Sec.  305.11  Contract awards; early construction start.

    EDA must determine that the award of all contracts necessary for 
design and construction of the Project facilities is in compliance with 
the terms and conditions of the Investment award in order for the costs 
to be eligible for EDA reimbursement. Pending this determination, the 
Recipient may issue a notice permitting construction under the contract 
to commence. If construction commences prior to EDA's determination, the 
Recipient proceeds at its own risk until EDA review and concurrence. The 
EDA regional office will advise the Recipient of the requirements 
necessary to obtain EDA's determination.