[Code of Federal Regulations]

[Title 48, Volume 4]

[Revised as of October 1, 2006]

From the U.S. Government Printing Office via GPO Access

[CITE: 48CFR315.404-4]



[Page 41-48]

 

            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM

 

                  CHAPTER 3--HEALTH AND HUMAN SERVICES

 

PART 315_CONTRACTING BY NEGOTIATION--Table of Contents

 

                     Subpart 315.4_Contract Pricing

 

Sec. 315.404-4  Profit.



    (b) Policy. (1) The structured approach for determining profit or 

fee (hereafter referred to as profit) provides contracting officers with 

a technique that will ensure consideration of the relative value of the 

appropriate profit factors described in paragraph (d) of this section in 

the establishment of a profit objective for the conduct of negotiations. 

The contracting officer's analysis of these profit factors is based on 

information available to him/her prior to negotiations. The information 

is furnished in proposals, audit data, assessment reports, preaward 

surveys and the like. The structured approach also provides a basis for 

documentation of this objective, including an explanation of any 

significant departure from this objective in reaching an agreement. The 

extent of documentation should be directly related to the dollar value 

and complexity of the proposed acquisition. Additionally, the 

negotiation process does not require agreement on either estimated cost 

elements or profit elements. The profit objective is a part of an 

overall negotiation objective which, as a going-in objective, bears a 

distinct relationship to the cost objective and any proposed sharing 

arrangement. Since profit is merely one of several interrelated 

variables, the Government negotiator generally should not complete the 

profit negotiation without simultaneously agreeing on the other 

variables. Specific agreement on the exact weights or values of the 

individual profit factors is not required and should not be attempted.

    (ii) The profit-analysis factors set forth at FAR 15.404-4(d) shall 

be used for establishing profit objectives under the following listed 

circumstances. Generally, it is expected that this method will be 

supported in a manner similar to that used in the structured approach 

(profit factor breakdown and documentation of the profit objective); 

however, factors within FAR 15.404-4(d) considered inapplicable to the 

acquisition will be excluded from the profit objective.

    (A) Contracts not expected to exceed $100,000;

    (B) Architect-engineer contracts;

    (C) Management contracts for operations and/or maintenance of 

Government facilities;

    (D) Construction contracts;

    (E) Contracts primarily requiring delivery of material supplies by 

subcontractors;

    (F) Termination settlements; and

    (G) Cost-plus-award-fee contracts (However, contracting officers may 

find it advantageous to perform a structured profit analysis as an aid 

in arriving at an appropriate fee arrangement). Other exceptions may be 

made in the negotiation of contracts having unusual pricing situations, 

but shall be justified in writing by the contracting officer in 

situations where the structured approach is determined to be unsuitable.

    (c) Contracting officer responsibilities. A profit objective is that 

part of the estimated contract price objective or



[[Page 42]]



value which, in the judgment of the contracting officer, constitutes an 

appropriate amount of profit for the acquisition being considered. This 

objective should realistically reflect the total overall task to be 

performed and the requirements placed on the contractor. Development of 

a profit objective should not begin until a thorough review of proposed 

contract work has been made; a review of all available knowledge 

regarding the contractor pursuant to FAR subpart 9.1, including audit 

data, preaward survey reports and financial statements, as appropriate, 

has been conducted; and an analysis of the contractor's cost estimate 

and comparison with the Government's estimate or projection of cost has 

been made.

    (d) Profit--analysis factors--(1) Common factors. The following 

factors shall be considered in all cases in which profit is to be 

negotiated. The weight ranges listed after each factor shall be used in 

all instances where the structured approach is used.



------------------------------------------------------------------------

             Profit factors                 Weight ranges (in percent)

------------------------------------------------------------------------

Contractor effort:

  Material acquisition.................  1 to 5.

  Direct labor.........................  4 to 15.

  Overhead.............................  4 to 9.

  General management (G&A).............  4 to 8.

  Other costs..........................  1 to 5.

Other factors:

  Cost risk............................  0 to 7.

  Investment...........................  -2 to +2.

  Performance..........................  -1 to +1.

  Socioeconomic programs...............  -.5 to +.5.

  Special situations...................

------------------------------------------------------------------------



    (i) Under the structured approach, the contracting officer shall 

first measure ``Contractor Effort'' by the assignment of a profit 

percentage within the designated weight ranges to each element of 

contract cost recognized by the contracting officer. The amount 

calculated for the cost of money for facilities capital is not to be 

included for the computation of profit as part of the cost base. The 

suggested categories under ``Contractor Effort'' are for reference 

purposes only. Often individual proposals will be in a different format, 

but since these categories are broad and basic, they provide sufficient 

guidance to evaluate all other items of cost.

    (ii) After computing a total dollar profit for ``Contractor 

Effort,'' the contracting officer shall then calculate the specific 

profit dollars assigned for cost risk, investment, performance, 

socioeconomic programs, and special situations. This is accomplished by 

multiplying the total Government Cost Objective, exclusive of any cost 

of money for facilities capital, by the specific weight assigned to the 

elements within the ``Other Factors'' category. Form HHS-674, Structured 

Approach Profit/Fee Objective, should be used, as appropriate, to 

facilitate the calculation of this profit objective. Form HHS-674 is 

illustrated in 353.370-674.

    (iii) In making a judgment of the value of each factor, the 

contracting officer should be governed by the definition, description, 

and purpose of the factors together with considerations for evaluating 

them.

    (iv) The structured approach was designed for arriving at profit 

objectives for other than nonprofit organizations. However, if 

appropriate adjustments are made to reflect differences between profit 

and nonprofit organizations, the structured approach can be used as a 

basis for arriving at profit objectives for nonprofit organizations. 

Therefore, the structured approach, as modified in paragraph 

(d)(1)(iv)(B) of this section, shall be used to establish profit 

objectives for nonprofit organizations.

    (A) For purposes of this section, nonprofit organizations are 

defined as those business entities organized and operated exclusively 

for charitable, scientific, or educational purposes, no part of the net 

earnings of which inure to the benefit of any private shareholder or 

individual, and which are exempt from Federal income taxation under 

Section 501 of the Internal Revenue Code.

    (B) For contracts with nonprofit organizations where profit is 

involved, an adjustment of up to 3 percentage points will be subtracted 

from the total profit objective percentage. In developing this 

adjustment, it will be necessary to consider the following factors;

    (1) Tax position benefits;

    (2) Granting of financing through advance payments; and

    (3) Other pertinent factors which may work to either the advantage 

or



[[Page 43]]



disadvantage of the contractor in its position as a nonprofit 

organization.

    (2) Contractor effort. Contractor effort is a measure of how much 

the contractor is expected to contribute to the overall effort necessary 

to meet the contract performance requirement in an efficient manner. 

This factor, which is apart from the contractor's responsibility for 

contract performance, takes into account what resources are necessary 

and what the contractor must do to accomplish a conversion of ideas and 

material into the final service or product called for in the contract. 

This is a recognition that within a given performance output, or within 

a given sales dollar figure, necessary efforts on the part of individual 

contractors can vary widely in both value and quantity, and that the 

profit objective should reflect the extent and nature of the 

contractor's contribution to total performance. A major consideration, 

particularly in connection with experimental, developmental, or research 

work, is the difficulty or complexity of the work to be performed, and 

the unusual demands of the contract, such as whether the project 

involves a new approach unrelated to existing technology and/or 

equipment or only refinements to these items. The evaluation of this 

factor requires an analysis of the cost content of the proposed contract 

as follows:

    (i) Material acquisition. (Subcontracted items, purchased parts, and 

other material.) Analysis of these cost items shall include an 

evaluation of the managerial and technical effort necessary to obtain 

the required subcontracted items, purchased parts, material or services. 

The contracting officer shall determine whether the contractor will 

obtain the items or services by routine order from readily available 

sources or by detailed subcontracts for which the prime contractor will 

be required to develop complex specifications. Consideration shall also 

be given to the managerial and technical efforts necessary for the prime 

contractor to select subcontractors and to perform subcontract 

administration functions. In application of this criterion, it should be 

recognized that the contribution of the prime contractor to its 

purchasing program may be substantial. Normally, the lowest unadjusted 

weight for direct material is 2 percent. A weighting of less than 2 

percent would be appropriate only in unusual circumstances when there is 

a minimal contribution by the contractor.

    (ii) Direct labor. (Professional, service, manufacturing and other 

labor). Analysis of the various labor categories of the cost content of 

the contract should include evaluation of the comparative quality and 

quantity of professional and semiprofessional talents, manufacturing and 

service skills, and experience to be employed. In evaluating 

professional and semiprofessional labor for the purpose of assigning 

profit dollars, consideration should be given to the amount of notable 

scientific talent or unusual or scarce talent needed in contrast to 

nonprofessional effort. The assessment should consider the contribution 

this talent will provide toward the achievement of contract objectives. 

Since nonprofessional labor is relatively plentiful and rather easily 

obtained by the contractor and is less critical to the successful 

performance of contract objectives, it cannot be weighted nearly as high 

as professional or semiprofessional labor. Service contract labor should 

be evaluated in a like manner by assigning higher weights to engineering 

or professional type skills required for contract performance. 

Similarly, the variety of manufacturing and other categories of labor 

skills required and the contractor's manpower resources for meeting 

these requirements should be considered. For purposes of evaluation, 

categories of labor (i.e., quality control, receiving and inspection, 

etc.) which do not fall within the definition for professional, service 

or manufacturing labor may be categorized as appropriate. However, the 

same evaluation considerations as outlined in this paragraph will be 

applied.

    (iii) Overhead and general management (G&A). (A) Analysis of these 

overhead items of cost should include the evaluation of the makeup of 

these expenses and how much they contribute to contract performance. To 

the extent practicable, analysis should include a determination of the 

amount of labor



[[Page 44]]



within these overhead pools and how this labor should be treated if it 

were considered as direct labor under the contract. The allocable labor 

elements should be given the same profit considerations that they would 

receive if they were treated as direct labor. The other elements of 

these overhead pools should be evaluated to determine whether they are 

routine expenses, such as utilities and maintenance, and hence given 

lesser profit consideration, or whether they are significant 

contributing elements. The composite of the individual determinations in 

relation to the elements of the overhead pools will be the profit 

consideration given the pools as a whole. The procedure for assigning 

relative values to these overhead expenses differs from the method used 

in assigning values of the direct labor. The upper and lower limits 

assignable to the direct labor are absolute. In the case of overhead 

expenses, individual expenses may be assigned values outside the range 

as long as the composite ratio is within the range.

    (B) It is not necessary that the contractor's accounting system 

break down overhead expenses within the classifications of research 

overhead, other overhead pools, and general administrative expenses, 

unless dictated otherwise by Cost Accounting Standards (CAS). The 

contractor whose accounting system reflects only one overhead rate on 

all direct labor need not change its system (if CAS exempt) to 

correspond with these classifications. The contracting officer, in an 

evaluation of such a contractor's overhead rate, could break out the 

applicable sections of the composite rate which could be classified as 

research overhead, other overhead pools, and general and administrative 

expenses, and follow the appropriate evaluation technique.

    (C) Management problems surface in various degrees and the 

management expertise exercised to solve them should be considered as an 

element of profit. For example, a contract for a new program for 

research or an item which is on the cutting edge of the state of the art 

will cause more problems and require more managerial time and abilities 

of a higher order than a follow-on contract. If new contracts create 

more problems and require a higher profit weight, follow-ons should be 

adjusted downward because many of the problems should have been solved. 

In any event, an evaluation should be made of the underlying managerial 

effort involved on a case-by-case basis.

    (D) It may not be necessary for the contracting officer to make a 

separate profit evaluation of overhead expenses in connection with each 

acquisition action for substantially the same project with the same 

contractor. Where an analysis of the profit weight to be assigned to the 

overhead pool has been made, that weight assigned may be used for future 

acquisitions with the same contractor until there is a change in the 

cost composition of the overhead pool or the contract circumstances, or 

the factors discussed in paragraph (d)(2)(iii)(C) of this section are 

involved.

    (iv) Other costs. Analysis of this factor should include all other 

direct costs associated with contractor performance (e.g., travel and 

relocation, direct support, and consultants). Analysis of these items of 

cost should include, the significance of the cost of contract 

performance, nature of the cost, and how much they contribute to 

contract performance. Normally, travel costs require minimal 

administrative effort by the contractor and, therefore, usually receive 

a weight no greater than 1%. Also, the contractor may designate 

individuals as ``consultants'' but in reality these individuals may be 

obtained by the contractor to supplement its workforce in the 

performance of routine duties required by contract. These costs would 

normally receive a minimum weight. However, there will be instances when 

the contractor may be required to locate and obtain the services of 

consultants having expertise in fields such as medicine or human 

services. In these instances, the contractor will be required to expend 

greater managerial and technical effort to obtain these services and, 

consequently, the costs should receive a much greater weight.

    (3) Other factors (i) Contract cost risk. The contract type employed 

basically determines the degree of cost risk assumed by the contractor. 

For example,



[[Page 45]]



where a portion of the risk has been shifted to the Government through 

cost-reimbursement provisions, unusual contingency provisions, or other 

risk-reducing measures, the amount of profit should be less than where 

the contractor assumes all the risk.

    (A) In developing the prenegotiation profit objective, the 

contracting officer will need to consider the type of contract 

anticipated to be negotiated and the contractor risk associated 

therewith when selecting the position in the weight range for profit 

that is appropriate for the risk to be borne by the contractor. This 

factor should be one of the most important in arriving at prenegotiation 

profit objective. Evaluation of this risk requires a determination of 

the degree of cost responsibility the contractor assumes; the 

reliability of the cost estimates in relation to the task assumed; and 

the complexity of the task assumed by the contractor. This factor is 

specifically limited to the risk of contract costs. Thus, risks on the 

part of the contractor such as reputation, losing a commercial market, 

risk of losing potential profits in other fields, or any risk which 

falls on the contracting office, such as the risk of not acquiring a 

satisfactory report, are not within the scope of this factor.

    (B) The first and basic determination of the degree of cost 

responsibility assumed by the contractor is related to the sharing of 

total risk of contract cost by the Government and the contractor through 

the selection of contract type. The extremes are a cost-plus-a-fixed-fee 

contract requiring the contractor to use its best efforts to perform a 

task and a firm fixed-price contract for a service or a complex item. A 

cost-plus-a-fixed-fee contract would reflect a minimum assumption of 

cost responsibility, whereas a firm-fixed-price contract would reflect a 

complete assumption of cost responsibility. Where proper contract 

selection has been made, the regard for risk by contract type would 

usually fall into the following percentage ranges:



------------------------------------------------------------------------

                                                                 Percent

------------------------------------------------------------------------

Cost-reimbursement type contracts.............................       0-3

Fixed-price type contracts....................................       2-7

------------------------------------------------------------------------



    (C) The second determination is that of the reliability of the cost 

estimates. Sound price negotiation requires well-defined contract 

objectives and reliable cost estimates. Prior experience assists the 

contractor in preparing reliable cost estimates on new acquisitions for 

similar related efforts. An excessive cost estimate reduces the 

possibility that the cost of performance will exceed the contract price, 

thereby reducing the contractor's assumption of contract cost risk.

    (D) The third determination is that of the difficulty of the 

contractor's task. The contractor's task can be difficult or easy, 

regardless of the type of contract.

    (E) Contractors are likely to assume greater cost risk only if 

contracting officers objectively analyze the risk incident to proposed 

contracts and are willing to compensate contractors for it. Generally, a 

cost-plus-fixed fee contract will not justify a reward for risk in 

excess of 0.5 percent, nor will a firm fixed-price contract justify a 

reward of less than the minimum in the structured approach. Where proper 

contract-type selection has been made, the reward for risk, by contract 

type, will usually fall into the following percentage ranges:

    (1) Type of contract and percentage ranges for profit objectives 

developed by using the structured approach for research and development 

and manufacturing contracts:



------------------------------------------------------------------------

                                                       Percent

------------------------------------------------------------------------

Cost-Plus-fixed fee.......................  0 to 0.5

Cost-plus-incentive fee:

  With cost incentive only................  1 to 2

  With multiple incentives................  1.5 to 3

Fixed-price-incentive:

  With cost incentive only................  2 to 4

  With multiple incentives................  3 to 5

  Prospective price redetermination.......  3 to 5

  Firm fixed-price........................  5 to 7

------------------------------------------------------------------------



    (2) Type of contract and percentage ranges for profit objectives 

developed by using the structured approach for service contracts:



------------------------------------------------------------------------

                                                       Percent

------------------------------------------------------------------------

Cost-plus-fixed-fee.......................  0 to 0.5

Cost-plus-incentive fee...................  1 to 2

Fixed-price incentive.....................  2 to 3

Firm fixed-price..........................  3 to 4

------------------------------------------------------------------------





[[Page 46]]



    (F) These ranges may not be appropriate for all acquisitions. For 

instance, a fixed-price-incentive contract that is closely priced with a 

low ceiling price and high incentive share may be tantamount to a firm 

fixed-price contract. In this situation, the contracting officer may 

determine that a basis exists for high confidence in the reasonableness 

of the estimate and that little opportunity exists for cost reduction 

without extraordinary efforts. On the other hand, a contract with a high 

ceiling and low incentive formula can be considered to contain cost-plus 

incentive-fee contract features. In this situation, the contracting 

officer may determine that the Government is retaining much of the 

contract cost responsibility and that the risk assumed by the contractor 

is minimal. Similarly, if a cost-plus-incentive-fee contract includes an 

unlimited downward (negative) fee adjustment on cost control, it could 

be comparable to a fixed-price-incentive contract. In such a pricing 

environment, the contracting officer may determine that the Government 

has transferred a greater amount of cost responsibility to the 

contractor than is typical under a normal cost-plus-incentive-fee 

contract.

    (G) The contractor's subcontracting program may have a significant 

impact on the contractor's acceptance or risk under a contract form. It 

could cause risk to increase or decrease in terms of both cost and 

performance. This consideration should be a part of the contracting 

officer's overall evaluation in selecting a factor to apply for cost 

risk. It may be determined, for instance, that the prime contractor has 

effectively transferred real cost risk to a subcontractor and the 

contract cost risk evaluation may, as a result, be below the range which 

would otherwise apply for the contract type being proposed. The contract 

cost risk evaluation should not be lowered, however, merely on the basis 

that a substantial portion of the contract costs represents subcontracts 

without any substantial transfer of contractor's risk.

    (H) In making a contract cost risk evaluation in an acquisition 

action that involves definitization of a letter contract, unpriced 

change orders, and unpriced orders under basic ordering agreements, 

consideration should be given to the effect on total contract cost risk 

as a result of having partial performance before definitization. Under 

some circumstances it may be reasoned that the total amount of cost risk 

has been effectively reduced. Under other circumstances it may be 

apparent that the contractor's cost risk remained substantially 

unchanged. To be equitable, the determination of profit weight for 

application to the total of all recognized costs, both those incurred 

and those yet to be expended, must be made with consideration to all 

attendant circumstances--not just the portion of costs incurred or 

percentage of work completed prior to definitization.

    (I) Time and material and labor hour contracts will be considered to 

be cost-plus-a-fixed-fee contracts for the purpose of establishing 

profit weights unless otherwise exempt under paragraph (b)(1)(ii) of 

this section in the evaluation of the contractor's assumption of 

contract cost risk.

    (ii) Investment. HHS encourages its contractors to perform their 

contracts with the minimum of financial, facilities, or other assistance 

from the Government. As such, it is the purpose of this factor to 

encourage the contractor to acquire and use its own resources to the 

maximum extent possible. The evaluation of this factor should include an 

analysis of the following:

    (A) Facilities. (Including equipment). To evaluate how this factor 

contributes to the profit objective requires knowledge of the level of 

facilities utilization needed for contract performance, the source and 

financing of the required facilities, and the overall cost effectiveness 

of the facilities offered. Contractors who furnish their own facilities 

which significantly contribute to lower total contract costs should be 

provided with additional profit. On the other hand, contractors who rely 

on the Government to provide or finance needed facilities should receive 

a corresponding reduction in profit. Cases between these examples should 

be evaluated on their merits with either positive or negative 

adjustments, as appropriate, in profit being made. However, where a 

highly facilitized contractor is to perform a contract which does not



[[Page 47]]



benefit from this facilitization or where a contractor's use of its 

facilities has a minimum cost impact on the contract, profit need not be 

adjusted. When applicable, the prospective contractor's computation of 

facilities capital cost of money for pricing purposed under CAS 414 can 

help the contracting officer identify the level of facilities investment 

to be employed in contract performance.

    (B) Payments. In analyzing this factor, consideration should be 

given to the frequency of payments by the Government to the contractor. 

The key to this weighting is to give proper consideration to the impact 

the contract will have on the contractor's cash flow. Generally, 

negative consideration should be given for advance payments and payments 

more frequent than monthly with maximum reduction being given as the 

contractor's working capital approaches zero. Positive consideration 

should be given for payments less frequent than monthly with additional 

consideration given for a capital turn-over rate on the contract which 

is less than the contractor's or the industry's normal capital turn-over 

rate.

    (iii) Performance. (Cost-control and other past accomplishments.) 

The contractor's past performance should be evaluated in such areas as 

quality of service or product, meeting performance schedules, efficiency 

in cost control (including need for and reasonableness of cost 

incurred), accuracy and reliability of previous cost estimates, degree 

of cooperation by the contractor (both business and technical), timely 

processing of changes and compliance with other contractual provisions, 

and management of subcontract programs. Where a contractor has 

consistently achieved excellent results in these areas in comparison 

with other contractors in similar circumstances, this performance merits 

a proportionately greater opportunity for profit. Conversely, a poor 

record in this regard should be reflected in determining what 

constitutes a fair and reasonable profit.

    (iv) Federal socioeconomic programs. This factor, which may apply to 

special circumstances or particular acquisitions, relates to the extent 

of a contractor's successful participation in Government sponsored 

programs such as small business, small disadvantaged business, women-

owned small business, and energy conservation efforts. The contractor's 

policies and procedures which energetically support Government 

socioeconomic programs and achieve successful results should be given 

positive considerations. Conversely, failure or unwillingness on the 

part of the contractor to support Government socioeconomic programs 

should be viewed as evidence of poor performance for the purpose of 

establishing a profit objective.

    (v) Special situations (A) Inventive and developmental 

contributions. The extent and nature of contractor-initiated and 

financed independent development should be considered in developing the 

profit objective, provided that the contracting officer has made a 

determination that the effort will benefit the contract. The importance 

of the development in furthering health and human services purposes, the 

demonstrable initiative in determining the need and application of the 

development, the extent of the contractor's cost risk, and whether the 

development cost was recovered directly or indirectly from Government 

sources should be weighed.

    (B) Unusual pricing agreements. Occasionally, unusual contract 

pricing arrangements are made with the contractor wherein it agrees to 

cost ceilings, e.g., a ceiling on overhead rates for conditions other 

than those discussed at FAR 42.707. In these circumstances, the 

contractor should receive favorable consideration in developing the 

profit objective.

    (C) Negative factors. Special situations need not be limited to 

those which only increase profit levels. A negative consideration may be 

appropriate when the contractor is expected to obtain spin-off-benefits 

as a direct result of the contract (e.g., products or services with 

commercial application).

    (4) Facilities capital cost of money. When facilities capital cost 

of money (cost of capital committed to facilities) is included as an 

item of cost in the contractor's proposal, a reduction in the profit 

objective shall be made in an



[[Page 48]]



amount equal to the amount of facilities capital cost of money allowed 

in accordance with the Facilities Capital Cost-of Money Cost Principal. 

If the contractor does not propose this cost, a provision must be 

inserted in the contract that facilities capital cost of money is not an 

allowable cost.