Sec.  140.609  Progress and final vouchers.

    (a) Progress vouchers may be submitted for the Federal share of 
bonds retired or about to be retired, including eligible interest on 
Interstate Bond Issue Projects, the proceeds of which have actually been 
expended for the construction of the project.
    (b) Upon completion of a bond issue project, a final voucher shall 
be submitted by the SHA. After final review, the SHA will be advised as 
to the total cost and Federal fund participation for the project.