Sec.  101.31  Temporary and conditional authorizations.



    (a) Operation at temporary locations. (1) Authorizations may be 

issued upon proper application for rendition of temporary service to 

subscribers under the following conditions:

    (i) When a fixed station, authorized to operate at temporary 

locations, is to remain at a single location for more than 6 months, an 

application for a station authorization designating that single location 

as the permanent location shall be filed at least 90 days prior to the 

expiration of the 6 month period;

    (ii) The station shall be used only for rendition of communication 

service at a remote point where the provision of wire facilities is not 

practicable within the required time frame; and

    (iii) The antenna structure height employed at any location shall 

not exceed the criteria set forth in Sec.  17.7 of this chapter unless, 

in each instance, authorization for use of a specific maximum antenna 

structure height for each location has been obtained from the Commission 

prior to erection of the antenna. See Sec.  101.125.

    (2) Applications for authorizations to operate stations at temporary 

locations under the provisions of this section shall be made upon FCC 

Form 601. Blanket applications may be submitted for the required number 

of transmitters. An application for authority to operate a fixed station 

at temporary locations must specify the precise geographic area within 

which the operation will be confined. The area specified must be defined 

as a radius of operation about a specific coordinate (latitude/

longitude), or as a county, or as a State. Exception to this specific 

requirement may be made for exceptionally large areas, such as the 

continental United States. Sufficient data must be submitted to show the 

need for the proposed area of operation.

    (3) Operations in the 17.8-19.7 GHz band are prohibited in the areas 

defined in Sec.  1.924 of this chapter. Operations proposed in the areas 

defined in Sec.  1.924 of this chapter may not commence without prior 

specific notification to, and authorization from, the Commission.

    (b) Conditional authorization. (1) An applicant for a new point-to-

point microwave radio station(s) or a modification of an existing 

station(s) in the 952.95-956.15, 956.55-959.75, 3,700-4,200; 5,925-

6,425; 6,525-6,875; 10,550-10,680; 10,700-11,700; 11,700-12,200; 12,700-

13,200; 13,200-13,250; 17,700-19,700; and 21,800-22,000 MHz, and 23,000-

23,200 MHz bands (see Sec.  101.147(s) for specific service usage) may 

operate the proposed station(s) during the pendency of its 

applications(s) upon the filing of a properly completed formal 

application(s) that complies with subpart B of part 101 if the applicant 

certifies that the following conditions are satisfied:

    (i) The frequency coordination procedures of Sec.  101.103 have been 

successfully completed;

    (ii) The antenna structure(s) has been previously studied by the 

Federal Aviation Administration and determined to pose no hazard to 

aviation safety as required by subpart B of part 17 of this chapter; or 

the antenna or tower structure does not exceed 6.1 meters above ground 

level or above an existing man-made structure (other than an antenna 

structure), if the antenna or tower has not been previously studied by 

the Federal Aviation Administration and cleared by the FCC;

    (iii) The grant of the application(s) does not require a waiver of 

the Commission's rules:

    (iv) The applicant has determined that the facility(ies) will not 

significantly affect the environment as defined in Sec.  1.1307 of this 

chapter;

    (v) The station site does not lie within 56.3 kilometers of any 

international border, within areas identified in Sec. Sec.  1.924(a) 

through (d) of this chapter unless the affected entity consents in 

writing to conditional operation or, if



[[Page 616]]



operated on frequencies in the 17.8-19.7 GHz band, within any of the 

areas identified in Sec.  1.924 of this chapter;

    (vi) If operated on frequencies in the 10.6-10.68 GHz band, the 

station site does not lie within any of the following regions:



----------------------------------------------------------------------------------------------------------------

                                        Dimensions=radius in

           Name of region                    kilometers                           Center-point

----------------------------------------------------------------------------------------------------------------

Kitt Peak, Arizona..................                       60   N31-57-22; W111-36-42

Big Pine, California................                       60   N37-13-54; W118-16-34

Vandenburg AFB, California..........                       75   N34-43-00; W120-34-00

Denver, Colorado....................                      150   N39-43-00; W104-46-00

Washington, DC......................                      150   N38-48-00; W76-52-00

Eglin AFB, Florida..................                       50   N30-29-00; W86-32-00

Mauna Kea, Hawaii...................                       60   N19-48-16; W155-27-29

North Liberty, Iowa.................                       60   N41-46-17; W91-34-26

Maryland Point, Maryland............                       60   N38-22-26; W77-14-00

Hancock, New Hampshire..............                       60   N42-56-01; W71-59-12

Los Alamos, New Mexico..............                       60   N35-46-30; W106-14-42

Pie Town, New Mexico................                       60   N34-18-04; W108-07-07

Socorro, New Mexico.................                      160   N34-04-43; W107-37-04

WSMR, New Mexico....................                       75   N32-23-00; W106-29-00

Minot AFB, North Dakota.............                       80   N48-15-00; W101-17-00

Arecibo, Puerto Rico................                      160   N18-20-37; W66-45-11

Fort Davis, Texas...................                       60   N30-38-06; W103-56-39

St. Croix, Virgin Islands...........                       60   N17-45-31; W64-35-03

Brewster, Washington................                       60   N48-07-53; W119-40-55

Green Bank, West Virginia...........                      160   N38-25-59; W79-50-24



----------------------------------------------------------------------------------------------------------------

Note: Coordinates are referenced to North American Datum 1983 (NAD83).



    (vii) With respect to the 21.8-22.0 GHz and 23.0-23.2 GHz band, the 

filed application(s) does not propose to operate on a frequency pair 

centered on other than 21.825/23.025 GHz, 21.875/23.075 GHz, 21.925/

23.125 GHz or 21.975/23.175 GHz and does not propose to operate with an 

E.I.R.P. greater than 55 dBm. The center frequencies are shifted from 

the center frequencies listed above for certain bandwidths as follows: 

add 0.005 GHz for 20 MHz bandwidth channels, add 0.010 GHz for 30 MHz 

bandwidth channels, and subtract 0.005 GHz for 40 MHz bandwidth 

channels. See specific channel listings in Sec.  101.147(s).

    (viii) The filed application(s) is consistent with the proposal that 

was coordinated pursuant to Sec.  101.103.

    (2) Conditional authority ceases immediately if the application(s) 

is returned by the Commission because it is not acceptable for filing.

    (3) Conditional authorization does not prejudice any action the 

Commission may take on the subject application(s). Conditional authority 

is accepted with the express understanding that such authority may be 

modified or cancelled by the Commission at any time without hearing if, 

in the Commission's discretion, the need for such action arises. An 

applicant operating pursuant to this conditional authority assumes all 

risks associated with such operation, the termination or modification of 

the conditional authority, or the subsequent dismissal or denial of its 

applications(s).



[61 FR 26677, May 28, 1996, as amended at 62 FR 55538, Oct. 27, 1997; 63 

FR 10779, Mar. 5, 1998; 63 FR 68981, Dec. 14, 1998; 65 FR 38327, June 

20, 2000; 68 FR 4955, Jan. 31, 2003; 69 FR 17959, Apr. 6, 2004]



                       Processing of Applications