    (a) Remedies for noncompliance. If a grantee or subgrantee 
materially fails to comply with any term of an award, whether stated in 
a Federal statute or regulation, an assurance, in a State plan or 
application, a notice of award, or elsewhere, the award agency may take 
one or more of the following actions, as appropriate in the 
circumstances:
    (1) Temporarily withhold cash payments pending correction of the 
deficiency by the grantee or subgrantee or more severe enforcement 
action by the awarding agency.
    (2) Disallow (that is, deny both use of funds and matching credit 
for) all or part of the cost of the activity or action not in 
compliance,
    (3) Wholly or partly suspend or terminate the current award for the 
grantee's or subgrantee's program,
    (4) Withhold further awards for the program, or
    (5) Take other remedies that may be legally available.
    (b) Hearings, appeals. In taking an enforcement action, the awarding 
agency will provide the grantee or subgrantee an opportunity for such 
hearing, appeal, or other administrative proceeding to which the grantee 
or subgrantee is entitled under any statute or regulation applicable to 
the action involved.
    (c) Effects of suspension and termination. Costs of grantee or 
subgrantee resulting from obligations incurred by the grantee or 
subgrantee during a suspension or after termination of an

[[Page 461]]

award are not allowable unless the awarding agency expressly authorizes 
them in the notice of suspension or termination or subsequently. Other 
grantee or subgrantee costs during suspension or after termination which 
are necessary and not reasonably avoidable are allowable if:
    (1) The costs result from obligations which were properly incurred 
by the grantee or subgrantee before the effective date of suspension or 
termination, are not in anticipation of it, and, in the case of a 
termination, are noncancellable, and,
    (2) The costs would be allowable if the award were not suspended or 
expired normally at the end of the funding period which the termination 
takes effect.
    (d) Relationship to debarment and suspension. The enforcement 
remedies identified in this section, including suspension and 
termination, do not preclude grantee or subgrantee from being subject to 
``Debarment and Suspension'' under E.O. 12549 (see Sec.  1273.35).