliance 

for facilities who request that compliance be measured employing a 

Technology Installation and Operation Plan and/or Restoration Plan must 

be determined in accordance with Sec.  125.98(b)(1)(iv).

    (2) Monitoring conditions. You must require the facility to perform 

monitoring in accordance with the Technology Installation and Operation 

Plan in Sec.  125.95(b)(4)(ii), the Restoration Plan required by Sec.  

125.95(b)(5), if applicable, and the Verification Monitoring Plan 

required by Sec.  125.95(b)(7). In determining any additional applicable 

monitoring requirements in accordance with Sec.  125.96, you must 

consider the monitoring facility's Verification Monitoring, Technology 

Installation and Operation, and/or Restoration Plans, as appropriate. 

You may modify the monitoring program based on changes in physical or 

biological conditions in the vicinity of the cooling water intake 

structure.

    (3) Recordkeeping and reporting. At a minimum, the permit must 

require the facility to report and keep records specified in Sec.  

125.97.

    (4) Design and construction technology approval--(i) For a facility 

that chooses to demonstrate that it has installed and properly operate 

and maintain a design and construction technology approved in accordance 

with Sec.  125.99, the Director must review and approve the information 

submitted in the Technology Installation and Operation Plan in Sec.  

125.95(b)(4)(ii) and determine if it meets the criteria in Sec.  125.99.

    (ii) If a person requests approval of a technology under Sec.  

125.99(b), the Director must review and approve the information 

submitted and determine its suitability for widespread use at facilities 

with similar site conditions in its jurisdiction with minimal study. As 

the Director, you must evaluate the adequacy of the technology when 

installed in accordance with the required design criteria and site 

conditions to consistently meet the performance standards in Sec.  

125.94. You, as the Director, may only approve a technology following 

public notice and consideration of comment regarding such approval.

    (5) Bi-annual status report. You must specify monitoring data and 

other information to be included in a status report every two years. The 

other information may include operation and maintenance records, 

summaries of adaptive management activities, or any other information 

that is relevant to determining compliance with the



[[Page 363]]



terms of the facility's Technology Operation and Installation Plan and/

or Restoration Plan.