Sec.  2881.12  When do I need a TUP for an oil and gas pipeline?



    You must obtain a TUP from BLM when you require temporary use of 

more land than your grant authorizes in order to construct, operate, 

maintain, or terminate your pipeline, or to protect the environment or 

public safety.