Sec.  203.47  Modifications to non-Federal flood control works.

    Modifications necessary to preserve the structural integrity of 
existing non-Federal projects may be constructed at additional Federal 
and non-Federal expense in conjunction with approved rehabilitation 
work. The additional Federal cost will be limited to not more than one-
third of the estimated Federal construction cost of rehabilitation to 
preflood level of protection, or $100,000, whichever is less. The 
modification work must be economically justified. Non-Federal interests 
are required to contribute a minimum of 25% of the total construction 
costs of the modification, LERRD's, and any additional funds necessary 
to support the remaining cost of the modification beyond what the Corps 
can provide. Engineering and design costs will be at Corps cost.
    (a) Cash contributions. Non-Federal contributions will be only in 
cash. In-kind services are not permitted for modification work.
    (b) Protection of additional areas. Modifications designed to 
provide protection to additional area are not authorized.