Sec.  1424.10  Succession and control of facilities and production.

    A person who obtains a facility that is under contract under this 
part may request permission to succeed to the program agreement and CCC 
may grant such request if it is determined that permitting such 
succession would serve the purposes of the program. If appropriate, CCC 
may require the consent of the original party to such succession. Also, 
CCC may terminate a contract and demand full refund of payments

[[Page 473]]

made if a contracting party loses control of a facility whose increased 
production is the basis of a program payment or otherwise fails to 
retain the ability to assure that all program obligations and 
requirements will be met.