Sec. 752.7009  Marking.



    The following clause is for use in all USAID contracts performed in 

whole or in part overseas.



                           Marking (JAN 1993)



    (a) It is USAID policy that USAID-financed commodities and shipping 

containers, and project construction sites and other project locations 

be suitably marked with the USAID emblem. Shipping containers are also 

to be marked with the last five digits of the USAID financing document 

number. As a general rule, marking is not required for raw materials 

shipped in bulk (such as coal, grain, etc.), or for semifinished 

products which are not packaged.

    (b) Specific guidance on marking requirements should be obtained 

prior to procurement of commodities to be shipped, and as early as 

possible for project construction sites and other project locations. 

This guidance will be provided through the cognizant technical office 

indicated on the cover page of this contract, or by the Mission Director 

in the Cooperating Country to which commodities are being shipped, or in 

which the project site is located.

    (c) Authority to waive marking requirements is vested with the 

Regional Assistant Administrators, and with Mission Directors.

    (d) A copy of any specific marking instructions or waivers from 

marking requirements is to be sent to the Contracting Officer; the



[[Page 73]]



original should be retained by the Contractor.



[49 FR 13259, Apr. 3, 1984, as amended at 58 FR 8703, Feb. 17, 1993]