Sec.  983.155  Completion of housing.

    (a) Completion deadline. The owner must develop and complete the 
housing in accordance with the Agreement. The Agreement must specify the 
deadlines for completion of the housing and for submission by the owner 
of the required evidence of completion.
    (b) Required evidence of completion--(1) Minimum submission. At a 
minimum, the owner must submit the following evidence of completion to 
the PHA in the form and manner required by the PHA:
    (i) Owner certification that the work has been completed in 
accordance with the HQS and all requirements of the Agreement; and
    (ii) Owner certification that the owner has complied with labor 
standards and equal opportunity requirements in development of the 
housing.
    (2) Additional documentation. At the discretion of the PHA, the 
Agreement may specify additional documentation that must be submitted by 
the owner as evidence of housing completion. For example, such 
documentation may include:
    (i) A certificate of occupancy or other evidence that the units 
comply with local requirements (such as code and zoning requirements); 
and
    (ii) An architect's certification that the housing complies with:
    (A) HUD housing quality standards;
    (B) State, local, or other building codes;
    (C) Zoning;
    (D) The rehabilitation work write-up (for rehabilitated housing) or 
the work description (for newly constructed housing); or
    (E) Any additional design or quality requirements pursuant to the 
Agreement.