[Code of Federal Regulations]

[Title 40, Volume 12]

[Revised as of July 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 40CFR63.1510]



[Page 64-73]

 

                   TITLE 40--PROTECTION OF ENVIRONMENT

 

         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)

 

PART 63_NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR 

SOURCE CATEGORIES--Table of Contents

 

Subpart RRR_National Emission Standards for Hazardous Air Pollutants for 

                      Secondary Aluminum Production

 

Sec.  63.1510  Monitoring requirements.



    (a) Summary. On and after the compliance date established by Sec.  

63.1501, the owner or operator of a new or existing affected source or 

emission unit must monitor all control equipment and processes according 

to the requirements in this section. Monitoring requirements for each 

type of affected source and emission unit are summarized in Table 3 to 

this subpart.

    (b) Operation, maintenance, and monitoring (OM&M) plan. The owner or 

operator must prepare and implement for each new or existing affected 

source and emission unit, a written operation, maintenance, and 

monitoring (OM&M) plan. The owner or operator of an existing affected 

source must submit the OM&M plan to the responsible permitting authority 

no later than the compliance date established by Sec.  63.1501(a). The 

owner or operator of any new affected source must submit the OM&M plan 

to the responsible permitting authority within 90 days after a 

successful initial performance test under Sec.  63.1511(b), or within 90 

days after the compliance date established by Sec.  63.1501(b) if no 

initial performance test is required. The plan must be accompanied by a 

written certification by the owner or operator that the OM&M plan 

satisfies all requirements of this section and is otherwise consistent 

with the requirements of this subpart. The owner or operator must comply 

with all of the provisions of the OM&M plan as submitted to the 

permitting authority, unless and until the plan is revised in accordance 

with the following procedures. If the permitting authority determines at 

any time after receipt of the OM&M plan that any revisions of the plan 

are necessary to satisfy the requirements of this section or this 

subpart, the owner or operator must promptly make all necessary 

revisions and resubmit the revised plan. If the owner or operator 

determines that any other revisions of the OM&M plan are necessary, such 

revisions will not become effective until the owner or operator submits 

a description of the changes and a revised plan incorporating them to 

the permitting authority. Each plan must contain the following 

information:

    (1) Process and control device parameters to be monitored to 

determine compliance, along with established operating levels or ranges, 

as applicable, for each process and control device.

    (2) A monitoring schedule for each affected source and emission 

unit.

    (3) Procedures for the proper operation and maintenance of each 

process unit and add-on control device used to meet the applicable 

emission limits or standards in Sec.  63.1505.

    (4) Procedures for the proper operation and maintenance of 

monitoring devices or systems used to determine compliance, including:

    (i) Calibration and certification of accuracy of each monitoring 

device, at least once every 6 months, according to the manufacturer's 

instructions; and

    (ii) Procedures for the quality control and quality assurance of 

continuous emission or opacity monitoring systems as required by the 

general provisions in subpart A of this part.

    (5) Procedures for monitoring process and control device parameters, 

including procedures for annual inspections of afterburners, and if 

applicable, the procedure to be used for determining charge/feed (or 

throughput) weight if a measurement device is not used.

    (6) Corrective actions to be taken when process or operating 

parameters or add-on control device parameters deviate from the value or 

range established in paragraph (b)(1) of this section, including:



[[Page 65]]



    (i) Procedures to determine and record the cause of any deviation or 

excursion, and the time the deviation or excursion began and ended; and

    (ii) Procedures for recording the corrective action taken, the time 

corrective action was initiated, and the time/date corrective action was 

completed.

    (7) A maintenance schedule for each process and control device that 

is consistent with the manufacturer's instructions and recommendations 

for routine and long-term maintenance.

    (8) Documentation of the work practice and pollution prevention 

measures used to achieve compliance with the applicable emission limits 

and a site-specific monitoring plan as required in paragraph (o) of this 

section for each group 1 furnace not equipped with an add-on air 

pollution control device.

    (c) Labeling. The owner or operator must inspect the labels for each 

group 1 furnace, group 2 furnace, in-line fluxer and scrap dryer/

delacquering kiln/decoating kiln at least once per calendar month to 

confirm that posted labels as required by the operational standard in 

Sec.  63.1506(b) are intact and legible.

    (d) Capture/collection system. The owner or operator must:

    (1) Install, operate, and maintain a capture/collection system for 

each affected source and emission unit equipped with an add-on air 

pollution control device; and

    (2) Inspect each capture/collection and closed vent system at least 

once each calendar year to ensure that each system is operating in 

accordance with the operating requirements in Sec.  63.1506(c) and 

record the results of each inspection.

    (e) Feed/charge weight. The owner or operator of an affected source 

or emission unit subject to an emission limit in kg/Mg (lb/ton) or 

[micro]g/Mg (gr/ton) of feed/charge must install, calibrate, operate, 

and maintain a device to measure and record the total weight of feed/

charge to, or the aluminum production from, the affected source or 

emission unit over the same operating cycle or time period used in the 

performance test. Feed/charge or aluminum production within SAPUs must 

be measured and recorded on an emission unit-by-emission unit basis. As 

an alternative to a measurement device, the owner or operator may use a 

procedure acceptable to the applicable permitting authority to determine 

the total weight of feed/charge or aluminum production to the affected 

source or emission unit.

    (1) The accuracy of the weight measurement device or procedure must 

be 1 percent of the weight being measured. The 

owner or operator may apply to the permitting agency for approval to use 

a device of alternative accuracy if the required accuracy cannot be 

achieved as a result of equipment layout or charging practices. A device 

of alternative accuracy will not be approved unless the owner or 

operator provides assurance through data and information that the 

affected source will meet the relevant emission standard.

    (2) The owner or operator must verify the calibration of the weight 

measurement device in accordance with the schedule specified by the 

manufacturer, or if no calibration schedule is specified, at least once 

every 6 months.

    (f) Fabric filters and lime-injected fabric filters. The owner or 

operator of an affected source or emission unit using a fabric filter or 

lime-injected fabric filter to comply with the requirements of this 

subpart must install, calibrate, maintain, and continuously operate a 

bag leak detection system as required in paragraph (f)(1) of this 

section or a continuous opacity monitoring system as required in 

paragraph (f)(2) of this section. The owner or operator of an aluminum 

scrap shredder must install and operate a bag leak detection system as 

required in paragraph (f)(1) of this section, install and operate a 

continuous opacity monitoring system as required in paragraph (f)(2) of 

this section, or conduct visible emission observations as required in 

paragraph (f)(3) of this section.

    (1) These requirements apply to the owner or operator of a new or 

existing affected source or existing emission unit using a bag leak 

detection system.

    (i) The owner or operator must install and operate a bag leak 

detection system for each exhaust stack of a fabric filter.



[[Page 66]]



    (ii) Each triboelectric bag leak detection system must be installed, 

calibrated, operated, and maintained according to the ``Fabric Filter 

Bag Leak Detection Guidance,'' (September 1997). This document is 

available from the U.S. Environmental Protection Agency; Office of Air 

Quality Planning and Standards; Emissions, Monitoring and Analysis 

Division; Emission Measurement Center (MD-19), Research Triangle Park, 

NC 27711. This document also is available on the Technology Transfer 

Network (TTN) under Emission Measurement Technical Information (EMTIC), 

Continuous Emission Monitoring. Other bag leak detection systems must be 

installed, operated, calibrated, and maintained in a manner consistent 

with the manufacturer's written specifications and recommendations.

    (iii) The bag leak detection system must be certified by the 

manufacturer to be capable of detecting PM emissions at concentrations 

of 10 milligrams per actual cubic meter (0.0044 grains per actual cubic 

foot) or less.

    (iv) The bag leak detection system sensor must provide output of 

relative or absolute PM loadings.

    (v) The bag leak detection system must be equipped with a device to 

continuously record the output signal from the sensor.

    (vi) The bag leak detection system must be equipped with an alarm 

system that will sound automatically when an increase in relative PM 

emissions over a preset level is detected. The alarm must be located 

where it is easily heard by plant operating personnel.

    (vii) For positive pressure fabric filter systems, a bag leak 

detection system must be installed in each baghouse compartment or cell. 

For negative pressure or induced air fabric filters, the bag leak 

detector must be installed downstream of the fabric filter.

    (viii) Where multiple detectors are required, the system's 

instrumentation and alarm may be shared among detectors.

    (ix) The baseline output must be established by adjusting the range 

and the averaging period of the device and establishing the alarm set 

points and the alarm delay time.

    (x) Following initial adjustment of the system, the owner or 

operator must not adjust the sensitivity or range, averaging period, 

alarm set points, or alarm delay time except as detailed in the OM&M 

plan. In no case may the sensitivity be increased by more than 100 

percent or decreased more than 50 percent over a 365-day period unless 

such adjustment follows a complete fabric filter inspection which 

demonstrates that the fabric filter is in good operating condition.

    (2) These requirements apply to the owner or operator of a new or 

existing affected source or an existing emission unit using a continuous 

opacity monitoring system.

    (i) The owner or operator must install, calibrate, maintain, and 

operate a continuous opacity monitoring system to measure and record the 

opacity of emissions exiting each exhaust stack.

    (ii) Each continuous opacity monitoring system must meet the design 

and installation requirements of Performance Specification 1 in appendix 

B to 40 CFR part 60.

    (3) These requirements apply to the owner or operator of a new or 

existing aluminum scrap shredder who conducts visible emission 

observations. The owner or operator must:

    (i) Perform a visible emissions test for each aluminum scrap 

shredder using a certified observer at least once a day according to the 

requirements of Method 9 in appendix A to 40 CFR part 60. Each Method 9 

test must consist of five 6-minute observations in a 30-minute period; 

and

    (ii) Record the results of each test.

    (g) Afterburner. These requirements apply to the owner or operator 

of an affected source using an afterburner to comply with the 

requirements of this subpart.

    (1) The owner or operator must install, calibrate, maintain, and 

operate a device to continuously monitor and record the operating 

temperature of the afterburner consistent with the requirements for 

continuous monitoring systems in subpart A of this part.

    (2) The temperature monitoring device must meet each of these 

performance and equipment specifications:



[[Page 67]]



    (i) The temperature monitoring device must be installed at the exit 

of the combustion zone of each afterburner.

    (ii) The monitoring system must record the temperature in 15-minute 

block averages and determine and record the average temperature for each 

3-hour block period.

    (iii) The recorder response range must include zero and 1.5 times 

the average temperature established according to the requirements in 

Sec.  63.1512(m).

    (iv) The reference method must be a National Institute of Standards 

and Technology calibrated reference thermocouple-potentiometer system or 

alternate reference, subject to approval by the Administrator.

    (3) The owner or operator must conduct an inspection of each 

afterburner at least once a year and record the results. At a minimum, 

an inspection must include:

    (i) Inspection of all burners, pilot assemblies, and pilot sensing 

devices for proper operation and clean pilot sensor;

    (ii) Inspection for proper adjustment of combustion air;

    (iii) Inspection of internal structures (e.g., baffles) to ensure 

structural integrity;

    (iv) Inspection of dampers, fans, and blowers for proper operation;

    (v) Inspection for proper sealing;

    (vi) Inspection of motors for proper operation;

    (vii) Inspection of combustion chamber refractory lining and clean 

and replace lining as necessary;

    (viii) Inspection of afterburner shell for corrosion and/or hot 

spots;

    (ix) Documentation, for the burn cycle that follows the inspection, 

that the afterburner is operating properly and any necessary adjustments 

have been made; and

    (x) Verification that the equipment is maintained in good operating 

condition.

    (xi) Following an equipment inspection, all necessary repairs must 

be completed in accordance with the requirements of the OM&M plan.

    (h) Fabric filter inlet temperature. These requirements apply to the 

owner or operator of a scrap dryer/delacquering kiln/decoating kiln or a 

group 1 furnace using a lime-injected fabric filter to comply with the 

requirements of this subpart.

    (1) The owner or operator must install, calibrate, maintain, and 

operate a device to continuously monitor and record the temperature of 

the fabric filter inlet gases consistent with the requirements for 

continuous monitoring systems in subpart A of this part.

    (2) The temperature monitoring device must meet each of these 

performance and equipment specifications:

    (i) The monitoring system must record the temperature in 15-minute 

block averages and calculate and record the average temperature for each 

3-hour block period.

    (ii) The recorder response range must include zero and 1.5 times the 

average temperature established according to the requirements in Sec.  

63.1512(n).

    (iii) The reference method must be a National Institute of Standards 

and Technology calibrated reference thermocouple-potentiometer system or 

alternate reference, subject to approval by the Administrator.

    (i) Lime injection. These requirements apply to the owner or 

operator of an affected source or emission unit using a lime-injected 

fabric filter to comply with the requirements of this subpart.

    (1) The owner or operator of a continuous lime injection system must 

verify that lime is always free-flowing by either:

    (i) Inspecting each feed hopper or silo at least once each 8-hour 

period and recording the results of each inspection. If lime is found 

not to be free-flowing during any of the 8-hour periods, the owner or 

operator must increase the frequency of inspections to at least once 

every 4-hour period for the next 3 days. The owner or operator may 

return to inspections at least once every 8 hour period if corrective 

action results in no further blockages of lime during the 3-day period; 

or

    (ii) Subject to the approval of the permitting agency, installing, 

operating and maintaining a load cell, carrier gas/lime flow indicator, 

carrier gas pressure drop measurement system or other system to confirm 

that lime is free-flowing. If lime is found not to be free-flowing, the 

owner or operator



[[Page 68]]



must promptly initiate and complete corrective action, or

    (iii) Subject to the approval of the permitting agency, installing, 

operating and maintaining a device to monitor the concentration of HCl 

at the outlet of the fabric filter. If an increase in the concentration 

of HCl indicates that the lime is not free-flowing, the owner or 

operator must promptly initiate and complete corrective action.

    (2) The owner or operator of a continuous lime injection system must 

record the lime feeder setting once each day of operation.

    (3) An owner or operator who intermittently adds lime to a lime 

coated fabric filter must obtain approval from the permitting authority 

for a lime addition monitoring procedure. The permitting authority will 

not approve a monitoring procedure unless data and information are 

submitted establishing that the procedure is adequate to ensure that 

relevant emission standards will be met on a continuous basis.

    (j) Total reactive flux injection rate. These requirements apply to 

the owner or operator of a group 1 furnace (with or without add-on air 

pollution control devices) or in-line fluxer. The owner or operator 

must:

    (1) Install, calibrate, operate, and maintain a device to 

continuously measure and record the weight of gaseous or liquid reactive 

flux injected to each affected source or emission unit.

    (i) The monitoring system must record the weight for each 15-minute 

block period, during which reactive fluxing occurs, over the same 

operating cycle or time period used in the performance test.

    (ii) The accuracy of the weight measurement device must be 1 percent of the weight of the reactive component of the 

flux being measured. The owner or operator may apply to the permitting 

authority for permission to use a weight measurement device of 

alternative accuracy in cases where the reactive flux flow rates are so 

low as to make the use of a weight measurement device of 1 percent impracticable. A device of alternative 

accuracy will not be approved unless the owner or operator provides 

assurance through data and information that the affected source will 

meet the relevant emission standards.

    (iii) The owner or operator must verify the calibration of the 

weight measurement device in accordance with the schedule specified by 

the manufacturer, or if no calibration schedule is specified, at least 

once every 6 months.

    (2) Calculate and record the gaseous or liquid reactive flux 

injection rate (kg/Mg or lb/ton) for each operating cycle or time period 

used in the performance test using the procedure in Sec.  63.1512(o).

    (3) Record, for each 15-minute block period during each operating 

cycle or time period used in the performance test during which reactive 

fluxing occurs, the time, weight, and type of flux for each addition of:

    (i) Gaseous or liquid reactive flux other than chlorine; and

    (ii) Solid reactive flux.

    (4) Calculate and record the total reactive flux injection rate for 

each operating cycle or time period used in the performance test using 

the procedure in Sec.  63.1512(o).

    (5) The owner or operator of a group 1 furnace or in-line fluxer 

performing reactive fluxing may apply to the Administrator for approval 

of an alternative method for monitoring and recording the total reactive 

flux addition rate based on monitoring the weight or quantity of 

reactive flux per ton of feed/charge for each operating cycle or time 

period used in the performance test. An alternative monitoring method 

will not be approved unless the owner or operator provides assurance 

through data and information that the affected source will meet the 

relevant emission standards on a continuous basis.

    (k) Thermal chip dryer. These requirements apply to the owner or 

operator of a thermal chip dryer with emissions controlled by an 

afterburner. The owner or operator must:

    (1) Record the type of materials charged to the unit for each 

operating cycle or time period used in the performance test.

    (2) Submit a certification of compliance with the applicable 

operational standard for charge materials in Sec.  63.1506(f)(3) for 

each 6-month reporting



[[Page 69]]



period. Each certification must contain the information in Sec.  

63.1516(b)(2)(i).

    (l) Dross-only furnace. These requirements apply to the owner or 

operator of a dross-only furnace. The owner or operator must:

    (1) Record the materials charged to each unit for each operating 

cycle or time period used in the performance test.

    (2) Submit a certification of compliance with the applicable 

operational standard for charge materials in Sec.  63.1506(i)(3) for 

each 6-month reporting period. Each certification must contain the 

information in Sec.  63.1516(b)(2)(ii).

    (m) In-line fluxers using no reactive flux. The owner or operator of 

an in-line fluxer that uses no reactive flux materials must submit a 

certification of compliance with the operational standard for no 

reactive flux materials in Sec.  63.1506(l) for each 6-month reporting 

period. Each certification must contain the information in Sec.  

63.1516(b)(2)(vi).

    (n) Sidewell group 1 furnace with add-on air pollution control 

devices. These requirements apply to the owner or operator of a sidewell 

group 1 furnace using add-on air pollution control devices. The owner or 

operator must:

    (1) Record in an operating log for each charge of a sidewell furnace 

that the level of molten metal was above the top of the passage between 

the sidewell and hearth during reactive flux injection, unless the 

furnace hearth was also equipped with an add-on control device.

    (2) Submit a certification of compliance with the operational 

standards in Sec.  63.1506(m)(7) for each 6-month reporting period. Each 

certification must contain the information in Sec.  63.1516(b)(2)(iii).

    (o) Group 1 furnace without add-on air pollution control devices. 

These requirements apply to the owner or operator of a group 1 furnace 

that is not equipped with an add-on air pollution control device.

    (1) The owner or operator must develop, in consultation with the 

responsible permitting authority, a written site-specific monitoring 

plan. The site-specific monitoring plan must be submitted to the 

permitting authority as part of the OM&M plan. The site-specific 

monitoring plan must contain sufficient procedures to ensure continuing 

compliance with all applicable emission limits and must demonstrate, 

based on documented test results, the relationship between emissions of 

PM, HCl, and D/F and the proposed monitoring parameters for each 

pollutant. Test data must establish the highest level of PM, HCl, and D/

F that will be emitted from the furnace. This may be determined by 

conducting performance tests and monitoring operating parameters while 

charging the furnace with feed/charge materials containing the highest 

anticipated levels of oils and coatings and fluxing at the highest 

anticipated rate. If the permitting authority determines that any 

revisions of the site-specific monitoring plan are necessary to meet the 

requirements of this section or this subpart, the owner or operator must 

promptly make all necessary revisions and resubmit the revised plan to 

the permitting authority.

    (i) The owner or operator of an existing affected source must submit 

the site-specific monitoring plan to the applicable permitting authority 

for review at least 6 months prior to the compliance date.

    (ii) The permitting authority will review and approve or disapprove 

a proposed plan, or request changes to a plan, based on whether the plan 

contains sufficient provisions to ensure continuing compliance with 

applicable emission limits and demonstrates, based on documented test 

results, the relationship between emissions of PM, HCl, and D/F and the 

proposed monitoring parameters for each pollutant. Test data must 

establish the highest level of PM, HCl, and D/F that will be emitted 

from the furnace. Subject to permitting agency approval of the OM&M 

plan, this may be determined by conducting performance tests and 

monitoring operating parameters while charging the furnace with feed/

charge materials containing the highest anticipated levels of oils and 

coatings and fluxing at the highest anticipated rate.

    (2) Each site-specific monitoring plan must document each work 

practice, equipment/design practice, pollution prevention practice, or 

other measure



[[Page 70]]



used to meet the applicable emission standards.

    (3) Each site-specific monitoring plan must include provisions for 

unit labeling as required in paragraph (c) of this section, feed/charge 

weight measurement (or production weight measurement) as required in 

paragraph (e) of this section and flux weight measurement as required in 

paragraph (j) of this section.

    (4) Each site-specific monitoring plan for a melting/holding furnace 

subject to the clean charge emission standard in Sec.  63.1505(i)(3) 

must include these requirements:

    (i) The owner or operator must record the type of feed/ charge 

(e.g., ingot, thermally dried chips, dried scrap, etc.) for each 

operating cycle or time period used in the performance test; and

    (ii) The owner or operator must submit a certification of compliance 

with the applicable operational standard for clean charge materials in 

Sec.  63.1506(n)(3) for each 6-month reporting period. Each 

certification must contain the information in Sec.  63.1516(b)(2)(iv).

    (5) If a continuous emission monitoring system is included in a 

site-specific monitoring plan, the plan must include provisions for the 

installation, operation, and maintenance of the system to provide 

quality-assured measurements in accordance with all applicable 

requirements of the general provisions in subpart A of this part.

    (6) If a continuous opacity monitoring system is included in a site-

specific monitoring plan, the plan must include provisions for the 

installation, operation, and maintenance of the system to provide 

quality-assured measurements in accordance with all applicable 

requirements of this subpart.

    (7) If a site-specific monitoring plan includes a scrap inspection 

program for monitoring the scrap contaminant level of furnace feed/

charge materials, the plan must include provisions for the demonstration 

and implementation of the program in accordance with all applicable 

requirements in paragraph (p) of this section.

    (8) If a site-specific monitoring plan includes a calculation method 

for monitoring the scrap contaminant level of furnace feed/charge 

materials, the plan must include provisions for the demonstration and 

implementation of the program in accordance with all applicable 

requirements in paragraph (q) of this section.

    (p) Scrap inspection program for group 1 furnace without add-on air 

pollution control devices. A scrap inspection program must include:

    (1) A proven method for collecting representative samples and 

measuring the oil and coatings content of scrap samples;

    (2) A scrap inspector training program;

    (3) An established correlation between visual inspection and 

physical measurement of oil and coatings content of scrap samples;

    (4) Periodic physical measurements of oil and coatings content of 

randomly-selected scrap samples and comparison with visual inspection 

results;

    (5) A system for assuring that only acceptable scrap is charged to 

an affected group 1 furnace; and

    (6) Recordkeeping requirements to document conformance with plan 

requirements.

    (q) Monitoring of scrap contamination level by calculation method 

for group 1 furnace without add-on air pollution control devices. The 

owner or operator of a group 1 furnace dedicated to processing a 

distinct type of furnace feed/charge composed of scrap with a uniform 

composition (such as rejected product from a manufacturing process for 

which the coating-to-scrap ratio can be documented) may include a 

program in the site-specific monitoring plan for determining, 

monitoring, and certifying the scrap contaminant level using a 

calculation method rather than a scrap inspection program. A scrap 

contaminant monitoring program using a calculation method must include:

    (1) Procedures for the characterization and documentation of the 

contaminant level of the scrap prior to the performance test.

    (2) Limitations on the furnace feed/charge to scrap of the same 

composition as that used in the performance test. If the performance 

test was conducted with a mixture of scrap and clean charge, limitations 

on the proportion of scrap in the furnace feed/



[[Page 71]]



charge to no greater than the proportion used during the performance 

test.

    (3) Operating, monitoring, recordkeeping, and reporting requirements 

to ensure that no scrap with a contaminant level higher than that used 

in the performance test is charged to the furnace.

    (r) Group 2 furnace. These requirements apply to the owner or 

operator of a new or existing group 2 furnace. The owner or operator 

must:

    (1) Record a description of the materials charged to each furnace, 

including any nonreactive, non-HAP-containing/non-HAP-generating fluxing 

materials or agents.

    (2) Submit a certification of compliance with the applicable 

operational standard for charge materials in Sec.  63.1506(o) for each 

6-month reporting period. Each certification must contain the 

information in Sec.  63.1516(b)(2)(v).

    (s) Site-specific requirements for secondary aluminum processing 

units. (1) An owner or operator of a secondary aluminum processing unit 

at a facility must include, within the OM&M plan prepared in accordance 

with Sec.  63.1510(b), the following information:

    (i) The identification of each emission unit in the secondary 

aluminum processing unit;

    (ii) The specific control technology or pollution prevention measure 

to be used for each emission unit in the secondary aluminum processing 

unit and the date of its installation or application;

    (iii) The emission limit calculated for each secondary aluminum 

processing unit and performance test results with supporting 

calculations demonstrating initial compliance with each applicable 

emission limit;

    (iv) Information and data demonstrating compliance for each emission 

unit with all applicable design, equipment, work practice or operational 

standards of this subpart; and

    (v) The monitoring requirements applicable to each emission unit in 

a secondary aluminum processing unit and the monitoring procedures for 

daily calculation of the 3-day, 24-hour rolling average using the 

procedure in Sec.  63.1510(t).

    (2) The SAPU compliance procedures within the OM&M plan may not 

contain any of the following provisions:

    (i) Any averaging among emissions of differing pollutants;

    (ii) The inclusion of any affected sources other than emission units 

in a secondary aluminum processing unit;

    (iii) The inclusion of any emission unit while it is shutdown; or

    (iv) The inclusion of any periods of startup, shutdown, or 

malfunction in emission calculations.

    (3) To revise the SAPU compliance provisions within the OM&M plan 

prior to the end of the permit term, the owner or operator must submit a 

request to the applicable permitting authority containing the 

information required by paragraph (s)(1) of this section and obtain 

approval of the applicable permitting authority prior to implementing 

any revisions.

    (t) Secondary aluminum processing unit. Except as provided in 

paragraph (u) of this section, the owner or operator must calculate and 

record the 3-day, 24-hour rolling average emissions of PM, HCl, and D/F 

for each secondary aluminum processing unit on a daily basis. To 

calculate the 3-day, 24-hour rolling average, the owner or operator 

must:

    (1) Calculate and record the total weight of material charged to 

each emission unit in the secondary aluminum processing unit for each 

24-hour day of operation using the feed/charge weight information 

required in paragraph (e) of this section. If the owner or operator 

chooses to comply on the basis of weight of aluminum produced by the 

emission unit, rather than weight of material charged to the emission 

unit, all performance test emissions results and all calculations must 

be conducted on the aluminum production weight basis.

    (2) Multiply the total feed/charge weight to the emission unit, or 

the weight of aluminum produced by the emission unit, for each emission 

unit for the 24-hour period by the emission rate (in lb/ton of feed/

charge) for that emission unit (as determined during the performance 

test) to provide emissions for each emission unit for the 24-hour 

period, in pounds.



[[Page 72]]



    (3) Divide the total emissions for each SAPU for the 24-hour period 

by the total material charged to the SAPU, or the weight of aluminum 

produced by the SAPU over the 24-hour period to provide the daily 

emission rate for the SAPU.

    (4) Compute the 24-hour daily emission rate using Equation 4:

    [GRAPHIC] [TIFF OMITTED] TR23MR00.003

    

Where,



Eday = The daily PM, HCl, or D/F emission rate for the 

secondary aluminum processing unit for the 24-hour period;

Ti = The total amount of feed, or aluminum produced, for 

emission unit i for the 24-hour period (tons or Mg);

ERi = The measured emission rate for emission unit i as 

determined in the performance test (lb/ton or [micro]g/Mg of feed/

charge); and

n = The number of emission units in the secondary aluminum processing 

unit.



    (5) Calculate and record the 3-day, 24-hour rolling average for each 

pollutant each day by summing the daily emission rates for each 

pollutant over the 3 most recent consecutive days and dividing by 3.

    (u) Secondary aluminum processing unit compliance by individual 

emission unit demonstration. As an alternative to the procedures of 

paragraph (t) of this section, an owner or operator may demonstrate, 

through performance tests, that each individual emission unit within the 

secondary aluminum production unit is in compliance with the applicable 

emission limits for the emission unit.

    (v) Alternative monitoring method for lime addition. The owner or 

operator of a lime-coated fabric filter that employs intermittent or 

noncontinuous lime addition may apply to the Administrator for approval 

of an alternative method for monitoring the lime addition schedule and 

rate based on monitoring the weight of lime added per ton of feed/charge 

for each operating cycle or time period used in the performance test. An 

alternative monitoring method will not be approved unless the owner or 

operator provides assurance through data and information that the 

affected source will meet the relevant emission standards on a 

continuous basis.

    (w) Alternative monitoring methods. If an owner or operator wishes 

to use an alternative monitoring method to demonstrate compliance with 

any emission standard in this subpart, other than those alternative 

monitoring methods which may be authorized pursuant to Sec.  

63.1510(j)(5) and Sec.  63.1510(v), the owner or operator may submit an 

application to the Administrator. Any such application will be processed 

according to the criteria and procedures set forth in paragraphs (w)(1) 

through (6) of this section.

    (1) The Administrator will not approve averaging periods other than 

those specified in this section.

    (2) The owner or operator must continue to use the original 

monitoring requirement until necessary data are submitted and approval 

is received to use another monitoring procedure.

    (3) The owner or operator shall submit the application for approval 

of alternate monitoring methods no later than the notification of the 

performance test. The application must contain the information specified 

in paragraphs (w)(3) (i) through (iii) of this section:

    (i) Data or information justifying the request, such as the 

technical or economic infeasibility, or the impracticality of using the 

required approach;

    (ii) A description of the proposed alternative monitoring 

requirements, including the operating parameters to be monitored, the 

monitoring approach and technique, and how the limit is to be 

calculated; and

    (iii) Data and information documenting that the alternative 

monitoring requirement(s) would provide equivalent or better assurance 

of compliance with the relevant emission standard(s).

    (4) The Administrator will not approve an alternate monitoring 

application unless it would provide equivalent or better assurance of 

compliance with the relevant emission standard(s). Before disapproving 

any alternate monitoring application, the Administrator will provide:



[[Page 73]]



    (i) Notice of the information and findings upon which the intended 

disapproval is based; and

    (ii) Notice of opportunity for the owner or operator to present 

additional supporting information before final action is taken on the 

application. This notice will specify how much additional time is 

allowed for the owner or operator to provide additional supporting 

information.

    (5) The owner or operator is responsible for submitting any 

supporting information in a timely manner to enable the Administrator to 

consider the application prior to the performance test. Neither 

submittal of an application nor the Administrator's failure to approve 

or disapprove the application relieves the owner or operator of the 

responsibility to comply with any provisions of this subpart.

    (6) The Administrator may decide at any time, on a case-by-case 

basis, that additional or alternative operating limits, or alternative 

approaches to establishing operating limits, are necessary to 

demonstrate compliance with the emission standards of this subpart.



[65 FR 15710, Mar. 23, 2000, as amended at 67 FR 59792, Sept. 24, 2002; 

67 FR 79816, Dec. 30, 2002; 69 FR 53984, Sept. 3, 2004]