Sec.  983.156  PHA acceptance of completed units.

    (a) PHA determination of completion. When the PHA has received owner 
notice that the housing is completed:
    (1) The PHA must inspect to determine if the housing has been 
completed in accordance with the Agreement, including compliance with 
the HQS and any additional requirement imposed by the PHA under the 
Agreement.
    (2) The PHA must determine if the owner has submitted all required 
evidence of completion.
    (3) If the work has not been completed in accordance with the 
Agreement, the PHA must not enter into the HAP contract.
    (b) Execution of HAP contract. If the PHA determines that the 
housing has been completed in accordance with the Agreement and that the 
owner has submitted all required evidence of completion, the PHA must 
submit the HAP contract for execution by the owner and must then execute 
the HAP contract.