Sec. 24.103 Construction requirements.
(a) Nationwide narrowband PCS licensees shall construct base
stations that provide coverage to a composite area of 750,000 square
kilometers or serve 37.5 percent of the U.S. population within five
years of initial license grant date; and, shall construct base stations
that provide coverage to a composite area of 1,500,000 square kilometers
or serve 75 percent of the U.S. population within ten years of initial
license grant date. Licensees may, in the alternative, provide
substantial service to the licensed area as provided in paragraph (d) of
this section.
(b) Regional narrowband PCS licensees shall construct base stations
that provide coverage to a composite area of 150,000 square kilometers
or serve 37.5 percent of the population of the service area within five
years of initial license grant date; and, shall construct base stations
that provide coverage to a composite area of 300,000 square kilometers
or serve 75 percent of the service area population within ten years of
initial license grant date. Licensees may, in the alternative, provide
substantial service to the licensed area as provided in paragraph (d) of
this section.
(c) MTA narrowband PCS licensees shall construct base stations that
provide coverage to a composite area of 75,000 square kilometers or 25
percent of the geographic area, or serve 37.5 percent of the population
of the service area within five years of initial license grant date;
and, shall construct base stations that provide coverage to a composite
area of 150,000 square kilometers or 50 percent of the geographic area,
or serve 75 percent of the population of the service area within ten
years of initial license grant date. Licensees may, in the alternative,
provide substantial service to the licensed area as provided in
paragraph (d) of this section.
(d) As an alternative to the requirements of paragraphs (a), (b),
and (c) of this section, narrowband PCS licensees may demonstrate that,
no later than ten years after the initial grant of their license, they
provide substantial service to their licensed area. Licensees choosing
this option must notify the FCC by filing FCC Form 601, no later than 15
days after the end of the five year period following the initial grant
of their license, that they plan to satisfy the alternative requirement
to provide substantial service. ``Substantial service'' is defined as
service that is sound, favorable, and substantially above a level of
mediocre service that would barely warrant renewal.
(e) In demonstrating compliance with the construction requirements
set forth in this section, licensees must base their calculations on
signal field strengths that ensure reliable service for the technology
utilized. Licensees may determine the population of geographic areas
included within their service contours using either the 1990 census or
the 2000 census, but not both.
[[Page 138]]
(1) For the purpose of this section, the service radius of a base
station may be calculated using the following formula:
dkm = 2.53 x hm0.34 x p\0.17\
where dkm is the radial distance in kilometers,
hm is the antenna HAAT of the base station in meters, and
p is the e.r.p. of the base station in watts.
(2) Alternatively, licensees may use any service radius contour
formula developed or generally used by industry, provided that such
formula is based on the technical characteristics of their system.
(f) Upon meeting the five and ten year benchmarks in paragraphs (a),
(b), and (c) of this section, or upon meeting the substantial service
alternative in paragraph (d), licensees shall notify the Commission by
filing FCC Form 601 and including a map and other supporting
documentation that demonstrate the required geographic area coverage,
population coverage, or substantial service to the licensed area. The
notification must be filed with the Commission within 15 days of the
expiration of the relevant period.
(g) If the sale of a license is approved, the new licensee is held
to the original build-out requirement.
(h) Failure by a licensee to meet the above construction
requirements shall result in forfeiture of the license and ineligibility
to regain it.
[59 FR 14118, Mar. 25, 1994, as amended at 65 FR 35852, June 6, 2000]