Sec.  302.8  Pre-approval Investment Assistance costs.

    Project activities carried out before approval of Investment 
Assistance shall be carried out at the sole risk of the Eligible 
Applicant. Such activity is subject to the rejection of the application, 
the disallowance of costs, or other adverse consequences as a result of 
non-compliance with EDA or Federal requirements, including but not 
limited to procurement requirements, civil rights requirements, Federal 
labor standards, or Federal environmental, historic preservation and 
related requirements.