Sec.  179.5  Certificate of construction.

    (a) Before a tank car is placed in service, the party assembling the 
completed car shall furnish a Certificate of Construction, Form AAR 4-2 
to the owner and the Executive Director--Tank Car Safety, AAR, 
certifying that the tank, equipment, and car fully conforms to all 
requirements of the specification.
    (b) When cars or tanks are covered in one application and are 
identical in all details are built in series, one certificate will 
suffice for each series when submitted to the Executive Director--Tank 
Car Safety, AAR.
    (c) If the owner elects to furnish service equipment, the owner 
shall furnish the Executive Director--Tank Car Safety, AAR, a report in 
prescribed form, certifying that the service equipment complies with all 
the requirements of the specifications.
    (d) When cars or tanks which are covered on one application and are 
identical in all details are built in series, one certificate shall 
suffice for each series when submitted to the Executive Director--Tank 
Car Safety, AAR. One copy of the Certificate of Construction must be 
furnished to the Executive Director--Tank Car Safety, AAR for each car 
number of consecutively numbered

[[Page 1062]]

group or groups covered by the original application.

[Amdt. 179-10, 36 FR 21344, Nov. 6, 1971, as amended at 63 FR 52850, 
Oct. 1, 1998; 68 FR 48571, Aug. 14, 2003]