Sec.  63.77  Application procedures.



    (a) To apply for an alternative emission limitation under Sec.  

63.72, an owner or operator of the source shall file a permit 

application with the appropriate permitting authority.

    (b) Except as provided in paragraph (e) of this section, the permit 

application shall contain the information required by Sec.  63.74, as 

applicable, and the additional information required for a complete 

permit application as specified by the applicable permit program 

established pursuant to title V of the Act.

    (c) Permit applications under this section for sources not subject 

to enforceable commitments shall be submitted by the later of the 

following dates:

    (1) 120 days after proposal of an otherwise applicable standard 

issued under section 112(d) of the Act; or

    (2) 120 days after the date an applicable permit program is approved 

or established pursuant to title V of the Act.



[[Page 101]]



    (d) Permit applications for sources subject to enforceable 

commitments pursuant to Sec.  63.75 shall be submitted no later than 

April 30, 1994.

    (e) If the post-reduction year does not end at least one month 

before the permit application deadline under paragraph (c) of this 

section, the source may file the post-reduction emissions information 

required under Sec.  63.74(d)(2), (d)(3), and (d)(5) later as a 

supplement to the original permit application. In such cases, this 

supplemental information shall be submitted to the permitting authority 

no later than one month after the end of the post-reduction year.

    (f) If a source test will be the supporting basis for establishing 

post-reduction emissions for one or more emissions units in the early 

reductions source, the test results shall be submitted by the applicable 

deadline for submittal of a permit application as specified in paragraph 

(c) or (d) of this section.

    (g) Review and disposition of permit applications submitted under 

this section will be accomplished according to the provisions of the 

applicable permit program established pursuant to title V of the Act.



[58 FR 62543, Nov. 29, 1993, as amended at 59 FR 59924, Nov. 21, 1994]