Sec.  633.27  Implementation of a project management plan.

    (a) Upon approval of a project management plan by the Administrator 
the recipient shall begin implementing the plan.
    (b) If a recipient must modify an approved project management plan, 
the recipient shall submit the proposed changes to the Administrator 
along with an explanation of the need for the changes.
    (c) A recipient shall submit periodic updates of the project 
management plan to the Administrator. Such updates shall include, but 
not be limited to:
    (1) Project budget;
    (2) Project schedule;
    (3) Financing, both capital and operating;
    (4) Ridership estimates, including operating plan; and
    (5) Where applicable, the status of local efforts to enhance 
ridership when estimates are contingent, in part, upon the success of 
such efforts.
    (d) A recipient shall submit current data on a major capital 
project's budget and schedule to the Administrator on a monthly basis.