[Code of Federal Regulations]

[Title 43, Volume 2]

[Revised as of October 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 43CFR3000.5]



[Page 326]

 

                    TITLE 43--PUBLIC LANDS: INTERIOR

 

    CHAPTER II--BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR

 

PART 3000_MINERALS MANAGEMENT: GENERAL--Table of Contents

 

                          Subpart 3000_General

 

Sec.  3000.5  Limitations on time to institute suit to contest a decision of the Secretary.



    No action contesting a decision of the Secretary involving any oil 

or gas lease, offer or application shall be maintained unless such 

action is commenced or taken within 90 days after the final decision of 

the Secretary relating to such matter.