[Code of Federal Regulations]
[Title 24, Volume 4]
[Revised as of April 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 24CFR941.404]

[Page 381]
 
                 TITLE 24--HOUSING AND URBAN DEVELOPMENT
 
CHAPTER IX--OFFICE OF ASSISTANT SECRETARY FOR PUBLIC AND INDIAN HOUSING, 
 
PART 941_PUBLIC HOUSING DEVELOPMENT--Table of Contents
 
                      Subpart D_Project Development
 
Sec.  941.404  Completion of development.

    (a) When all development has been completed and paid for, but not 
later than 12 months after the end of the initial operating period 
unless a longer period is approved by HUD, the PHA shall submit a 
statement of the actual development cost. For this purpose, the initial 
operating period with respect to each project is the period commencing 
with the date of initiation of the project and ending with the earliest 
of the following three dates: the end of the calendar quarter in which 
ninety-five percent of the dwelling units in the project are occupied; 
the end of the calendar quarter that is six, seven, or eight months 
after the date of full availability of the project; or the end of the 
calendar quarter next preceding the date of physical completion of the 
project.
    (b) HUD shall review the statement and establish the actual 
development cost of the project, which becomes the maximum total 
development cost for purposes of the ACC.

    Effective Date Note: At 61 FR 38021, July 22, 1996, Sec.  941.404 
was revised. This section contains information collection and 
recordkeeping requirements and will not become effective until approval 
has been given by the Office of Management and Budget.