[Code of Federal Regulations]

[Title 43, Volume 2]

[Revised as of October 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 43CFR3162.2-10]



[Page 431]

 

                    TITLE 43--PUBLIC LANDS: INTERIOR

 

    CHAPTER II--BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR

 

PART 3160_ONSHORE OIL AND GAS OPERATIONS--Table of Contents

 

   Subpart 3162_Requirements for Operating Rights Owners and Operators

 

Sec.  3162.2-10  Will BLM notify me when it determines that drainage is occurring?



    We will send you a demand letter by certified mail, return receipt 

requested, or personally serve you with notice, if we believe that 

drainage is occurring. However, your responsibility to take protective 

action arises when you first knew or had constructive notice of the 

drainage, even when that date precedes the BLM demand letter.



[66 FR 1894, Jan. 10, 2001]