[Code of Federal Regulations]

[Title 43, Volume 2]

[Revised as of October 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 43CFR1822.14]



[Page 37]

 

                    TITLE 43--PUBLIC LANDS: INTERIOR

 

    CHAPTER II--BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR

 

PART 1820_APPLICATION PROCEDURES--Table of Contents

 

                 Subpart 1822_Filing a Document with BLM

 

Sec.  1822.14  What if I try to file a required document on the last day of the stated period for filing, but the BLM office where it is to be filed is 

          officially closed all day?



    BLM considers the document timely filed if we receive it in the 

office on the next day it is officially open.