Sec. 307.7107  Review.



    Upon receipt of the RFC, the contracting officer shall review its 

contents to ensure that all pertinent information has been provided by 

the program office and that it includes an acceptable SOW. If pertinent 

information is missing or the SOW is inadequate, the contracting officer 

shall obtain or clarify the information as soon as possible so that the 

acquisition schedule can be met. If the program office delays furnishing 

the information or clarification, the contracting officer should notify 

the head of the sponsoring program office, in writing, of the possible 

slippage in the acquisition schedule and the need for an expeditious 

remedy. The contracting officer should also notify the chief of the 

contracting office. A program office's or project officer's continued 

failure to adhere to agreed on milestones should also be reported to the 

head of the contracting activity.