Sec.  983.153  When Agreement is executed.

    (a) Prohibition of excess subsidy. The PHA may not enter the 
Agreement with the owner until the subsidy layering review is completed 
(see Sec.  983.55).
    (b) Environmental approval. The PHA may not enter the Agreement with 
the owner until the environmental review is completed and the PHA has 
received the environmental approval (see Sec.  983.58).
    (c) Prompt execution of Agreement. The Agreement must be executed 
promptly after PHA notice of proposal selection to the selected owner.