    (a) The facility supervisor should be experienced in the operation 

of the type of facility designed or, in the case of an innovated design, 

be adequately trained by responsible personnel in the operation of the 

facility.

    (b) Alternate and standby disposal and operating procedures should 

be established for implementation during emergencies, air pollution 

episodes, and shutdown periods.

    (c) Upon completion of facility construction, provision should be 

made for instruction of the staff in proper operation and maintenance 

procedures.

    (d) A routine maintenance schedule should be established and 

followed.

    (e) As-built engineering drawings of the facility should be provided 

at the conclusion of construction of the facility. These should be 

updated to show modifications by the owner as changes



[[Page 328]]



are made and should be readily available. A schematic showing the 

relationships of the various subsystems should also be available.

    (f) Key operational procedures should be prominently posted.

    (g) Equipment manuals, catalogs, spare parts lists, and spare parts 

should be readily available at the facility.

    (h) Training opportunities for facility operating personnel should 

be provided.