[Code of Federal Regulations] [Title 48, Volume 4] [Revised as of October 1, 2006] From the U.S. Government Printing Office via GPO Access [CITE: 48CFR332.703-1] [Page 60] TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM CHAPTER 3--HEALTH AND HUMAN SERVICES PART 332_CONTRACT FINANCING--Table of Contents Subpart 332.7_Contract Funding Sec. 332.703-1 General. (b) The following general guidelines are applicable to incrementally funded contracts: (1) The estimated total cost of the project (all planned phases or increments) is to be taken into consideration when determining the requirements which must be met before entering into the contract; i.e., justification for noncompetitive acquisition, approval or award, etc. (2) The RFP and resultant contract are to include a statement of work which describes the total project covering the proposed multiple year period of performance and indicating timetables consistent with planned phases or increments and corresponding allotments of funds. (3) Offerors will be expected to respond to RFPs with technical and cost proposals for the entire project indicating distinct break-outs of the planned phases or increments, and the multiple year period of performance. (4) Negotiations will be conducted based upon the total project, including all planned phases or increments, and the multiple year period of performance. (5) Sufficient funds must be obligated under the basic contract to cover no less than the first year of performance, unless the contracting officer determines it is advantageous to the Government to fund the contract for a lesser period. In that event, the contracting officer shall ensure that the obligated funds are sufficient to cover a complete phase or increment of performance representing a material and measurable part of the total project, and the contract period shall be reduced accordingly. (6) Because of the magnitude of the scope of work and multiple year period of performance under an incrementally funded contract, there is a critical need for careful program planning. Program planning must provide for appropriate surveillance of the contractor's performance and adequate controls to ensure that projected funding will not impinge on the program office's ability to support, within anticipated appropriations, other equally important contract or grant programs. (7) An incrementally funded contract must contain precise requirements for progress reports to enable the project officer to effectively monitor the contract. The project officer should be required to prepare periodic performance evaluation reports to facilitate the program office's ultimate decision to allot additional funds under the contract.