[Code of Federal Regulations]

[Title 43, Volume 2]

[Revised as of October 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 43CFR2885.19]



[Page 292]

 

                    TITLE 43--PUBLIC LANDS: INTERIOR

 

    CHAPTER II--BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR

 

PART 2880_RIGHTS-OF-WAY UNDER THE MINERAL LEASING ACT--Table of Contents

 

        Subpart 2885_Terms and Conditions of MLA Grants and TUPs

 

Sec.  2885.19  What is the rent for a linear right-of-way?



    (a) Except as noted in paragraph (b) of this section, BLM will use 

the Per Acre Rent Schedule at Sec.  2806.20(b) of this chapter to 

calculate the rent. The Per Acre Rent Schedule is updated annually in 

accordance with Sec.  2806.21 of this chapter.

    (b) BLM may determine your rent using the methods described in Sec.  

2806.50 of this chapter, rather than by using the rent schedule cited in 

paragraph (a) of this section if the rent determined by comparable 

commercial practices or an appraisal would be 10 or more times the rent 

from the schedule.

    (c) Once you are on a rent schedule, BLM will not remove you from 

it, unless:

    (1) The BLM State Director decides to remove you from the schedule 

under paragraph (b) of this section; or

    (2) You file an application to amend your grant.

    (d) You may obtain the current linear right-of-way rent schedule 

from any BLM state or field office or by writing: Director, BLM, 1849 C 

St., NW., Mail Stop 1000 LS, Washington, DC 20240. BLM also posts the 

current rent schedule on the BLM Homepage on the Internet at http://

www.blm.gov.