Sec.  226.62  Enforcement.

    (a) Remedies for noncompliance. If a recipient materially fails to 
comply with the terms and conditions of an award, whether stated in a 
Federal statute, regulation, assurance, application, or notice of award, 
USAID may, in addition to imposing any of the special conditions 
outlined in Sec.  226.14, take one or more of the following actions, as 
appropriate in the circumstances.
    (1) Temporarily withhold cash payments pending correction of the 
deficiency by the recipient or more severe enforcement action by USAID.
    (2) Disallow (that is, deny both use of funds and any applicable 
matching credit for) all or part of the cost of the activity or action 
not in compliance.
    (3) Wholly or partly suspend or terminate the current award.
    (4) Withhold further awards for the project or program.
    (5) Take other remedies that may be legally available.
    (b) Hearings and appeals. The recipient may appeal, in accordance 
with Subpart F, any action taken by USAID on which a dispute exists and 
a decision by the Agreement Officer has been obtained. There is no right 
to a hearing on such an appeal.
    (c) Effects of suspension and termination. Costs of a recipient 
resulting from obligations incurred by the recipient during a suspension 
or after termination of an award are not allowable unless USAID 
expressly authorizes them in the notice of suspension or termination or 
subsequently. Other recipient costs during suspension or after 
termination which are necessary and not reasonably avoidable are 
allowable if:
    (1) The costs result from obligations which were properly incurred 
by the recipient before the effective date of suspension or termination, 
are not in anticipation of it, and in the case of a termination, are 
noncancellable, and
    (2) The costs would be allowable if the award were not suspended or 
expired normally at the end of the funding period in which the 
termination takes effect.
    (d) Relationship to debarment and suspension. The enforcement 
remedies identified in this section, including suspension and 
termination, do not preclude a recipient from being subject to debarment 
and suspension under E.O.s 12549 and 12689 and USAID's implementing 
regulations (see 22 CFR Part 208).