[Code of Federal Regulations]
[Title 33, Volume 3]
[Revised as of July 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 33CFR222.6]

[Page 257-311]
 
                TITLE 33--NAVIGATION AND NAVIGABLE WATERS
 
 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 
                                 DEFENSE
 
PART 222_ENGINEERING AND DESIGN--Table of Contents
 
Sec.  222.6  National Program for Inspection of Non-Federal Dams.

    (a) Purpose. This regulation states objectives, assigns 
responsibilities and prescribes procedures for implementation of a 
National Program for Inspection of Non-Federal Dams.
    (b) Applicability. This regulation is applicable to all Divisions 
and Districts having Civil Works functions.
    (c) References. (1) The National Dam Inspection Act, Pub. L. 92-367, 
8 August 1972.
    (2) Freedom of Information Act, Pub. L. 87-487, 4 July 1967.
    (3) ER 500-1-1.
    (d) Authority. The National Dam Inspection Act, Public Law 92-367, 8 
August 1972 authorizes the Secretary of the Army, acting through the 
Chief of Engineers, to carry out a national program of inspection of 
non-Federal dams for the purpose of protecting human life and property.
    (e) Scope. The program provides for:
    (1) An update of the National Inventory of Dams.
    (2) Inspection of the following non-Federal dams (the indicated 
hazard potential categories are based upon the location of the dams 
relative to developed areas):
    (i) Dams which are in the high hazard potential category (located on 
Federal and non-Federal lands).
    (ii) Dams in the significant hazard potential category believed by 
the State to represent an immediate danger to the public safety due to 
the actual condition of the dam.
    (iii) Dams in the significant hazard potential category located on 
Federal lands.
    (iv) Specifically excluded from the national inspection program are:
    (A) Dams under the jurisdiction of the Bureau of Reclamation, the 
Tennessee Valley Authority, the International Boundary and Water 
Commission and the Corps of Engineers and
    (B) Dams which have been constructed pursuant to licenses issued 
under the authority of the Federal Power Act, and
    (C) Dams which have been inspected within the 12-month period 
immediately prior to the enactment of this act by a State agency and 
which the Governor of such State requests be excluded from inspection.
    (f) Objectives. The objectives of the program are:
    (1) To update the National Inventory of Dams by 30 September 1980.
    (2) To perform the initial technical inspection and evaluation of 
the non-Federal dams described in paragraph 222.8(e) of this section to 
identify conditions which constitute a danger to human life or property 
as a means of expediting the correction of hazardous conditions by non-
Federal interests. The inspection and evaluation is to be completed by 
30 September 1981.
    (3) To obtain additional information and experience that may be 
useful in determining if further Federal actions are necessary to assure 
national dam safety.
    (4) Encourage the States to establish effective dam safety programs 
for non-Federal dams by 30 September 1981 and assist the States in the 
development of the technical capability to carry out such a program.
    (g) Program execution--(1) Responsibilities. (i) The owner has the 
basic legal responsibility for potential hazards created by their 
dam(s). Phase II studies, as described in Chapter 4, Appendix D, and 
remedial actions are the owner's responsibility.
    (ii) The State has the basic responsibility for the protection of 
the life and property of its citizens. Once a dam has been determined to 
be unsafe, it is the State's responsibility to see that timely remedial 
actions are taken.
    (iii) The Corps of Engineers has the responsibility for executing 
the national program. The Federal program for inspection of dams does 
not modify the basic responsibilities of the States or dam owners. The 
Engineering Division of the Civil Works Directorate is responsible for 
overall program goals, guidance, technical criteria for inspections and 
inventory and headquarters level coordination with other agencies. The 
Water Resources Support Center (WRSC) located at Kingman Building, Fort 
Belvoir, Virginia 22060 is responsible for:
    (A) Program Coordination of both the inventory and inspection 
programs.

[[Page 258]]

    (B) Developing and defining functional tasks to achieve program 
objectives.
    (C) Determining resource requirements. (Budget)
    (D) Compiling and disseminating progress reports.
    (E) Monitoring and evaluating program progress and recommending 
corrective measures as needed.
    (F) Collecting and evaluating data pertaining to inspection reports, 
dam owners' responses to inspection report recommendations, attitudes 
and capabilities of State officials, State dam safety legislation, 
Architect-Engineer performance, etc., for defining a comprehensive 
national dam safety program.
    (G) Responding to Congressional, media, scientific and engineering 
organization and general public inquiries.

Division and District offices are responsible for executing the program 
at the State level. Assignment of Division reponsibilities for States is 
shown in Appendix A.
    (2) State participation. Where State capability exists, every effort 
should be made to encourage the State to execute the inspection program 
either with State personnel or with Architect-Engineer (A-E) contracts 
under State supervision. If the State does not have the capability to 
carry out the inspection program, the program will be managed by the 
Corps of Engineers utilizing Corps employees or contracts with A-E firm.
    (h) Update of National Inventory of Dams. (RCS-DAEN-CWE-17/OMB No. 
49-RO421)
    (1) The National Inventory of Dams should be updated and verified to 
include all Federal and non-Federal dams covered by the Act. Those dams 
are defined as all artificial barriers together with appurtenant works 
which impound or divert water and which: (1) Are twenty-five feet or 
more in height or (2) have an impounding capacity of fifty acre-feet or 
more. Barriers which are six feet or less in height, regardless of 
storage capacity or barriers which have a storage capacity at maximum 
water storage elevation of fifteen acre-feet or less regardless of 
height are not included.
    (2) Inventory data for all dams shall be provided in accordance with 
Appendix B.
    (3) The hazard potential classification shall be in accordance with 
paragraph 2.1.2 Hazard Potential of the Recommended Guideline for Safety 
Inspection of Dams (Appendix D to this section).

                                    Table 2--Hazard Potential Classification
----------------------------------------------------------------------------------------------------------------
                Category                          Urban development                      Economic loss
----------------------------------------------------------------------------------------------------------------
Low....................................  No permanent structure for human     Minimal (Undeveloped to occasional
                                          habitation.                          structures or agriculture).
Significant............................  No urban development and no more     Appreciable (Notable agriculture,
                                          than a small number of habitable     industry or structures).
                                          structures.
High...................................  Urban development with more than a   Excessive (Extensive community,
                                          small number of habitable            industry or agriculture).
                                          structures.
----------------------------------------------------------------------------------------------------------------

    (4) As in the original development of the inventory, the States 
should be encouraged to participate in the work of completing, verifying 
and updating the inventory. Also, when available, personnel of other 
appropriate Federal agencies should be utilized for the inventory work 
on a reimbursable basis. Work in any State may be accomplished:
    (i) Under State supervision utilizing State personnel or Architect-
Engineers contracts.
    (ii) Under Corps supervision utilizing Corps employees, employees of 
other Federal agencies or Architect-Engineer contracts.
    (5) A minimum staff should be assigned in Districts and Divisions to 
administer and monitor the inventory activities. Generally, the work 
should be accomplished by architect-engineers or other Federal agency 
personnel under State or Corps supervision. Corps personnel should 
participate in the inventory only to the extent needed to assure that 
accurate data are collected.

[[Page 259]]

    (6) The National Inventory of Dams computerized data base in stored 
on the Boeing Computer Services (BCS) EKS computer system in Seattle, 
Washington. The data base uses Data Base Management System 2000 and is 
accessible for query by all Corps offices.
    (7) Appendix B indicates details on accessing and updating inventory 
data.
    (8) Appendix I describes the procedure for using NASA Land Satellite 
(LANDSAT) Multispectral Scanner data along with NASA's Surface Water 
Detection and Mapping (DAM) computer program to assist in updating and 
verifying and National Inventory of Dams.
    (9) All inventory data for dams will be completed and verified 
utilizing all available sources of information (including LANDSAT 
overlay maps) and will include site visitation if required. It is the 
responsibility of the District Engineer to insure that the inventory of 
each State within his area of responsibility is accurate and contains 
the information required by the General Instructions for completing the 
forms for each Federal and non-Federal dam.
    (i) [Reserved]
    (j) Inspection Program. (RCS-DAEN-CWE-17 and OMB No. 49-RO421)
    (1) Scheduling of inspections. The Governor of each State or his 
designee will continue to be involved in the selection and scheduling of 
the dams to be inspected. Priority will be given to inspection of those 
dams considered to offer the greatest potential threat to public safety.
    (i) No inspection of a dam should be initiated until the hazard 
potential classification of the dam has been verified to the 
satisfaction of the Corps. Dams in the significant hazard category 
should be inspected only if requested by the State and only then if the 
State can provide information to show that the dam has deficiencies that 
pose an immediate danger to the public safety. Guidance for the 
selection of significant category non-Federal dams on Federal lands will 
be given in the near future.
    (ii) Selection for inspection of non-Federal dams located on Federal 
lands or non-Federal dams designed and constructed under the 
jurisdiction of some Federal agency, should be coordinated with the 
responsible Federal agency. The appropriate State or regional 
representative of the Federal agency also should be contacted to obtain 
all available data on the dam. Representatives of the agency may 
participate in the inspection if they desire and should be given the 
opportunity to review and comment on the findings and recommendations in 
the inspection report prior to submission to the Governor and the dam 
owner. Examples of such dams are: non-Federal dams built on lands 
managed by National Forest Service, Bureau of Land Management, Fish and 
Wildlife Service, etc.; non-Federal dams designed and constructed by the 
Soil Conservation Service of the U.S. Department of Agriculture; high 
hazard mine tailings and coal mine waste dams under the jurisdiction of 
the Mine Safety and Health Administration, Department of Labor.
    (iii) Indian-owned dams on trust lands are considered to be non-
Federal dams. All dams in the high hazard potential category will be 
inspected. Privately-owned dams located on Indian lands are to be 
included in the program, however BIA-owned dams on Indian lands are 
Federal dams and are exempt.
    (2) Procedures. The Division Engineer is responsible for the quality 
of inspections and reports prepared by the District Engineer. Close 
liaison between the District Engineer and the State agency or A-E firm 
responsible for the inspections will be required in order to obtain a 
dependable result. To avoid undesirable delays in the evaluation of 
safety of individual dams, contracts with A-E's or agreements with 
States which are managing the program will provide that reports be 
completed and furnished to the District Engineer within a specified time 
after completion of the on-site inspection of the dam.
    (i) Inspection guidelines. The inspection should be conducted in 
accordance with the Recommended Guidelines for Safety Inspection of Dams 
(Appendix D to this section). Expanded Guidance for Hydrologic and 
Hydraulic Assessment of Dams is provided in Appendix C. The criteria in 
the recommended guidelines are screening criteria to be used only

[[Page 260]]

for initial determinations of the adequacy of the dam. Conditions found 
during the investigation which do not meet the guideline recommendations 
should be assessed as to their importance from the standpoint of the 
degree of risk involved.
    (ii) Coordinators. Experience has shown that coordination and 
communications among technical disciplines, Public Affairs Office, 
emergency officials, training officers, operations personnel, State 
representatives and A-E firms has been best in those districts where one 
person was delegated the responsiblity for coordinating the actions of 
all involved elements. Each district should evaluate its overall 
coordination procedures to insure that all involved elements have the 
best possible access to necessary data.
    (iii) Field investigations should be carried out in a systematic 
manner. A detailed checklist or inspection form should be developed and 
used for each dam inspection and appended to the inspection report. The 
size of the field inspection team should be as small as practicable, 
generally consisting of only one representative of each required 
discipline in order to control the costs of the inspection without 
sacrificing the quality of the inspection. The inspection team for the 
smaller less complex dams should be limited to two or three 
representatives from appropriate technical areas with additional 
specialists used only as special conditions warrant. The larger more 
complex projects may require inspection teams of three or four 
specialists. Performance of overly detailed and precise surveys and 
mapping should be avoided. Necessary measurement of spillway, dam 
slopes, etc. can generally be made with measuring tapes and hand levels.
    (iv) Additional engineering studies. Dam inspections should be 
limited to Phase I investigations as outlined in Chapter 3 of Appendix 
D. However, if recommended by the investigating engineer and approved by 
the District Engineer, some additional inexpensive investigations may be 
performed when a reasonable judgment on the safety of the dam cannot be 
made without additional investigation. Any further Phase II 
investigation needed to prove or disprove the findings of the District 
Engineer or to devise remedial measures to correct deficiencies are the 
responsibility of the owner and will not be undertaken by the Corps of 
Engineers.
    (v) Assessment of the investigation. (A) The findings of the visual 
inspection and review of existing engineering data for a dam shall be 
assessed to determine its general condition. Dams assessed to be in 
generally good condition should be so described in the inspection 
report. Deficiencies found in a dam should be described and assessed as 
to the degree of risk they present. The degree of risk should consider 
only loss of life and/or property damage resulting from flooding due to 
dam failure. Loss of project benefits i.e., municipal water supply, 
etc., should not be considered. If deficiencies are assessed to be of 
such a nature that, if not corrected, they could result in the failure 
of the dam with subsequent loss of life and/or substantial property 
damage, the dam should be assessed as ``Unsafe.'' If the probable 
failure of an ``Unsafe'' dam is judged to be imminent and immediate 
action is required to reduce or eliminate the hazard, the ``unsafe'' 
condition of the dam should be considered an ``emergency.'' If the 
probable failure is judged not to be imminent, the ``unsafe'' condition 
should be considered a ``non-emergency.''
    (B) Adequacy of spillway. The ``Recommended Guidelines for Safety 
Inspection of Dams,'' Appendix D, provide current, acceptable inspection 
standards for spillway capacity. Any spillway capacity that does not 
meet the criteria in the ``Guidelines'' is considered inadequate. When a 
spillway's capacity is so deficient that it is seriously inadequate, the 
project must be considered unsafe. If all of the following conditions 
prevail, the Governor of the State shall be informed that such project 
is unsafe:
    (1) There is high hazard to loss of life from large flows downstream 
of the dam.
    (2) Dam failure resulting from overtopping would significantly 
increase the hazard to loss of life downstream from the dam over that 
which would exist just before overtopping failure.

[[Page 261]]

    (3) The spillway is not capable of passing one-half of the probable 
maximum flood without overtopping the dam and causing failure.

Classification of dams with seriously inadequate spillways as ``unsafe, 
non-emergency'' is generally a proper designation of the urgency of the 
unsafe condition. However, there may be cases where the spillway 
capacity is unusually small and the consequences of dam overtopping and 
failure would be catastrophic. In such cases, the unsafe dam should be 
classified as an emergency situation.
    (vi) All inspection reports will receive one level of independent 
review by the Corps. If the reports are prepared by the Corps, the 
independent review may be performed internally within the district 
office. However, in cases which involve significant economic, social or 
political impacts and technical uncertainties in evaluating the dams, 
advice may be obtained from the staffs of the Division Engineer and the 
Office, Chief of Engineers.
    (3) Reports--(i) Preparation. A written report on the condition of 
each dam should be prepared as soon as possible after the completion of 
the field inspection and assessment. A suggested report format is 
attached as Appendix E. It is important that the inspection report be 
completed in a timely manner. For inspections being done by Corps 
employees, it is suggested that once an inspection team has been 
assigned to a dam inspection it be allowed to complete the inspection 
and report without interruption by other work.
    (ii) Review and approval. The coordinating engineer should determine 
which disciplines should review the report and establish a procedure to 
accomplish the review in a timely manner. A review panel, made up of the 
appropriate Division and Branch Chiefs has worked well in some 
districts. Use of a review panel should be seriously considered by all 
districts. All inspection reports shall be approved by the District 
Engineer who will maintain a complete file of final approved reports. 
Any State or Federal agency having jurisdiction over the dam or the land 
on which the dam is built should be given the opportunity to review and 
comment on the report prior to submission to the Governor or dam owner. 
The District Engineer will transmit final approved reports to the 
Governor of the State and the dam owner (or the Governor only, when 
requested in writing by State officials). If the report is initially 
furnished to the Governor only, a period of up to ten days may be 
allowed before the report is furnished to the dam owner. If the Governor 
or the owner indicates additional technical information is available 
that might affect the assessment of the dam's condition, the District 
Engineer will furnish the proposed final report to the Governor and the 
owner and establish a definite time period for comments to be furnished 
to the District Engineer prior to report approval.
    (iii) In general the Governor will be responsible for public release 
of an inspection report and for initiating any public Statements. 
However, an approved report must be treated as any other document 
subject to release upon request under the Freedom of Information Act. 
The letters of transmittal to the Governor and owner should indicate 
that under the provisions of the Freedom of Information Act, the 
documents will be subject to release upon request after receipt by the 
Governor. Proposed final reports will be considered as internal working 
papers not subject to release under the Freedom of Information Act. 
Corps personnel, A-E contractor personnel and others working under 
supervision of the Corps will be cautioned to avoid public statements 
about the condition of the dam until after the District Engineer has 
approved the report. The Corps will respond fully to inquiries after the 
Governor has received the approved report or been notified of an unsafe 
dam. An information copy of the report should be sent to the District 
office normally having jurisdiction if other than the District 
responsible for the inspection.
    (iv) Follow-up action. A Federal investment of the magnitude 
anticipated for this inspection program makes it desirable that a 
reporting system be established to keep the District Engineer abreast of 
the implementation of the recommendations in the inspection reports. The 
letters of transmittal to the Governor and owner will request that

[[Page 262]]

the District Engineer be informed of the actions taken on the 
recommendations in the inspection reports. However, the National Dam 
Inspection Act only authorizes the initial inspection of certain dams; 
therefore, once a report is completed no reinspection will be 
undertaken.
    (4) Unsafe dams. The investigating engineer will be required to 
immediately notify the District Engineer when a dam is assessed as being 
unsafe. He will also indicate if probable failure of the unsafe dam is 
judged to be imminent and immediate action is required to reduce or 
eliminate the threat. The District Engineer will evaluate the findings 
of the investigating team and will immediately notify the Governor and 
the owner if the findings are Unsafe Non-Emergency or Unsafe-Emergency. 
The appropriate State agency and the Corps of Engineers officials having 
emergency operation responsibility for the area in which the dam is 
located will also be notified. The information provided in the unsafe 
dam notice shall be as indicated in Appendix F. Any emergency procedures 
or remedial actions deemed necessary by the District Engineer will be 
recommended to the Governor who has the responsibility for any 
corrective actions. As provided in ER 500-1-1, Corps assistance under 
Pub. L. 84-99 ``Advance Measures,'' may be made available to complement 
the owner's and Governor's action under certain conditions and subject 
to the approval of the Director of Civil Works. The District Engineer's 
Emergency Operation Officer will coordinate the advance measures request 
in accordance with existing procedures. Coordination will be maintained 
between the District responsible for emergency action under Pub. L. 84-
90 and the District responsible for the inspection.
    (5) Emergency action plans. An emergency action plan should be 
available for every dam in the high and significant hazard category. 
Such plans should outline actions to be taken by the operator to 
minimize downstream effects of an emergency and should include an 
effective warning system. If an emergency action plan has not been 
developed, the inspection report should recommend that the owner develop 
such an action plan. However, the Corps has no authority to require an 
emergency action plan.
    (k) Progress reports. Progress reports should be submitted monthly 
by the Division Engineer to WRSC. The reports shall include progress 
through the last Saturday of the month and should be mailed by the 
following Monday. The reports shall contain the information and be 
typewritten in the format shown in Appendix G. Copies of Unsafe Dam Data 
Sheets will be submitted with the progress report. Copies of the 
completed inspection report for Dams in the Unsafe-Emergency category 
will be submitted also. (RCS-DAEN-CWE-19)
    (l) Contracts--(1) Corps of Engineers supervision. Contracts for 
performing inventory and inspection activities under supervision of the 
Corps of Engineers shall be Fixed-Price Architect Engineer Contracts for 
Services. A sample scope of work setting forth requirements is provided 
in Appendix H. Experience has shown that costs for individual dam 
inspection have been lower when multiple inspections are included in one 
contract. Therefore, each A-E contract should include multiple dam 
inspections where practicable. Corps participation in A-E inspections 
should be held to a minimum. Corps representatives should participate in 
only enough A-E inspections to assure the equality of the inspections.
    (2) State supervision. Contracts with States for performing 
inventory and inspection activities under State supervision may be 
either a Cost-Reimbursement type A-E Contract for Services or a Fixed-
Price type contract. The selection of Architect-Engineers by the State 
should require approval of the Corps of Engineers Contracting Officer. 
The negotiated price for A-E services under cost-reimbursement type 
contracts with States will also require approval by the Contracting 
Officer. Contracts with States should require timely submission of the 
inspection reports to the District Engineer for review and approval. The 
contract provisions should also prevent public release of or public 
comment on the inspection report until the District Engineer has 
reviewed and approved the report. Corps

[[Page 263]]

of Engineers participation in State inspections should be limited to 
occasional selected inspections to assure the quality of the State 
program.
    (m) Training. As indicated in paragraph (f) of this section, one 
objective of the inspection program for non-Federal Dams is to prepare 
the States to provide effective dam safety programs. In many States this 
will require training of personnel of State agencies in the technical 
aspects of dam inspections. The Office, Chief of Engineers is studying 
the need for and content of a comprehensive Corps-sponsored training 
program in dam inspection technology. Pending the possible adoption of 
such a comprehensive plan, division and district Engineers are 
encouraged to take advantage of suitable opportunities to provide needed 
training in dam safety activities to qualified employees of State 
agencies and, when appropriate, to employees of architect-engineer firms 
engaged in the program. The following general considerations should be 
observed in providing such training:
    (1) Priority must be placed on inspection of dams and updating the 
national dam inventory; hence, diversion of resources to training 
activities should not deter or delay these principle program functions.
    (2) Salaries, per diem and travel expenses relating to training 
activities of State employees will be a State expense. There will be no 
tuition charge for State employees.
    (3) Architect-Engineer firms will be required to pay expenses and 
tuition costs for their employees participating in Corps-sponsored 
training activities.
    (4) Corps-sponsored training will require that each trainee is a 
qualified engineer or geologist and will concentrate on engineering 
technology related directly to dam safety. (This may require screening 
of proposed candidates for training.)
    (5) Under this program, the Corps will not sponsor training that is 
intended primarily to satisfy requirements for a degree.
    (6) Training by participation in actual dam inspections and/or 
management of the inspection program should be encouraged.

             Appendix A to Sec.  222.6--Division Assignments

    To facilitate better coordination with the States, the Division 
Engineers are responsible for the dam inspection program by States as 
follows:

New England Division: Maine, Rhode Island, Connecticut, Vermont, New 
Hampshire, Massachusetts
North Atlantic Division: New York, New Jersey, Pennsylvania, Delaware, 
Maryland, Virginia, District of Columbia
Ohio River Division: West Virginia, Ohio, Kentucky, Tennessee, Indiana
South Atlantic Division: North Carolina, South Carolina, Georgia, 
Florida, Alabama, Puerto Rico, Virgin Islands
Lower Mississippi Valley Division: Mississippi, Louisiana, Missouri
North Central Division: Michigan, Wisconsin, Illinois, Minnesota, Iowa
Southwestern Division: Arkansas, Oklahoma, Texas, New Mexico
Missouri River Division: Kansas, Nebraska, South Dakota, North Dakota, 
Wyoming, Colorado
North Pacific Division: Oregon, Idaho, Montana, Washington, Alaska
South Pacific Division: Utah, California, Arizona, Nevada
Pacific Ocean Division: Hawaii, Trust Territories, American Samoa

              Appendix B to Sec.  222.6--Inventory of Dams

                 (RCS-DAEN-CWE-17 and OMB No. 49-RO421)

    1. The updating of the inventory will include the completion of all 
items of data for all dams now included in the inventory, verification 
of the data now included in the inventory, and inclusion of complete 
data for all appropriate existing dams not previously listed. Data 
completion, verification and updating will be scheduled over a three 
year period.
    2. The inventory data will be recorded on Engineering Form 4474 and 
4474A (Exhibit 2). The general instructions for completing the forms are 
printed on the back of the forms. Parts I and II of the forms are to be 
fully completed. The instruction for completing Item 29, Line 5, Para. 
II (Engr Form 4474A) is revised to conform identically with the hazard 
potential classification contained in the recommended guidelines for 
safety inspection of dams. Additional data has been added to designate 
Corps districts in which the dam is located, Federal agency owned dams, 
Corps owned dams, Federal agency regulated dams, dams constructed with 
technical or financial assistance of the U.S. Soil Conservation Service, 
and privately owned dams located on Federal property.
    3. All inventory data will be verified utilizing all available 
sources of information and will include site visitation if required.

[[Page 264]]

    4. The Inventory Data Base is stored on the Boeing Computer Services 
(BCS) EKS System in Seattle, Washington. The data is available to all 
Corps offices for queries using Data Base Management System 2000 (S2K).
    a. To access the National Data Base log on BCS and type the 
following:

GET,DAMS/UN=CECELB

CALL,DAMS

    b. For current information and changes to the National Inventory 
Data Base, type:

OLD,HOTDAM/UN=CEC1AT

LIST

    5. The inventory update data will be furnished and the National Data 
Base will be updated on a monthly basis. The monthly submission will 
cover all dams whose inventory data were completed since the last 
report. The update data will be loaded directly onto the Boeing Computer 
by the field office.
    a. The procedure for loading the data on the Boeing Computer can be 
printed by accessing the Boeing Computer and listing the information 
file ``HOTDAM.'' (See paragraph 4b. above.)
    b. It is the responsibility of the submitting office to edit the 
data prior to furnishing it for the update. Editing will be accomplished 
by processing the data using the Inventory Edit Computer program 
developed by the Kansas City District. This procedure is described in 
the ``HOTDAM'' file.
    6. Federal agencies will be uniformly designated by major and minor 
abbreviations according to the following list whenever applicable to 
Items 46 through 53. Abbreviations are to be left justified within the 
field with one blank separating major and minor abbreviations.

------------------------------------------------------------------------
                                             Major            Minor
------------------------------------------------------------------------
a. International Boundary and Water     IBWC
 Commission.
b. U.S. Department of Agriculture:
  (1) Soil Conservation Service.......  USDA             SCS
  (2) Forest Service..................  USDA             FS
c. U.S. Department of Energy Federal    DOE              FERC
 Energy Regulatory Commission.
d. Tennessee Valley Authority.........  TVA
e. U.S. Department of Interior:
  (1) Bureau of Sport Fisheries and     DOI              BSFW
   Wildlife.
  (2) Geological Survey...............  DOI              GS
  (3) Bureau of Land Management.......  DOI              BLM
  (4) Bureau of Reclamation...........  DOI              USBR
  (5) Bureau of Indian Affairs........  DOI              BIA
f. U.S. Department of Labor: (1) Mine   DOL              MSHA
 Safety and Health Administration.
g. Corps of Engineers:
  (1) Lower Mississippi Valley
   Division:
    (a) Memphis District..............  DAEN             LMM
    (b) New Orleans District..........  DAEN             LMN
    (c) St. Louis District............  DAEN             LMS
    (d) Vicksburg District............  DAEN             LMK
  (2) Missouri River Division:
    (a) Kansas City District..........  DAEN             MRK
    (b) Omaha District................  DAEN             MRO
  (3) New England Division............  DAEN             NED
  (4) North Atlantic Division:........
    (a) Baltimore District............  DAEN             NAB
    (b) New York District.............  DAEN             NAN
    (c) Norfolk District..............  DAEN             NAO
    (d) Philadelphia District.........  DAEN             NAP
  (5) North Central Division:
    (a) Buffalo District..............  DAEN             NCB
    (b) Chicago District..............  DAEN             NCC
    (c) Detroit District..............  DAEN             NCE
    (d) Rock Island District..........  DAEN             NCR
    (e) St. Paul District.............  DAEN             NCS
  (6) North Pacific Division:
    (a) Alaska District...............  DAEN             NPA
    (b) Portland District.............  DAEN             NPP
    (c) Seattle District..............  DAEN             NPS
    (d) Walla Walla District..........  DAEN             NPW
  (7) Ohio River Division:
    (a) Huntington District...........  DAEN             ORH
    (b) Louisville District...........  DAEN             ORL
    (c) Nashville District............  DAEN             ORN
    (d) Pittsburgh District...........  DAEN             ORP
  (8) Pacific Ocean Division..........  DAEN             POD
  (9) South Atlantic Division:
    (a) Charleston District...........  DAEN             SAC
    (b) Jacksonville District.........  DAEN             SAJ
    (c) Mobile District...............  DAEN             SAM
    (d) Savannah District.............  DAEN             SAS
    (e) Wilmington District...........  DAEN             SAW
  (10) South Pacific Division:
    (a) Los Angeles District..........  DAEN             SPL
    (b) Sacramento District...........  DAEN             SPK
    (c) San Franciso District.........  DAEN             SPN
  (11) Southwestern Division:
    (a) Albuquerque District..........  DAEN             SWA
    (b) Fort Worth District...........  DAEN             SWF
    (c) Galveston District............  DAEN             SWG
    (d) Little Rock District..........  DAEN             SWL
    (e) Tulsa District................  DAEN             SWT
------------------------------------------------------------------------

    7. Procedures for Revising and Updating the Inventory of Dams Master 
File.
    a. To Change Correct or Add an Item. Submit a change card that 
contains the identification assigned to the dams (Columns 1 thru 7), the 
proper card code (Column 80) and only the item or items changed, 
corrected or added. Data on the master file is added or replaced on an 
item for item basis.
    b. To Delete an Item. Submit a change card that contains the 
identification assigned to the dam, (Columns 1 thru 7), the proper card 
code (Column 80), and an asterisk (*) in the left most column of the 
item or items to be deleted. More than one item can be changed, 
corrected, added on or deleted from the same card.
    c. To Delete the Entire Data for a Dam from the Master File. Submit 
a zero (0) card punched as follows:

Columns 1 thru 7--Item 1 identification assigned to the dam
Columns 8 thru 10--Item 2, Division Code
Columns 11 thru 16--The word DELETE
Columns 17 thru 79--Blank Spaces
Column 80--A zero

    8. Keypunch Instructions and Punched Card Formats.

[[Page 265]]

    a. Table 1 describes the character set to be used for keypunch cards 
of Engr. Forms 4474 and 4474A.
    b. Exhibit 1 is the EDPC keypunch instructions and punch card 
formats defining the data fields (Items) and card columns to be used in 
preparing punched cards in compliance with the requirements of this 
regulation.
    c. Exhibit 2 are prints of Engr. Forms 4474 and 4474A which are laid 
out in punch card format to facilitate punching cards directly from the 
completed forms.
[GRAPHIC] [TIFF OMITTED] TC31OC91.000


[[Page 266]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.001


[[Page 267]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.002


[[Page 268]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.003


[[Page 269]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.004


[[Page 270]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.005


[[Page 271]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.006


[[Page 272]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.007


[[Page 273]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.008


[[Page 274]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.009


[[Page 275]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.010


[[Page 276]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.011

 Appendix C to Sec.  222.6--Hydrologic and Hydraulic Assessment of Dams

    1. Phase I inspections are not intended to provide detailed 
hydrologic and hydraulic analyses of dam and reservoir capabilities. 
However, when such analyses are available, they should be evaluated for 
reliability and completeness. If a project's ability to pass the 
appropriate flood (see Table 3, page D-12 of Recommended Guidelines) can 
be determined from available information of a brief study, such an 
assessment should be made. It should be noted that hydrologic and 
hydraulic analyses connected with the Phase I inspections should be 
based on approximate methods or systematized computer programs that take 
minimal effort. The Hydrologic Engineering Center (HEC) has developed a 
special computer program for hydrologic and hydraulic analyses to be 
used with the Phase I inspection program. Other Field Operating Agencies 
have developed similar computer programs or generalized procedures which 
are acceptable for use. All such efforts should be completed with 
minimum resources.
    2. A finding that a dam will not safely pass the flood indicated in 
the Recommended Guidelines does not necessarily indicate that the dam 
should be classified as unsafe. The degree of inadequacy of the spillway 
to pass the appropriate flood and the probable adverse impacts of dam 
failure because of overtopping must be considered in making such 
classification. The following criteria have

[[Page 277]]

been selected which indicate when spillway capacity is so seriously 
inadequate that a project must be classified as unsafe. All of the 
following conditions must prevail before designating a dam unsafe:
    a. There is high hazard to loss of life from large flows downstream 
of the dam.
    b. Dam failure resulting from overtopping would significantly 
increase the hazard to loss of life downstream from the dam from that 
which would exist just before overtopping failure.
    c. The spillway is not capable of passing one-half of the probable 
maximum flood without overtopping the dam and causing failure.
    3. The above criteria are generally adequate for evaluating most 
non-Federal dams. However, in a few cases the increased hazard potential 
from overtopping and failure is so great as to result in catastrophic 
consequences. In such cases, the evaluation of condition 2c should 
utilize a flood more closely approximating the full probable maximum 
flood rather than one-half the flood. An example of such a situation 
would be a large dam immediately above a highly populated flood plain, 
with little likelihood of time for evacuation in the event of an 
emergency.
    4. Conditions 2a and 2b require an approximation of housing location 
in relation to flooded areas. Resources available in Phase I inspections 
do not permit detailed surveys or time-consuming studies to develop such 
relationships. Therefore, rough estimates will generally be made from 
data obtained during the inspection and from readily available maps and 
drawings. Brief computer routings such as the HEC-1 dam break analysis, 
using available data, are recommended in marginal cases. The HEC-1, dam 
break version, is available on the Boeing Computer Services or may be 
obtained from the Hydrologic Engineering Center, Davis, California. 
Available resources do not permit detailed studies or investigations to 
establish the amount of overtopping that would cause a dam to fail, as 
designated in condition 2c. Professional judgment and available 
information will have to be used in these determinations. When detailed 
investigations and studies are required to make a reasonable judgment of 
the conditions which designate an unsafe dam, the inspection report 
should recommend that such studies be the responsibility of the dam 
owner.
    5. During the inspection of a dam, consideration should be given to 
impacts on other dams located downstream from the project being 
inspected. When failure of a dam would be likely to cause failure of 
another dam(s) downstream, its designation as an unsafe dam could result 
in multiple impacts. Therefore, the information should be explicitly 
described in the inspection report. Such information may be vital to the 
priorities established by State Governors for dam improvements. 
Similarly, when the failure of an upstream dam (classified as unsafe) 
could cause failure of the dam being inspected, this information should 
be prominently displayed in the inspection report.
    6. The criteria established in paragraph 2 for designating unsafe 
dams because of seriously inadequate spillways are considered reasonable 
and prudent. They provide a consistent bases for declaring unsafe dams 
and also serve as an effective compromise between the Recommended 
Guidelines and unduly low standards suggested by special interests and 
individuals unfamiliar with flood hazard potential.
    7. The Hydrometeorological Branch (HMB) of the National Weather 
Service has reviewed some 500 experienced large storms in the United 
States. The purpose of the review was to ascertain the relative 
magnitude of experienced large storms to probable maximum precipitation 
(PMP) and their distribution throughout the country. Their review 
reveals that about 25 percent of the major storms have exceeded 50 
percent of the probable maximum precipitation for one or more 
combinations of area and duration. In fact some storms have very closely 
approximated the PMP values. Exhibits C-1 thru C-5 indicate locations 
where experienced storms have exceeded 50 percent of the PMP.
    8. There are several options to consider when selecting mitigation 
measures to avoid severe consequences of a dam failure from overtopping. 
The following measures may be required by a Governor when sufficient 
legal authority is available under State laws and a dam presents a 
serious threat to loss of life.
    a. Remove the dam.
    b. Increase the height of dam and/or spillway size to pass the 
probable maximum flood without overtopping the dam.
    c. Purchase downstream land that would be adversely impacted by dam 
failure and restrict human occupancy.
    d. Enhance the stability of the dam to permit overtopping by the 
probable maximum flood without failure.
    e. Provide a highly reliable flood warning system (generally does 
not prevent damage but avoids loss of life).

[[Page 278]]



 Table 1--Storms With Rainfall =150% of PMP, U.S. East of the 105th Meridian (for 10 mi\2\, 6 Hours;
                                200 mi\2\, 24 Hours and/or 1,000 mi\2\, 48 Hours)
----------------------------------------------------------------------------------------------------------------
                                       Corps assignment             Storm center
          Storm date            Index       No. (if     ------------------------------------ Latitude  Longitude
                                 No.      available)           Town              State
----------------------------------------------------------------------------------------------------------------
July 26, 1819................       1  ................  Catskill........  NY..............  42[deg]1  73[deg]53
                                                                                               2[min]      [min]
Aug. 5, 1843.................       2  ................  Concordville....  PA..............  39[deg]5  75[deg]32
                                                                                               3[min]      [min]
Sept. 10-13, 1878............       3  OR 9-19.........  Jefferson.......  OH..............  41[deg]4  80[deg]46
                                                                                               5[min]      [min]
Sept. 20-24, 1882............       4  NA 1-3..........  Paterson........  NJ..............  40[deg]5  74[deg]10
                                                                                               5[min]      [min]
June 13-17, 1886.............       5  LMV 4-27........  Alexandria......  LA..............  31[deg]1  92[deg]33
                                                                                               9[min]      [min]
June 27-July 11, 1899........       6  GM 3-4..........  Turnersville....  TX..............  30[deg]5  96[deg]32
                                                                                               2[min]      [min]
Aug. 24-28, 1903.............       7  MR 1-10.........  Woodburn........  IA..............  40[deg]5  93[deg]35
                                                                                               7[min]      [min]
Oct. 7-11, 1903..............       8  GL 4-9..........  Paterson........  NJ..............  40[deg]5  74[deg]10
                                                                                               5[min]      [min]
July 18-23, 1909.............       9  UMV 1-11B.......  Ironwood........  MI..............  46[deg]2  90[deg]11
                                                                                               7[min]      [min]
July 18-23, 1909.............      10  UMV 1-11A.......  Beaulieu........  MN..............  47[deg]2  95[deg]48
                                                                                               1[min]      [min]
July 22-23, 1911.............      11  ................  Swede Home......  NB..............  40[deg]2  96[deg]54
                                                                                               2[min]      [min]
July 19-24, 1912.............      12  GL 2-29.........  Merrill.........  WI..............  45[deg]1  89[deg]41
                                                                                               1[min]      [min]
July 13-17, 1916.............      13  SA 2-9..........  Altapass........  NC..............  35[deg]3  82[deg]01
                                                                                               3[min]      [min]
Sept. 8-10, 1921.............      14  GM 4-12.........  Taylor..........  TX..............  30[deg]3  97[deg]18
                                                                                               5[min]      [min]
Oct. 4-11, 1924..............      15  SA 4-20.........  New Smyrna......  FL..............  29[deg]0  80[deg]55
                                                                                               7[min]      [min]
Sept. 17-19, 1926............      16  MR 4-24.........  Boyden..........  IA..............  43[deg]1  96[deg]00
                                                                                               2[min]      [min]
Mar. 11-16, 1929.............      17  UMV 2-20........  Elba............  AL..............  31[deg]2  86[deg]04
                                                                                               5[min]      [min]
June 30-July 2, 1932.........      18  GM 5-1..........  State Fish        TX..............  30[deg]0  99[deg]07
                                                          Hatchery.                            1[min]      [min]
Sept. 16-17, 1932............      19  ................  Ripogenus Dam...  ME..............  45[deg]5  69[deg]09
                                                                                               3[min]      [min]
July 22-27, 193..............      20  LMV 2-26........  Logansport......  LA..............  31[deg]5  94[deg]00
                                                                                               8[min]      [min]
Apr. 3-4 1934................      21  SW 2-11.........  Cheyenne........  OK..............  35[deg]3  99[deg]40
                                                                                               7[min]      [min]
May 30-31, 1935..............      22  MR 3-28A........  Cherry Creek....  CO..............  39[deg]1  104[deg]3
                                                                                               3[min]     2[min]
May 31, 1935.................      23  GM 5-20.........  Woodward........  TX..............  29[deg]2  99[deg]28
                                                                                               0[min]      [min]
July 6-10, 1935..............      24  NA 1-27.........  Hector..........  NY..............  42[deg]3  76[deg]53
                                                                                               0[min]      [min]
Sept. 2-6, 1935..............      25  SA 1-26.........  Easton..........  MD..............  38[deg]4  76[deg]01
                                                                                               6[min]      [min]
Sept. 14-18, 1936............      26  GM 5-7..........  Broome..........  TX..............  31[deg]4  100[deg]5
                                                                                               7[min]     0[min]
June 19-20, 1939.............      27  ................  Snyder..........  TX..............  32[deg]4  100[deg]5
                                                                                               4[min]     5[min]
July 4-5, 1939...............      28  ................  Simpson.........  KY..............  38[deg]1  83[deg]22
                                                                                               3[min]      [min]
Aug. 19, 1939................      29  NA 2-3..........  Manahawkin......  NJ..............  39[deg]4  74[deg]16
                                                                                               2[min]      [min]
June 3-4, 1940...............      30  MR 4-5..........  Grant Township..  NB..............  42[deg]0  96[deg]53
                                                                                               1[min]      [min]
Aug. 6-9, 1940...............      31  LMV 4-24........  Miller Isl......  LA..............  29[deg]4  92[deg]10
                                                                                               5[min]      [min]
Aug. 10-17, 1940.............      32  SA 5-19A........  Keysville.......  VA..............  37[deg]0  78[deg]30
                                                                                               3[min]      [min]
Sept. 1, 1940................      33  NA 2-4..........  Ewan............  NJ..............  39[deg]4  75[deg]12
                                                                                               2[min]      [min]
Sept. 2-6, 1940..............      34  SW 2-18.........  Hallet..........  OK..............  36[deg]1  96[deg]36
                                                                                               5[min]      [min]
Aug. 28-31, 1941.............      35  UMV 1-22........  Haywood.........  WI..............  46[deg]0  91[deg]28
                                                                                               0[min]      [min]
Oct. 17-22, 1941.............      36  SA 5-6..........  Trenton.........  FL..............  29[deg]4  82[deg]57
                                                                                               8[min]      [min]
July 17-18, 1942.............      37  OR 9-23.........  Smethport.......  PA..............  41[deg]5  78[deg]25
                                                                                               0[min]      [min]
Oct. 11-17, 1942.............      38  SA 1-28A........  Big Meadows.....  VA..............  38[deg]3  78[deg]26
                                                                                               1[min]      [min]
May 6-12, 1943...............      39  SW 2-20.........  Warner..........  OK..............  35[deg]2  95[deg]18
                                                                                               9[min]      [min]
May 12-20, 1943..............      40  SW 2-21.........  Nr. Mounds......  OK..............  35[deg]5  96[deg]04
                                                                                               2[min]      [min]
July 27-29, 1943.............      41  GM 5-21.........  Devers..........  TX..............  30[deg]0  94[deg]35
                                                                                               2[min]      [min]
Aug. 4-5, 1943...............      42  OR 3-30.........  Nr. Glenville...  WV..............  38[deg]5  80[deg]50
                                                                                               6[min]      [min]
June 10-13, 1944.............      43  MR 6-15.........  Nr. Stanton.....  NB..............  41[deg]5  97[deg]03
                                                                                               2[min]      [min]
Aug. 12-15, 1946.............      44  MR 7-2A.........  Cole Camp.......  MO..............  38[deg]4  93[deg]13
                                                                                               0[min]      [min]
Aug. 12-16, 1946.............      45  MR 7-2B.........  Nr. Collinsville  IL..............  38[deg]4  89[deg]59
                                                                                               0[min]      [min]
Sept. 26-27, 1946............      46  GM 5-24.........  Nr. San Antonio.  TX..............  29[deg]2  98[deg]29
                                                                                               0[min]      [min]
June 23-24, 1948.............      47  ................  Nr. Del Rio.....  TX..............  29[deg]2  100[deg]3
                                                                                               2[min]     7[min]
Sept. 3-7, 1950..............      48  SA 5-8..........  Yankeetown......  FL..............  29[deg]0  82[deg]42
                                                                                               3[min]      [min]
June 23-28, 1954.............      49  SW 3-22.........  Vic Pierce......  TX..............  30[deg]2  101[deg]2
                                                                                               2[min]     3[min]
Aug. 17-20, 1955.............      50  NA 2-22A........  Westfield.......  MA..............  42[deg]0  72[deg]45
                                                                                               7[min]      [min]
May 15-16, 1957..............      51  ................  Hennessey.......  OK..............  36[deg]0  97[deg]56
                                                                                               2[min]      [min]
June 14-15, 1957.............      52  ................  Nr. E. St. Louis  IL..............  38[deg]3  90[deg]24
                                                                                               7[min]      [min]
June 23-24, 1963.............      53  ................  David City......  NB..............  41[deg]1  97[deg]05
                                                                                               4[min]      [min]
June 13-20, 1965.............      54  ................  Holly...........  CO..............  37[deg]4  102[deg]2
                                                                                               3[min]     3[min]
June 24, 1966................      55  ................  Glenullin.......  ND..............  47[deg]2  101[deg]1
                                                                                               1[min]     9[min]
Aug. 12-13, 1966.............      56  ................  Nr. Greely......  NB..............  41[deg]3  98[deg]32
                                                                                               3[min]      [min]
Sept. 19-24, 1967............      57  SW 3-24.........  Falfurrias......  TX..............  27[deg]1  98[deg]12
                                                                                               6[min]      [min]
July 16-17, 1968.............      58  ................  Waterloo........  IA..............  42[deg]3  92[deg]19
                                                                                               0[min]      [min]
July 4-5, 1969...............      59  ................  Nr. Wooster.....  OH..............  40[deg]5  82[deg]00
                                                                                               0[min]      [min]
Aug. 19-20, 1969.............      60  NA 2-3..........  Nr. Tyro........  VA..............  37[deg]4  79[deg]00
                                                                                               9[min]      [min]
June 9, 1972.................      61  ................  Rapid City......  SD..............  44[deg]1  103[deg]3
                                                                                               2[min]     1[min]
June 19-23, 1972.............      62  ................  Zerbe...........  PA..............  40[deg]3  76[deg]31
                                                                                               7[min]      [min]
July 21-22, 1972.............      63  ................  Nr. Cushing.....  MN..............  46[deg]1  94[deg]30
                                                                                               0[min]      [min]
Sept. 10-12, 1972............      64  ................  Harlan..........  IA..............  41[deg]4  95[deg]15
                                                                                               3[min]      [min]
Oct. 10-11, 1973.............      65  ................  Enid............  OK..............  36[deg]2  97[deg]52
                                                                                               5[min]      [min]
----------------------------------------------------------------------------------------------------------------


[[Page 279]]


 Table 2--Storms With Rainfall =50% of PMP, U.S. West of Continental Divide (for 10 mi \2\ 6 Hours or
                              1,000 mi\2\ for One Duration Between 6 and 72 Hours)
----------------------------------------------------------------------------------------------------------------
                                                        Storm center                                    Duration
                                   Index -----------------------------------------                         for
           Storm date               No.                                            Latitude  Longitude    1,000
                                                  Town                State                               mi\2\
----------------------------------------------------------------------------------------------------------------
Aug. 11, 1890...................       1  Palmetto...........  NV................  37[deg]2  117[deg]4  ........
                                                                                     7[min]     2[min]
Aug. 12, 1891...................       2  Campo..............  CA................  32[deg]3  116[deg]2  ........
                                                                                     6[min]     8[min]
Aug. 28, 1898...................       3  Ft. Mohave.........  AZ................  35[deg]0  114[deg]3  ........
                                                                                     3[min]     6[min]
Oct. 4-6, 1911..................       4  Gladstone..........  CO................  37[deg]5  107[deg]3  ........
                                                                                     3[min]     9[min]
Dec. 29, 1913-Jan. 3, 1914......       5  ...................  CA................  39[deg]5  121[deg]2  ........
                                                                                     5[min]     5[min]
Feb. 17-22, 1914................       6  Colby Ranch........  CA................  34[deg]1  118[deg]0  ........
                                                                                     8[min]     7[min]
Feb. 20-25, 1917................       7  ...................  CA................  37[deg]3  119[deg]3  ........
                                                                                     5[min]     6[min]
Sept. 13, 1918..................       8  Red Bluff..........  CA................  40[deg]1  122[deg]1  ........
                                                                                     0[min]     4[min]
Feb. 26-Mar 4, 1938.............       9  ...................  CA................  34[deg]1  117[deg]1  ........
                                                                                     4[min]     1[min]
Mar. 30-Apr. 2, 1931............      10  ...................  ID................  46[deg]3  114[deg]5        24
                                                                                     0[min]     0[min]
Feb. 26, 1932...................      11  Big Four...........  WA................  48[deg]0  121[deg]3  ........
                                                                                     5[min]     0[min]
Nov. 21, 1933...................      12  Tatoosh Is.........  WA................  48[deg]2  124[deg]4  ........
                                                                                     3[min]     4[min]
Jan. 20-25, 1935................      13  ...................  WA................  47[deg]3  123[deg]3         6
                                                                                     0[min]     0[min]
Jan. 20-25, 1935................      14  ...................  WA................  47[deg]0  122[deg]0        72
                                                                                     0[min]     0[min]
Feb. 4-8, 1937..................      15  Cyamaca Dam........  CA................  33[deg]0  116[deg]3  ........
                                                                                     0[min]     5[min]
Dec. 9-12, 1937.................      16  ...................  CA................  38[deg]5  122[deg]4  ........
                                                                                     1[min]     3[min]
Feb. 27-Mar. 4, 1938............      17  ...................  AZ................  34[deg]5  111[deg]4        12
                                                                                     7[min]     4[min]
Jan. 19-24, 1943................      18  ...................  CA................  37[deg]3  119[deg]2        18
                                                                                     5[min]     5[min]
Jan. 19-24, 1943................      19  Hoegee's Camp......  CA................  34[deg]1  118[deg]0  ........
                                                                                     3[min]     2[min]
Jan. 30-Feb. 3, 1945............      20  ...................  CA................  37[deg]3  119[deg]3  ........
                                                                                     5[min]     0[min]
Dec. 27, 1945...................      21  Mt. Tamalpias......  CA................  37[deg]5  122[deg]3  ........
                                                                                     4[min]     4[min]
Nov. 13-21, 1950................      22  ...................  CA................  36[deg]3  118[deg]3        24
                                                                                     0[min]     0[min]
Aug. 25-30, 1951................      23  ...................  AZ................  34[deg]0  112[deg]2        72
                                                                                     7[min]     1[min]
July 19, 1955...................      24  Chiatovich Flat....  CA................  37[deg]4  118[deg]1  ........
                                                                                     4[min]     5[min]
Aug. 16, 1958...................      25  Morgan.............  UT................  41[deg]0  111[deg]3  ........
                                                                                     3[min]     8[min]
Sept. 18, 1959..................      26  Newton.............  CA................  40[deg]2  122[deg]1  ........
                                                                                     2[min]     2[min]
June 7-8, 1964..................      27  Nyack Ck...........  MT................  48[deg]3  113[deg]3        12
                                                                                     0[min]     8[min]
Sept. 3-7, 1970.................      28  ...................  UT................  37[deg]3  109[deg]0         6
                                                                                     8[min]     4[min]
Sept. 3-7, 1970.................      29  ...................  AZ................  33[deg]4  110[deg]5         6
                                                                                     9[min]     6[min]
June 7, 1972....................      30  Bakersfield........  CA................  35[deg]2  119[deg]0  ........
                                                                                     5[min]     3[min]
Dec. 9-12, 1937.................      31  ...................  CA................  39[deg]4  121[deg]3        48
                                                                                     5[min]     0[min]
----------------------------------------------------------------------------------------------------------------


[[Page 280]]

[GRAPHIC] [TIFF OMITTED] TC31OC91.012


[[Page 281]]

[GRAPHIC] [TIFF OMITTED] TC31OC91.013


[[Page 282]]

[GRAPHIC] [TIFF OMITTED] TC31OC91.014


[[Page 283]]

[GRAPHIC] [TIFF OMITTED] TC31OC91.015


[[Page 284]]

[GRAPHIC] [TIFF OMITTED] TC31OC91.016


[[Page 285]]

Appendix D to Sec.  222.6--Recommended Guidelines for Safety Inspection 
                                 of Dams

        Department of the Army--Office of the Chief of Engineers

                                 Preface

    The recommended guidelines for the safety inspection of dams were 
prepared to outline principal factors to be weighed in the determination 
of existing or potential hazards and to define the scope of activities 
to be undertaken in the safety inspection of dams. The establishment of 
rigid criteria or standards is not intended. Safety must be evaluated in 
the light of peculiarities and local conditions at a particular dam and 
in recognition of the many factors involved, some of which may not be 
precisely known. This can only be done by competent, experienced 
engineering judgment, which the guidelines are intended to supplement 
and not supplant. The guidelines are intended to be flexible, and the 
proper flexibility must be achieved through the employment of 
experienced engineering personnel.
    Conditions found during the investigation which do not meet 
guideline recommendations should be assessed by the investigator as to 
their import from the standpoint of the involved degree of risk. Many 
deviations will not compromise project safety and the investigator is 
expected to identify them in this manner if that is the case. Others 
will involve various degrees of risk, the proper evaluation of which 
will afford a basis for priority of subsequent attention and possible 
remedial action.
    The guidelines present procedures for investigating and evaluating 
existing conditions for the purpose of identifying deficiencies and 
hazardous conditions. The two phases of investigation outlined in the 
guidelines are expected to accomplish only this and do not encompass in 
scope the engineering which will be required to perform the design 
studies for corrective modification work.
    It is recognized that some States may have established or will adopt 
inspection criteria incongruous in some respects with these guidelines. 
In such instances assessments of project safety should recognize the 
State's requirements as well as guideline recommendations.
    The guidelines were developed with the help of several Federal 
agencies and many State agencies, professional engineering 
organizations, and private engineers. In reviewing two drafts of the 
guidelines they have contributed many helpful suggestions. Their 
contributions are deeply appreciated and have made it possible to evolve 
a document representing a consensus of the engineering fraternity. As 
experience is gained with use of the guidelines, suggestions for future 
revisions will be generated. All such suggestions should be directed to 
the Chief of Engineers, U.S. Army, DAEN-CWE-D, Washington, D.C. 20314.

          Recommended Guidelines for Safety Inspection of Dams

                            Table of Contents

                                 Preface

                         Chapter 1--Introduction

Para.
1.1 Purpose.
1.2 Applicability.
1.3 Authority.

                     Chapter 2--General Requirements

2.1 Classification of dams.
2.1.1 Size.
2.1.2 Hazard potential.
2.2 Selection of dams to be investigated.
2.3 Technical investigations.
2.4 Qualifications of investigators.
2.5 Reports.

                    Chapter 3--Phase I Investigation

3.1 Purpose.
3.2 Scope.
3.3 Engineering data.
3.4 Field inspections.
3.5 Evaluation of hydraulic and hydrologic features.
3.5.1 Design data.
3.5.2 Experience data.
3.6 Evaluation of structural stability.
3.6.1 Design and construction data.
3.6.2 Operating records.
3.6.3 Post contruction changes.
3.6.4 Seismic stability.

                    Chapter 4--Phase II Investigation

4.1 Purpose.
4.2 Scope.
4.3 Hydraulic and hydrologic analysis.
4.3.1 Maximum water surface based on SDF peak inflow.
4.3.1.1 Peak for 100-year flood.
4.3.1.2 Peak for PMF or fraction thereof.
4.3.2 Maximum water surface based on SDF hydrograph.
4.3.3 Acceptable procedures.
4.3.4 Freeboard allowances.
4.4 Stability investigations.
4.4.1 Foundation and material investigations.
4.4.2 Stability assessment.
4.4.2.1 Seismic stability.
4.4.2.2 Clay shale foundation.
4.4.3 Embankment dams.
4.4.3.1 Liquefaction.
4.4.3.2 Shear failure.
4.4.3.3 Loading conditions.
4.4.3.4 Safety factors.
4.4.3.5 Seepage failure.
4.4.3.6 Seepage analyses.

[[Page 286]]

4.4.4 Concrete dams and appurtenant structures.
4.4.4.1 Requirements for stability.
4.4.4.2 Loads.
4.4.4.3 Stresses.
4.4.4.4 Overturning.
4.4.4.5 Sliding.
4.4.4.5.1 Sliding resistance.
4.4.4.5.2 Downstream resistance.
4.4.4.5.3 Safety factor.

                           Chapter 5--Reports

5.1 General.
5.2 Preparation of report.
5.2.1 Phase I reports.
5.2.2 Phase II reports.

                                 Tables

Table
1 Size classification.
2 Hazard potential classification.
3 Hydrologic evaluation guidelines.
4 Factors of safety (embankment dams).

                                 Figures

Fig.
1 Seismic zone map of contiguous States.
2 Seismic zone map of California, Nevada and Arizona.
3 Seismic zone map of Alaska.
4 Seismic zone map of Hawaii.
5 Design envelope for Case I (Table 4).
6 Design envelope for Cases II and III (Table 4).

                               Appendixes

Appendix I to App. D--Engineering data
Appendix II to App. D--Inspection items
Appendix III to App. D--Pub. L. 92-367

                         Chapter 1--Introduction

    1.1. Purpose. This document provides recommended guidelines for the 
inspection and evaluation of dams to determine if they constitute 
hazards to human life or property.
    1.2. Applicability. The procedures and guidelines outlined in this 
document apply to the inspection and evaluation of all dams as defined 
in the National Dam Inspection Act, Public Law 92-367. Included in this 
program are all artificial barriers together with appurtenant works 
which impound or divert water and which (1) are twenty-five feet or more 
in height or (2) have an impounding capacity of fifty acre-feet or more. 
Not included are barriers which are six feet or less in height, 
regardless of storage capacity, or barriers which have a storage 
capacity at maximum water storage elevation of fifteen acre-feet or less 
regardless of height.
    1.3. Authority. The Dam Inspection Act, Public Law 92-367 (Appendix 
III), authorized the Secretary of the Army, through the Corps of 
Engineers, to initiate a program of safety inspection of dams throughout 
the United States. The Chief of Engineers issues these guidelines 
pursuant to that authority.

                     Chapter 2--General Requirements

    2.1. Classification of dams. Dams should be classified in accordance 
with size and hazard potential in order to formulate a priority basis 
for selecting dams to be included in the inspection program and also to 
provide compatibility between guideline requirements and involved risks. 
When possible the initial classifications should be based upon 
information listed in the National Inventory of Dams with respect to 
size, impoundment capacity and hazard potential. It may be necessary to 
reclassify dams when additional information becomes available.
    2.1.1. Size. The classification for size based on the height of the 
dam and storage capacity should be in accordance with Table 1. The 
height of the dam is established with respect to the maximum storage 
potential measured from the natural bed of the stream or watercourse at 
the downstream toe of the barrier, or if it is not across a stream or 
watercourse, the height from the lowest elevation of the outside limit 
of the barrier, to the maximum water storage elevation. For the purpose 
of determining project size, the maximum storage elevation may be 
considered equal to the top of dam elevation. Size classification may be 
determined by either storage or height, whichever gives the larger size 
category.

                      Table 1--Size Classification
------------------------------------------------------------------------
                                                Impoundment
            Category             ---------------------------------------
                                    Storage (ac-ft)       Height (ft)
------------------------------------------------------------------------
Small...........................  <1,000 and =50.             eq>=25.
Intermediate....................  =1,000   =40 and
                                   and <50,000.        <100.
Large...........................  =50,000  =100.
------------------------------------------------------------------------

    2.1.2. Hazard Potential. The classification for potential hazards 
should be in accordance with Table 2. The hazards pertain to potential 
loss of human life or property damage in the area downstream of the dam 
in event of failure or misoperation of the dam or appurtenant 
facilities. Dams conforming to criteria for the low hazard potential 
category generally will be located in rural or agricultural areas where 
failure may damage farm buildings, limited agricultural land, or 
township and country roads. Significant hazard potential category 
structures will be those located in predominantly rural or agricultural 
areas where failure may damage isolated homes, secondary highways or 
minor railroads or cause interruption of use or service of relatively 
important public utilities. Dams in the high hazard potential category 
will be those located where failure may cause serious damage to homes, 
extensive agricultural, industrial and commercial facilities, important 
public utilities, main highways, or railroads.

[[Page 287]]



                                    Table 2--Hazard Potential Classification
----------------------------------------------------------------------------------------------------------------
                                               Loss of life (extent of             Economic loss (extent of
                Category                             development)                        development)
----------------------------------------------------------------------------------------------------------------
Low....................................  None expected (No permanent          Minimal (Undeveloped to occasional
                                          structures for human habitation).    structures or agriculture).
Significant............................  Few (No urban developments and no    Appreciable (Notable agriculture,
                                          more than a small number of          industry or structures).
                                          inhabitable structures).
High...................................  More than few......................  Excessive (Extensive community,
                                                                               industry or agriculture).
----------------------------------------------------------------------------------------------------------------

    2.2. Selection of dams to be investigated. The selection of dams to 
be investigated should be based upon an assessment of existing 
developments in flood hazard areas. Those dams possessing a hazard 
potential classified high or significant as indicated in Table 2 should 
be given first and second priorities, respectively, in the inspection 
program. Inspection priorities within each category may be developed 
from a consideration of factors such as size classification and age of 
the dam, the population size in the downstream flood area, and potential 
developments anticipated in flood hazard areas.
    2.3. Technical Investigations. A detailed, systematic, technical 
inspection and evaluation should be made of each dam selected for 
investigation in which the hydraulic and hydrologic capabilities, 
structural stability and operational adequacy of project features are 
analyzed and evaluated to determine if the dam constitutes a danger to 
human life or property. The investigation should vary in scope and 
completeness depending upon the availability and suitability of 
engineering data, the validity of design assumptions and analyses and 
the condition of the dam. The minimum investigation will be designated 
Phase I, and an in-depth investigation designated Phase II should be 
made where deemed necessary. Phase I investigations should consist of a 
visual inspection of the dam, abutments and critical appurtenant 
structures, and a review of readily available engineering data. It is 
not intended to perform costly explorations or analyses during Phase I. 
Phase II investigations should consist of all additional engineering 
investigations and analyses found necessary by results of the Phase I 
investigation.
    2.4. Qualifications of investigators. The technical investigations 
should be conducted under the direction of licensed professional 
engineers experienced in the investigation, design, construction and 
operation of dams, applying the disciplines of hydrologic, hydraulic, 
soils and structural engineering and engineering geology. All field 
inspections should be conducted by qualified engineers, engineering 
geologists and other specialists, including experts on mechanical and 
electrical operation of gates and controls, knowledgeable in the 
investigation, design, construction and operation of dams.

                    Chapter 3--Phase I Investigation

    3.1. Purpose. The primary purpose of the Phase I investigation 
program is to identify expeditiously those dams which may pose hazards 
to human life or property.
    3.2. Scope. The Phase I investigation will develop an assessment of 
the general condition with respect to safety of the project based upon 
available data and a visual inspection, determine any need for emergency 
measures and conclude if additional studies, investigation and analyses 
are necessary and warranted. A review will be made of pertinent existing 
and available engineering data relative to the design, construction and 
operation of the dam and appurtenant structures, including electrical 
and mechanical operating equipment and measurements from inspection and 
performance instruments and devices; and a detailed systematic visual 
inspection will be performed of those features relating to the stability 
and operational adequacy of the project. Based upon findings of the 
review of engineering data and the visual inspection, an evaluation will 
be made of the general condition of the dam, including where possible 
the assessment of the hydraulic and hydrologic capabilities and the 
structural stability.
    3.3. Engineering data. To the extent feasible the engineering data 
listed in Appendix I relating to the design, construction and operation 
of the dam and appurtenant structures, should be collected from existing 
records and reviewed to aid in evaluating the adequacy of hydraulic and 
hydrologic capabilities and stability of the dam. Where the necessary 
engineering data are unavailable, inadequate or invalid, a listing 
should be made of those specific additional data deemed necessary by the 
engineer in charge of the investigation and included in the Phase I 
report.
    3.4. Field inspections. The field inspection of the dam, appurtenant 
stuctures, reservoir area, and downstream channel in the vicinity of the 
dam should be conducted in a systematic manner to minimize the 
possibility of any significant feature being overlooked. A detailed 
checklist should be developed and followed for each dam inspected to 
document

[[Page 288]]

the examination of each significant structural and hydraulic feature 
including electrical and mechanical equipment for operation of the 
control facilities that affect the safety of the dam.
    3.4.1. Particular attention should be given to detecting evidence of 
leakage, erosion, seepage, slope instability, undue settlement, 
displacement, tilting, cracking, deterioration, and improper functioning 
of drains and relief wells. The adequacy and quality of maintenance and 
operating procedures as they pertain to the safety of the dam and 
operation of the control facilities should also be assessed.
    3.4.2. Photographs and drawings should be used freely to record 
conditions in order to minimize descriptions.
    3.4.3. The field inspection should include appropriate features and 
items, including but not limited to those listed in Appendix II, which 
may influence the safety of the dam or indicate potential hazards to 
human life or property.
    3.5. Evaluation of hydraulic and hydrologic Features.
    3.5.1. Design data. Original hydraulic and hydrologic design 
assumptions obtained from the project records should be assessed to 
determine their acceptability in evaluating the safety of the dam. All 
constraints on water control such as blocked entrances, restrictions on 
operation of spillway and outlet gates, inadequate energy dissipators or 
restrictive channel conditions, significant reduction in reservoir 
capacity by sediment deposits and other factors should be considered in 
evaluating the validity of discharge ratings, storage capacity, 
hydrographs, routings and regulation plans. The discharge capacity and/
or storage capacity should be capable of safely handling the recommended 
spillway design flood for the size and hazard potential classification 
of the dam as indicated in Table 3. The hydraulic and hydrologic 
determinations for design as obtained from project records will be 
acceptable if conventional techniques similar to the procedures outlined 
in paragraph 4.3. were used in obtaining the data. When the project 
design flood actually used exceeds the recommended spillway design 
flood, from Table 3, the project design flood will be acceptable in 
evaluating the safety of the dam.

                Table 3--Hydrologic Evaluation Guidelines
                  [Recommended spillway design floods]
------------------------------------------------------------------------
                                                        Spillway design
             Hazard                      Size           flood (SDF) \1\
------------------------------------------------------------------------
Low.............................  Small.............  50 to 100-yr
                                                       frequency.
                                  Intermediate......  100-yr to \1/2\
                                                       PMF.
                                  Large.............  \1/2\ PMF to PMF.
Significant.....................  Small.............  100-yr to \1/2\
                                                       PMF.
                                  Intermediate......  \1/2\ PMF to PMF.
                                  Large.............  PMF.
High............................  Small.............  \1/2\ PMF to PMF.
                                  Intermediate......  PMF.
                                  Large.............  PMF.
------------------------------------------------------------------------
\1\ The recommended design floods in this column represent the magnitude
  of the spillway design flood (SDF), which is intended to represent the
  largest flood that need be considered in the evaluation of a given
  project, regardless of whether a spillway is provided; i.e., a given
  project should be capable of safely passing the appropriate SDF. Where
  a range of SDF is indicated, the magnitude that most closely relates
  to the involved risk should be selected.

1000-yr=100-Year Exceedence Interval. The flood magnitude expected to be 
exceeded, on the average, of once in 100 years. It may also be expressed 
as an exceedence frequency with a one-percent chance of being exceeded 
in any given year.
PMF=Probable Maximum Flood. The flood that may be expected from the most 
severe combination of critical meteorologic and hydrologic conditions 
that are reasonably possible in the region. The PMF is derived from 
probable maximum precipitation (PMP), which information is generally 
available from the National Weather Service, NOAA. Most Federal agencies 
apply reduction factors to the PMP when appropriate. Reductions may be 
applied because rainfall isohyetals are unlikely to conform to the exact 
shape of the drainage basin and/or the storm is not likely to center 
exactly over the drainage basin. In some cases local topography will 
cause changes from the generalized PMP values, therefore it may be 
advisable to contact Federal construction agencies to obtain the 
prevailing practice in specific areas.
    3.5.2. Experience data. In some cases where design data are lacking, 
an evaluation of overtopping potential may be based on watershed 
characteristics and rainfall and reservoir records. An estimate of the 
probable maximum flood may also be developed from a conservative, 
generalized comparison of the drainage area size and the magnitude of 
recently adopted probable maximum floods for damsites in comparable 
hydrologic regions. Where the review of such experience data indicates 
that the recommended spillway design flood would not cause overtopping 
additional hydraulic and hydrologic determinations will be unnecessary.
    3.6. Evaluation of structural stability. The Phase I evaluations of 
structural adequacy of project features are expected to be based 
principally on existing conditions as revealed by the visual inspection, 
together with available design and construction information and records 
of performance. The objectives are to determine the existence of 
conditions which are hazardous, or which with time might develop into 
safety hazards,

[[Page 289]]

and to formulate recommendations pertaining to the need for any 
additional studies, investigations, or analyses. The results of this 
phase of the inspection must rely very substantially upon the experience 
and judgment of the inspecting engineer.
    3.6.1. Design and construction data. The principal design 
assumptions and analyses obtained from the project records should be 
assessed. Original design and construction records should be used 
judiciously, recognizing the restricted applicability of such data as 
material strengths and permeabilities, geological factors and 
construction descriptions. Original stability studies and analyses 
should be acceptable if conventional techniques and procedures similar 
to those outlined in paragraph 4.4 were employed, provided that review 
of operational and performance data confirm that the original design 
assumptions were adequately conservative. The need for such analyses 
where either none exist or the originals are incomplete or 
unsatisfactory will be determined by the inspecting engineer based upon 
other factors such as condition of structures, prior maximum loadings 
and the hazard degree of the project. Design assumptions and analyses 
should include all applicable loads including earthquake and indicate 
the structure's capability to resist overturning, sliding and 
overstressing with adequate factors of safety. In general seepage and 
stability analyses comparable to the requirements of paragraph 4.4 
should be on record for all dams in the high hazard category and large 
dams in the significant hazard category. This requirement for other dams 
will be subject to the opinion of the inspecting engineer.
    3.6.2. Operating records. The performance of structures under prior 
maximum loading conditions should in some instances provide partial 
basis for stability evaluation. Satisfactory experience under loading 
conditions not expected to be exceeded in the future should generally be 
indicative of satisfactory stability, provided adverse changes in 
physical conditions have not occurred. Instrumentation observations of 
forces, pressures, loads, stresses, strains, displacements, deflections 
or other related conditions should also be utilized in the safety 
evaluation. Where such data indicate abnormal behavior, unsafe movement 
or deflections, or loadings which adversely affect the stability or 
functioning of the structure, prompt reporting of such circumstances is 
required without the delay for preparation of the official inspection 
report.
    3.6.3. Post construction changes. Data should be collected on 
changes which have occurred since project construction that might 
influence the safety of the dam such as road cuts, quarries, mining and 
groundwater changes.
    3.6.4. Seismic stability. An assessment should be made of the 
potential vulnerability of the dam to seismic events and a 
recommendation developed with regard to the need for additional seismic 
investigation. In general, projects located in Seismic Zones 0, 1 and 2 
may be assumed to present no hazard from earthquake provided static 
stability conditions are satisfactory and conventional safety margins 
exist. Dams in Zones 3 and 4 should, as a minimum, have on record 
suitable analyses made by conventional equivalent static load methods. 
The seismic zones together with appropriate coefficients for use in such 
analyses are shown in Figures 1 through 4. Boundary lines are 
approximate and in the event of doubt about the proper zone, the higher 
zone should be used. All high hazard category dams in Zone 4 and high 
hazard dams of the hydraulic fill type in Zone 3 should have a stability 
assessment based upon knowledge of regional and local geology, 
engineering seismology, in situ properties of materials and appropriate 
dynamic analytical and testing procedures. The assessment should include 
the possibility of physical displacement of the structures due to 
movements along active faults. Departure from this general guidance 
should be made whenever in the judgment of the investigating engineer 
different seismic stability requirements are warranted because of local 
geological conditions or other reasons.

                    Chapter 4--Phase II Investigation

    4.1. Purpose. The Phase II investigation will be supplementary to 
Phase I and should be conducted when the results of the Phase I 
investigation indicate the need for additional in-depth studies, 
investigations or analyses.
    4.2. Scope. The Phase II investigation should include all additional 
studies, investigations and analyses necessary to evaluate the safety of 
the dam. Included, as required, will be additional visual inspections, 
measurements, foundation exploration and testing, materials testing, 
hydraulic and hydrologic analysis and structural stability analyses.
    4.3. Hydraulic and hydrologic analysis. Hydraulic and hydrologic 
capabilities should be determined using the following criteria and 
procedures. Depending on the project characteristics, either the 
spillway design flood peak inflow or the spillway design flood 
hydrograph should be the basis for determining the maximum water surface 
elevation and maximum outflow. If the operation or failure of upstream 
water control projects would have significant impact on peak flow or 
hydrograph analyses, the impact should be assessed.
    4.3.1. Maximum water surface based on SDF peak inflow. When the 
total project discharge capability at maximum pool exceeds the peak 
inflow of the recommended SDF, and

[[Page 290]]

operational constraints would not prevent such a release at controlled 
projects, a reservoir routing is not required. The maximum discharge 
should be assumed equal to the peak inflow of the spillway design flood. 
Flood volume is not controlling in this situation and surcharge storage 
is either absent or is significant only to the extent that it provides 
the head necessary to develop the release capability required.
    4.3.1.1. Peak for 100-year flood. When the 100-year flood is 
applicable under the provisions of Table 3 and data are available, the 
spillway design flood peak inflow may be determined by use of ``A 
Uniform Technique for Determining Flood Frequencies,'' Water Resources 
Council (WRC), Hydrology Committee, Bulletin 15, December 1967. Flow 
frequency information from regional analysis is generally preferred over 
single station results when available and appropriate. Rainfall-runoff 
techniques may be necessary when there are inadequate runoff data 
available to make a reasonable estimate of flow frequency.
    4.3.1.2. Peak for PMF or fraction thereof. When either the Probable 
Maximum Flood peak or a fraction thereof is applicable under the 
provisions of Table 3, the unit hydrograph--infiltration loss technique 
is generally the most expeditious method of computing the spillway 
design flood peak for most projects. This technique is discussed in the 
following paragraph.
    4.3.2. Maximum water surface based on SDF hydrograph. Both peak and 
volume are required in this analysis. Where surcharge storage is 
significant, or where there is insufficient discharge capability at 
maximum pool to pass the peak inflow of the SDF, considering all 
possible operational constraints, a flood hydrograph is required. When 
there are upstream hazard areas that would be imperiled by fast rising 
reservoirs levels, SDF hydrographs should be routed to ascertain 
available time for warning and escape. Determination of probable maximum 
precipitation or 100-year precipitation, which ever is applicable, and 
unit hydrographs or runoff models will be required, followed by the 
determination of the PMF or 100-year flood. Conservative loss rates 
(significantly reduced by antecedent rainfall conditions where 
appropriate) should be estimated for computing the rainfall excess to be 
utilized with unit hydrographs. Rainfall values are usually arranged 
with gradually ascending and descending rates with the maximum rate late 
in the storm. When applicable, conservatively high snowmelt runoff rates 
and appropriate releases from upstream projects should be assumed. The 
PMP may be obtained from National Weather Service (NWS) publications 
such as Hydrometeorological Report (HMR) 33. Special NWS publications 
for particular areas should be used when available. Rainfall for the 
100-year frequency flood can be obtained from the NWS publication 
``Rainfall Frequency Atlas of the United States,'' Technical Paper No. 
40; Atlas 2, ``Precipitation Frequency Atlas of Western United States;'' 
or other NWS publications. The maximum water surface elevation and 
spillway design flood outflow are then determined by routing the inflow 
hydrograph through the reservoir surcharge storage, assuming a starting 
water surface at the bottom of surcharge storage, or lower when 
appropriate. For projects where the bottom of surcharge space is not 
distinct, or the flood control storage space (exclusive of surcharge) is 
appreciable, it may be appropriate to select starting water surface 
elevations below the top of the flood control storage for routings. 
Conservatively high starting levels should be estimated on the basis of 
hydrometeorological conditions reasonably characteristic for the region 
and flood release capability of the project. Necessary adjustment of 
reservoir storage capacity due to existing or future sediment or other 
encroachment may be approximated when accurate determination of 
deposition is not practicable.
    4.3.3. Acceptable procedures. Techniques for performing hydraulic 
and hydrologic analyses are generally available from publications 
prepared by Federal agencies involved in water resources development or 
textbooks written by the academic community. Some of these procedures 
are rather sophisticated and require expensive computational equipment 
and large data banks. While results of such procedures are generally 
more reliable than simplified methods, their use is generally not 
warranted in studies connected with this program unless they can be 
performed quickly and inexpensively. There may be situations where the 
more complex techniques have to be employed to obtain reliable results; 
however, these cases will be exceptions rather than the rule. Whenever 
the acceptability of procedures is in question, the advice of competent 
experts should be sought. Such expertise is generally available in the 
Corps of Engineers, Bureau of Reclamation and Soil Conservation Service. 
Many other agencies, educational facilities and private consultants can 
also provide expert advice. Regardless of where such expertise is based, 
the qualification of those individuals offering to provide it should be 
carefully examined and evaluated.
    4.3.4. Freeboard allowances. Guidelines on specific minimum 
freeboard allowances are not considered appropriate because of the many 
factors involved in such determinations. The investigator will have to 
assess the critical parameters for each project and develop its minimum 
requirement. Many projects are reasonably safe without freeboard 
allowance because they are designed for overtopping, or other factors 
minimize possible overtopping. Conversely,

[[Page 291]]

freeboard allowances of several feet may be necessary to provide a safe 
condition. Parameters that should be considered include the duration of 
high water levels in the reservoir during the design flood; the 
effective wind fetch and reservoir depth available to support wave 
generation; the probability of high wind speed occurring from a critical 
direction; the potential wave runup on the dam based on roughness and 
slope; and the ability of the dam to resist erosion from overtopping 
waves.
    4.4 Stability investigations. The Phase II stability investigations 
should be compatible with the guidelines of this paragraph.
    4.4.1 Foundation and material investigations. The scope of the 
foundation and materials investigation should be limited to obtaining 
the information required to analyze the structural stability and to 
investigate any suspected condition which would adversely affect the 
safety of the dam. Such investigations may include borings to obtain 
concrete, embankment, soil foundation, and bedrock samples; testing 
specimens from these samples to determine the strength and elastic 
parameters of the materials, including the soft seams, joints, fault 
gouge and expansive clays or other critical materials in the foundation; 
determining the character of the bedrock including joints, bedding 
planes, fractures, faults, voids and caverns, and other geological 
irregularities; and installing instruments for determining movements, 
strains, suspected excessive internal seepage pressures, seepage 
gradients and uplift forces. Special investigations may be necessary 
where suspect rock types such as limestone, gypsum, salt, basalt, 
claystone, shales or others are involved in foundations or abutments in 
order to determine the extent of cavities, piping or other deficiencies 
in the rock foundation. A concrete core drilling program should be 
undertaken only when the existence of significant structural cracks is 
suspected or the general qualitative condition of the concrete is in 
doubt. The tests of materials will be necessary only where such data are 
lacking or are outdated.
    4.4.2. Stability assessment. Stability assessments should utilize in 
situ properties of the structure and its foundation and pertinent 
geologic information. Geologic information that should be considered 
includes groundwater and seepage conditions; lithology, stratigraphy, 
and geologic details disclosed by borings, ``as-built'' records, and 
geologic interpretation; maximum past overburden at site as deduced from 
geologic evidence; bedding, folding and faulting; joints and joint 
systems; weathering; slickensides, and field evidence relating to 
slides, faults, movements and earthquake activity. Foundations may 
present problems where they contain adversely oriented joints, 
slickensides or fissured material, faults, seams of soft materials, or 
weak layers. Such defects and excess pore water pressures may contribute 
to instability. Special tests may be necessary to determine physical 
properties of particular materials. The results of stability analyses 
afford a means of evaluating the structure's existing resistance to 
failure and also the effects of any proposed modifications. Results of 
stability analyses should be reviewed for compatibility with performance 
experience when possible.
    4.4.2.1. Seismic stability. The inertial forces for use in the 
conventional equivalent static force method of analysis should be 
obtained by multiplying the weight by the seismic coefficient and should 
be applied as a horizontal force at the center of gravity of the section 
or element. The seismic coefficients suggested for use with such 
analyses are listed in Figures 1 through 4. Seismic stability 
investigations for all high hazard category dams located in Seismic Zone 
4 and high hazard dams of the hydraulic fill type in Zone 3 should 
include suitable dynamic procedures and analyses. Dynamic analyses for 
other dams and higher seismic coefficients are appropriate if in the 
judgment of the investigating engineer they are warranted because of 
proximity to active faults or other reasons. Seismic stability 
investigations should utilize ``state-of-the-art'' procedures involving 
seismological and geological studies to establish earthquake parameters 
for use in dynamic stability analyses and, where appropriate, the 
dynamic testing of materials. Stability analyses may be based upon 
either time-history or response spectra techniques. The results of 
dynamic analyses should be assessed on the basis of whether or not the 
dam would have sufficient residual integrity to retain the reservoir 
during and after the greatest or most adverse earthquake which might 
occur near the project location.
    4.4.2.2. Clay shale foundation. Clay shale is a highly 
overconsolidated sedimentary rock comprised predominantly of clay 
minerals, with little or no cementation. Foundations of clay shales 
require special measures in stability investigations. Clay shales, 
particularly those containing montmorillonite, may be highly susceptible 
to expansion and consequent loss of strength upon unloading. The shear 
strength and the resistance to deformation of clay shales may be quite 
low and high pore water pressures may develop under increase in load. 
The presence of slickensides in clay shales is usually an indication of 
low shear strength. Prediction of field behavior of clay shales should 
not be based solely on results of conventional laboratory tests since 
they may be misleading. The use of peak shear strengths for clay shales 
in stability analyses may be unconservative because of nonuniform stress 
distribution and possible progressive failures. Thus the available shear 
resistance may be less than if the peak shear strength

[[Page 292]]

were mobilized simultaneously along the entire failure surface. In such 
cases, either greater safety factors or residual shear strength should 
be used.
    4.4.3. Embankment dams.
    4.4.3.1. Liquefaction. The phenomenon of liquefaction of loose, 
saturated sands and silts may occur when such materials are subjected to 
shear deformation or earthquake shocks. The possibility of liquefaction 
must presently be evaluated on the basis of empirical knowledge 
supplemented by special laboratory tests and engineering judgment. The 
possiblitity of liquefaction in sands diminishes as the relative density 
increases above approximately 70 percent. Hydraulic fill dams in Seismic 
Zones 3 and 4 should receive particular attention since such dams are 
susceptible to liquefaction under earthquake shocks.
    4.4.3.2. Shear failure. Shear failure is one in which a portion of 
an embankment or of an embankment and foundation moves by sliding or 
rotating relative to the remainder of the mass. It is conventionally 
represented as occurring along a surface and is so assumed in stability 
analyses, although shearing may occur in a zone of substantial 
thickness. The circular arc or the sliding wedge method of analyzing 
stability, as pertinent, should be used. The circular arc method is 
generally applicable to essentially homogeneous embankments and to soil 
foundations consisting of thick deposits of fine-grained soil containing 
no layers significantly weaker than other strata in the foundation. The 
wedge method is generally applicable to rockfill dams and to earth dams 
on foundations containing weak layers. Other methods of analysis such as 
those employing complex shear surfaces may be appropriate depending on 
the soil and rock in the dam and foundation. Such methods should be in 
reputable usage in the engineering profession.
    4.4.3.3. Loading conditions. The loading conditions for which the 
embankment structures should be investigated are (I) Sudden drawdown 
from spillway crest elevation or top of gates, (II) Partial pool, (III) 
Steady state seepage from spillway crest elevation or top of gate 
elevation, and (IV) Earthquake. Cases I and II apply to upstream slopes 
only; slopes; and Case IV applies to both upstream and downstream Case 
III applies to downstream slopes. A summary of suggested strengths and 
safety factors are shown in Table 4.

                                          Table 4--Factors of Safety\1\
----------------------------------------------------------------------------------------------------------------
                                           Factor
       Case and loading condition            of         Shear \2\ strength                   Remarks
                                           safety
----------------------------------------------------------------------------------------------------------------
I Sudden drawdown from spillway crest or  \3\ 1.2  Minimum composite of R and   Within the drawdown zone
 top of gates to minimum drawdown                   S shear strengths. See       submerged unit weights of
 elevation.                                         Figure 5.                    materials are used for
                                                                                 computing forces resisting
                                                                                 sliding and saturated unit
                                                                                 weights are used for computing
                                                                                 forces contributing to sliding.
II Partial pool with assumed horizontal       1.5  R+S/2 for RS........   of R and
                                                                                 S shear strengths. See Figure
                                                                                 6.
III Steady seepage from spillway crest        1.5  Same as Case II............
 or top of gates with Kh/Kv=9 assumed\4\.
IV Earthquake (Cases II and III with          1.0  (\5\ ).....................  See Figures 1 through 4 for
 seismic loading).                                                               Seismic Coefficients.
----------------------------------------------------------------------------------------------------------------
\1\ Not applicable to embankments on clay shale foundation. Experience has indicated special problems in
  determination of design shear strengths for clay shale foundations and acceptable safety factors should be
  compatible with the confidence level in shear strength assumptions.
\2\ Other strength assumptions may be used if in common usage in the engineering profession.
\3\ The safety factor should not be less than 1.5 when drawdown rate and pore water pressure developed from flow
  nets are used in stability analyses.
\4\ Kh/Kv is the ratio of horizontal to vertical permeability. A minimum of 9 is suggested for use in compacted
  embankments and alluvial sediments.
\5\ Use shear strength for case analyzed without earthquake. It is not necessary to analyze sudden drawdown for
  earthquake loading. Shear strength tests are classified according to the controlled drainage conditions
  maintained during the test. R tests are those in which specimen drainage is allowed during consolidation (or
  swelling) under initial stress conditions, but specimen drainage is not allowed during application of shearing
  stresses. S tests allow full drainage during initial stress application and shearing is at a slow rate so that
  complete specimen drainage is permitted during the complete test.

    4.4.3.4. Safety factors. Safety factors for embankment dam stability 
studies should be based on the ratio of available shear strength to 
developed shear strength, SD :
[GRAPHIC] [TIFF OMITTED] TC15NO91.000

Where:

C=Cohesion
[phis]=Angle of internal friction
[sigma]=Normal stress

    The factors of safety listed in Table 4 are recommended as minimum 
acceptable. Final accepted factors of safety should depend upon the 
degree of confidence the investigating engineer has in the engineering 
data

[[Page 293]]

available to him. The consequences of a failure with respect to human 
life and property damage are important considerations in establishing 
factors of safety for specific investigations.
    4.4.3.5. Seepage failure. A critical uncontrolled underseepage or 
through seepage condition that develops during a rising pool can quickly 
reduce a structure which was stable under previous conditions, to a 
total structural failure. The visually confirmed seepage conditions to 
be avoided are (1) the exit of the phreatic surface on the downstream 
slope of the dam and (2) development of hydrostatic heads sufficient to 
create in the area downstream of the dam sand boils that erode materials 
by the phenomenon known as ``piping'' and (3) localized concentrations 
of seepage along conduits or through pervious zones. The dams most 
susceptible to seepage problems are those built of or on pervious 
materials of uniform fine particle size, with no provisions for an 
internal drainage zone and/or no underseepage controls.
    4.4.3.6. Seepage analyses. Review and modifications to original 
seepage design analyses should consider conditions observed in the field 
inspection and piezometer instrumentation. A seepage analysis should 
consider the permeability ratios resulting from natural deposition and 
from compaction placement of materials with appropriate variation 
between horizontal and vertical permeability. An underseepage analysis 
of the embankment should provide a critical gradient factor of safety 
for the maximum head condition of not less than 1.5 in the area 
downstream of the embankment.
[GRAPHIC] [TIFF OMITTED] TC15NO91.001

Where:

ic=Critical gradient
i=Design gradient
H=Uplift head at downstream toe of dam measured above tailwater
Hc=The critical uplift
Db=The thickness of the top impervious blanket at the 
downstream toe of the dam
[gamma]m=The estimated saturated unit weight of the material 
in the top impervious blanket
[gamma]w=The unit weight of water

    Where a factor of safety less than 1.5 is obtained the provision of 
an underseepage control system is indicated. The factor of safety of 1.5 
is a recommended minimum and may be adjusted by the responsible engineer 
based on the competence of the engineering data.
    4.4.4. Concrete dams and appurtenant structures.
    4.4.4.1. Requirements for stability. Concrete dams and structures 
appurtenant to embankment dams should be capable of resisting 
overturning, sliding and overstressing with adequate factors of safety 
for normal and maximum loading conditions.
    4.4.4.2. Loads. Loadings to be considered in stability analyses 
include the water load on the upstream face of the dam; the weight of 
the structure; internal hydrostatic pressures (uplift) within the body 
of the dam, at the base of the dam and within the foundation; earth and 
silt loads; ice pressure, seismic and thermal loads, and other loads as 
applicable. Where tailwater or backwater exists on the downstream side 
of the structure it should be considered, and assumed uplift pressures 
should be compatible with drainage provisions and uplift measurements if 
available. Where applicable, ice pressure should be applied to the 
contact surface of the structure of normal pool elevation. A unit 
pressure of not more than 5,000 pounds per square foot should be used. 
Normally, ice thickness should not be assumed greater than two feet. 
Earthquake forces should consist of the inertial forces due to the 
horizontal acceleration of the dam itself and hydrodynamic forces 
resulting from the reaction of the reservoir water against the 
structure. Dynamic water pressures for use in a conventional methods of 
analysis may be computed by means of the ``Westergaard Formula'' using 
the parabolic approximation (H.M. Westergaard, ``Water Pressures on Dams 
During Earthquakes,'' Trans., ASCE, Vol 98, 1933, pages 418-433), or 
similar method.
    4.4.4.3. Stresses. The analysis of concrete stresses should be based 
on in situ properties of the concrete and foundation. Computed maximum 
compressive stresses for normal operating conditions in the order of \1/
3\ or less of in situ strengths should be satisfactory. Tensile stresses 
in unreinforced concrete should be acceptable only in locations where 
cracks will not adversely affect the overall performance and stability 
of the structure. Foundation stresses should be such as to provide 
adequate safety against failure of the foundation material under all 
loading conditions.
    4.4.4.4. Overturning. A gravity structure should be capable of 
resisting all overturning forces. It can be considered safe against 
overturning if the resultant of all combinations of horizontal and 
vertical forces, excluding earthquake forces, acting above any 
horizontal plane through the structure or at its base is located within 
the middle third of the section. When earthquake is included the 
resultant should fall within the limits of the plane or base, and 
foundation pressures must be acceptable. When these requirements for 
location of the resultant are not satisfied the investigating engineer 
should assess the importance to stability of the deviations.
    4.4.4.5. Sliding. Sliding of concrete gravity structures and of 
abutment and foundation rock masses for all types of concrete dams

[[Page 294]]

should be evaluated by the shear-friction resistance concept. The 
available sliding resistance is compared with the driving force which 
tends to induce sliding to arrive at a sliding stability safety factor. 
The investigation should be made along all potential sliding paths. The 
critical path is that plane or combination of planes which offers the 
least resistance.
    4.4.4.5.1. Sliding resistance. Sliding resistance is a function of 
the unit shearing strength at no normal load (cohesion) and the angle of 
friction on a potential failure surface. It is determined by computing 
the maximum horizontal driving force which could be resisted along the 
sliding path under investigation. The following general formula is 
obtained from the principles of statics and may be derived by resolving 
forces parallel and perpendicular to the sliding plane:
[GRAPHIC] [TIFF OMITTED] TC15NO91.002

Where:

RR=Sliding Resistance (maximum horizontal driving force which 
can be resisted by the critical path)
[phis]=Angle of internal friction of foundation material or, where 
applicable, angle of sliding friction
V=Summation of vertical forces (including uplift)
c=Unit shearing strength at zero normal loading along potential failure 
plane
A=Area of potential failure plane developing unit shear strength ``c''
[alpha]=Angle between inclined plane and horizontal (positive for uphill 
sliding)

    For sliding downhill the angle [alpha] is negative and Equation (1) 
becomes:
[GRAPHIC] [TIFF OMITTED] TC15NO91.003

    When the plane of investigation is horizontal, and the angle [alpha] 
is zero and Equation (1) reduced to the following:
[GRAPHIC] [TIFF OMITTED] TC15NO91.004

    4.4.4.5.2. Downstream esistance. When the base of a concrete 
structure is embedded in rock or the potential failure plane lies below 
the base, the passive resistance of the downstream layer of rock may 
sometimes be utilized for sliding resistance. Rock that may be subjected 
to high velocity water scouring should not be used. The magnitude of the 
downstream resistance is the lesser of (a) the shearing resistance along 
the continuation of the potential sliding plane until it daylights or 
(b) the resistance available from the downstream rock wedge along an 
inclined plane. The theoretical resistance offered by the passive wedge 
can be computed by a formula equivalent to formula (3):
[GRAPHIC] [TIFF OMITTED] TC15NO91.005

Where:

Pp=Passive resistance of rock wedge
W=Weight (buoyant weight if applicable) of downstream rock wedge above 
inclined plane of resistance, plus any superimposed loads
[phis]=Angle of internal friction or, if applicable, angle of sliding 
friction
[alpha]=Angle between inclined failure plane and horizontal
c=Unit shearing strength at zero normal load along failure plane
A=Area of inclined plane of resistance

    When considering cross-bed shear through a relatively shallow, 
competent rock strut, without adverse jointing or faulting, W and 
[alpha] may be taken at zero and 45[deg], respectively, and an estimate 
of passive wedge resistance

[[Page 295]]

per unit width obtained by the following equation:
[GRAPHIC] [TIFF OMITTED] TC15NO91.006

Where:

D=Thickness of the rock strut

    4.4.4.5.3. Safety factor. The shear-friction safety factor is 
obtained by dividing the resistance RR by H, the summation of 
horizontal service loads to be applied to the structure:
[GRAPHIC] [TIFF OMITTED] TC15NO91.007

    When the downstream passive wedge contributes to the sliding 
resistance, the shear friction safety factor formula becomes:
[GRAPHIC] [TIFF OMITTED] TC15NO91.008

    The above direct superimposition of passive wedge resistance is 
valid only if shearing rigidities of the foundation components are 
similar. Also, the compressive strength and buckling resistance of the 
downstream rock layer must be sufficient to develop the wedge 
resistance. For example, a foundation with closely spaced, near 
horizontal, relatively weak seams might not contain sufficient buckling 
strength to develop the magnitude of wedge resistance computed from the 
cross-bed shear strength. In this case wedge resistance should not be 
assumed without resorting to special treatment (such as installing 
foundation anchors). Computed sliding safety factors approximating 3 or 
more for all loading conditions without earthquake, and 1.5 including 
earthquake, should indicate satisfactory stability, depending upon the 
reliability of the strength parameters used in the analyses. In some 
cases when the results of comprehensive foundation studies are 
available, smaller safety factors may be acceptable. The selection of 
shear strength parameters should be fully substantiated. The bases for 
any assumptions; the results of applicable testing, studies and 
investigations; and all pre-existing, pertinent data should be reported 
and evaluated.

                           Chapter 5--Reports

    5.1. General. This chapter outlines the procedures for reporting the 
results of the technical investigations. Hazardous conditions should be 
reported immediately upon detection to the owner of the dam, the 
Governor of the State in which the dam is located and the appropriate 
regulatory agency without delay for preparation of the formal report.
    5.2. Preparation of report. A formal report should be prepared for 
each dam investigated for submission to the regulatory agency and the 
owner of the dam. Each report should contain the information indicated 
in the following paragraphs. The signature and registration 
identification of the professional engineer who directed the 
investigation and who was responsible for evaluation of the dam should 
be included in the report.
    5.2.1. Phase I reports. Phase I reports should contain the following 
information:
    5.2.1.1. Description of dam including regional vicinity map showing 
location and plans, elevations and sections showing the essential 
project features and the size and hazard potential classifications.
    5.2.1.2. Summary of existing engineering data, including geologic 
maps and information.
    5.2.1.3. Results of the visual inspection of each project feature 
including photographs and drawings to minimize descriptions.
    5.2.1.4. Evaluation of operational adequacy of the reservoir 
regulation plan and maintenance of the dam and operating facilities and 
features that pertain to the safety of the dam.
    5.2.1.5. Description of any warning system in effect.
    5.2.1.6. Evaluation of the hydraulic and hydrologic assumptions and 
structural stability.
    5.2.1.7. An assessment of the general condition of the dam with 
respect to safety based upon the findings of the visual inspection and 
review of engineering data. Where data on the original design indicate 
significant departure from or non-conformance with guidelines contained 
herein, the engineer-in-charge of the investigation will give his 
opinion of the significance, with regard to safety, of such factors. Any 
additional studies, investigations and analyses considered essential to 
assessment of the safety of the dam should be listed, together with an 
opinion about the urgency of such additional work.
    5.2.1.8. Indicate alternative possible remedial measures or 
revisions in operating and maintenance procedures which may (subject to 
further evaluation) correct deficiencies and hazardous conditions found 
during the investigation.
    5.2.2. Phase II reports. Phase II reports should describe the 
detailed investigations and should supplement Phase I reports. They 
should contain the following information:
    5.2.2.1. Summary of additional engineering data obtained to 
determine the hydraulic and hydrologic capabilities and/or structural 
stability.
    5.2.2.2. Results of all additional studies, investigations, and 
analyses performed.
    5.2.2.3. Technical assessment of dam safety including deficiences 
and hazardous conditions found to exist.
    5.2.2.4. Indicate alternative possible remedial measures or revision 
in maintenance and operating procedures which may (subject

[[Page 296]]

to further evaluation) correct deficiencies and hazardous conditions 
found during the investigation.
[GRAPHIC] [TIFF OMITTED] TC31OC91.017


[[Page 297]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.018


[[Page 298]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.019


[[Page 299]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.020


[[Page 300]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.021

          Appendix I to App. D to Sec.  222.6--Engineering Data

    This appendix lists engineering data which should be collected from 
project records and, to the extent available, included in the

[[Page 301]]

Phase I investigation report. The list is intended to serve as a 
checklist and not to establish rigid data requirements. Such a 
compilation should also facilitate future inspections and 
investigations. Only data readily available will be included in Phase I 
reports, but data lacking and deemed necessary for an adequate safety 
evaluation should be identified.
    1. General Project Data.
    a. Regional Vicinity Map showing the location of the dam, the 
upstream drainage area and the downstream area subject to potential 
damage due to failure of the dam and misoperation or failure of the 
operating equipment.
    b. As-Built Drawings indicating plans, elevations and sections of 
the dam and appurtenant structures including the details of the 
discharge facilities such as outlet works, limited service and emergency 
spillways, flashboards, fuse plugs and operating equipment.
    2. Hydrologic and Hydraulic Data including the following:
    a. Drainage area and basin runoff characteristics (indicating 
pending changes).
    b. Elevation of top of conservation pool or normal upper retention 
water surface elevation, as applicable (base level of any flood 
impoundment).
    c. Storage capacity including dead or inactive storage, 
corresponding to top of conservation or normal upper retention level 
(cumulative, excluding flood control and surcharge storage).
    d. Elevation of the top of flood control pool.
    e. Storage capacity of flood control zone (incremental).
    f. Elevation of maximum design pool (corresponding to top of 
surcharge storage or spillway design flood).
    g. Storage capacity of surcharge zone (incremental, above top of 
flood control pool or, above normal upper retention level if flood 
control space not provided).
    h. Height of freeboard (distance between maximum design flood water 
surface and top of dam).
    i. Elevation of top of dam (lowest point of embankment or non-
overflow structure).
    j. Elevation of crest, type, width, crest length and location of 
spillways (number, size and type of gates if controlled).
    k. Type, location, entrance and exit inverts of outlet works and 
emergency drawdown facilities (number, size and shape of conduits and 
gates, including penstocks and sluices).
    l. Location, crest elevation, description of invert and abutments 
(concrete, rock, grass, earth) and length of limited service and 
emergency spillways.
    m. Location and dscription of flashboards and fuse plugs, including 
hydraulic head (pool elevation) and other conditions required for 
breaching, along with the assumed results of breaching.
    n. Location and top elevation of dikes and floodwalls (overflow and 
non-overflow) affected by reservoir. Include information on low reaches 
of reservoir rim.
    o. Type, location, observations and records of hydrometeorological 
gages appurtenant to the project.
    p. Maximum non-damaging discharge, or negligible damage rate, at 
potential damage locations downstream.
    3. Foundation Data and Geological Features including logs of 
borings, geological maps, profiles and cross sections, and reports of 
foundation treatment.
    4. Properties of Embankments and Foundation Materials including 
results of laboratory tests, field permeability tests, construction 
control tests, and assumed design properties for materials.
    5. Concrete Properties including the source and type of aggregate, 
cement used, mix design data and the results of testing during 
construction.
    6. Electrical and Mechanical Equipment type and rating of normal and 
emergency power supplies, hoists, cranes, valves and valve operator, 
control and alarm systems and other electrical and mechanical equipment 
and systems that could affect the safe operation of the dam.
    7. Construction History including diversion scheme, construction 
sequence, pertinent construction problems, alterations, modifications 
and maintenance repairs.
    8. Water Control Plan including regulation plan under normal 
conditions and during flood events or other emergency conditions. The 
availability of dam tenders, means of communication between dam tenders 
and authority supervising water control, and method of gate operation 
(manual, automatic, or remote control) should be included. Flood warning 
systems should be described in sufficient detail to enable assessment of 
their reduction in the flood hazard potential.
    9. Operation Record.
    a. Summary of past major flood events including any experiences that 
presented a serious threat to the safety of the project or to human life 
or property. The critical project feature, date and duration of event, 
causative factor, peak inflow and outflow, maximum elevation of water 
surface, wind and wave factors if significant, issuance of alert or 
evacuation warnings and adequacy of project feature involved should be 
included in the summary of past experience of serious threat to the 
safety of the project.
    b. Records of performance observations including instrumentation 
records.
    c. List of any known deficiencies that pose a threat to the safety 
of the dam or to human life or property.

[[Page 302]]

    d. History of previous failures or deficiencies and pending remedial 
measures for correcting known deficiencies and the schedule for 
accomplishing remedial measures should be indicated.
    10. Earthquake History including a summary of the seismic data of 
significant recorded earthquakes in the vicinity of the dam and 
information on major damage in the vicinity of the dam from both 
recorded and unrecorded earthquakes. Regional geologic maps and other 
documents showing fault locations should be collected.
    11. Inspection History including the results of the last safety 
inspection, the organization that performed the inspection, the date 
inspection performed and the authority for conducting the inspection.
    12. Principal Design Assumptions and Analyses.
    a. Hydrologic and Hydraulic Determinations.
    (1) Quantity, time and area distribution, and reference source of 
depth-area-duration data of spillway design storm precipitation (point 
precipitation if applicable).
    (2) Maximum design flood inflow hydrograph including loss rates 
(initial and average for design flood conditions) and time of runoff 
concentration of reservior watershed (peak inflow only when applicable).
    (3) Maximum design flood outflow hydrograph (maximum outflow only 
when applicable).
    (4) Discharge-frequency relationship, preferably at damsite, 
including estimated frequency of spillway design flood for small dams, 
when appropriate.
    (5) Reservior area and storage capacity versus water surface 
elevation (table or curves).
    (6) Rating curves (free flow and partial gate openings) for all 
discharge facilities contributing to the maximum design flood outflow 
hydrograph. Also a composite-rating of all contributing facilities, if 
appropriate.
    (7) Tailwater rating curve immediately below damsite including 
elevation corresponding to maximum design flood discharge and 
approximate nondamaging channel capacity.
    (8) Hydrologic map of watershed above damsite including reservior 
area, watercourse, elevation contours, and principal stream-flow and 
precipitation gaging stations.
    b. Stability and Stress Analysis of the dam, spillway and 
appurtenant structures and features including the assumed properties of 
materials and all pertinent applied loads.
    c. Seepage and Settlement Analyses. The determination of 
distribution, direction and magnitude of seepage forces and the design 
and construction measures for their control. Settlement estimates and 
steps adopted to compensate for total settlement and to minimize 
differential settlements.

         Appendix II to App. D to Sec.  222.6--Inspection Items

    This appendix provides guidance for performing field inspections and 
may serve as the basis for developing a detailed checklist for each dam.
    1. Concrete Structures in General.
    a. Concrete Surfaces. The condition of the concrete surfaces should 
be examined to evaluate the deterioration and continuing serviceability 
of the concrete. Descriptions of concrete conditions should conform with 
the appendix to ``Guide for Making a Condition Survey of Concrete in 
Service,'' American Concrete Institute (ACI) Journal, Proceedings Vol. 
65, No. 11, November 1968, page 905-918.
    b. Structural Cracking. Concrete structures should be examined for 
structural cracking resulting from overstress due to applied loads, 
shrinkage and temperature effects or differential movements.
    c. Movement--Horizontal and Vertical Alignment. Concrete structures 
should be examined for evidence of any abnormal settlements, heaving, 
deflections, or lateral movements.
    d. Junctions. The conditions at the junctions of the structure with 
abutments or embankments should be determined.
    e. Drains--Foundation, Joint, Face. All drains should be examined to 
determine that they are capable of performing their design function.
    f. Water Passages. All water passages and other concrete surfaces 
subject to running water should be examined for erosion, cavitation, 
obstructions, leakage or significant structural cracks.
    g. Seepage or Leakage. The faces, abutments and toes of the concrete 
structures should be examined for evidence of seepage or abnormal 
leakage, and records of flow of downstream springs reviewed for 
variation with reservoir pool level. The sources of seepage should be 
determined if possible.
    h. Monolith Joints--Construction Joints. All monolith and 
construction joints should be examined to determine the condition of the 
joint and filler material, any movement of joints, or any indication of 
distress or leakage.
    i. Foundation. Foundation should be examined for damage or possible 
undermining of the downstream toe.
    j. Abutments. The abutments should be examined for sign of 
instability or excessive weathering.
    2. Embankment Structures.
    a. Settlement. The embankments and downstream toe areas should be 
examined for any evidence of localized or overall settlement, 
depressions or sink holes.
    b. Slope Stability. Embankment slopes should be examined for 
irregularities in

[[Page 303]]

alignment and variances from smooth uniform slopes, unusual changes from 
original crest alignment and elevation, evidence of movement at or 
beyond the toe, and surface cracks which indicate movement.
    c. Seepage. The downstream face of abutments, embankment slopes and 
toes, embankment--structure contacts, and the downstream valley areas 
should be examined for evidence of existing or past seepage. The sources 
of seepage should be investigated to determine cause and potential 
severity to dam safety under all operating conditions. The presence of 
animal burrows and tree growth on slopes which might cause detrimental 
seepage should be examined.
    d. Drainage Systems. All drainage systems should be examined to 
determine whether the systems can freely pass discharge and that the 
discharge water is not carrying embankment or foundation material. 
Systems used to monitor drainage should be examined to assure they are 
operational and functioning properly.
    e. Slope Protection. The slope protection should be examined for 
erosion-formed gullies and wave-formed notches and benches that have 
reduced the embankment cross-section or exposed less wave resistant 
materials. The adequacy of slope protection against waves, currents, and 
surface runoff that may occur at the site should be evaluated. The 
condition of vegetative cover should be evaluated where pertinent.
    3. Spillway Structures. Examination should be made of the structures 
and features including bulkheads, flashboards, and fuse plugs of all 
service and auxiliary spillways which serve as principal or emergency 
spillways for any condition which may impose operational constraints on 
the functioning of the spillway.
    a. Control Gates and Operating Machinery. The structural members, 
connections, hoists, cables and operating machinery and the adequacy of 
normal and emergency power supplies should be examined and tested to 
determine the structural integrity and verify the operational adequacy 
of the equipment. Where cranes are intended to be used for handling 
gates and bulkheads, the availability, capacity and condition of the 
cranes and lifting beams should be investigated. Operation of control 
systems and protective and alarm devices such as limit switches, sump 
high water alarms and drainage pumps should be investigated.
    b. Unlined Saddle Spillways. Unlined saddle spillways should be 
examined for evidence of erosion and any conditions which may impose 
constraints on the functioning of the spillway. The ability of the 
spillway to resist erosion due to operation and the potential hazard to 
the safety of the dam from such operation should be determined.
    c. Approach and Outlet Channels. The approach and outlet channels 
should be examined for any conditions which may impose constraints on 
the functioning of the spillway and present a potential hazard to the 
safety of the dam.
    d. Stilling Basin (Energy Dissipators). Stilling basins including 
baffles, flip buckets or other energy dissipators should be examined for 
any conditions which may pose constraints on the ability of the stilling 
basin to prevent downstream scour or erosion which may create or present 
a potential hazard to the safety of the dam. The existing condition of 
the channel downstream of the stilling basin should be determined.
    4. Outlet Works. The outlet works examination should include all 
structures and features designed to release reservoir water below the 
spillway crest through or around the dam.
    a. Intake Structure. The structure and all features should be 
examined for any conditions which may impose operational constraints on 
the outlet works. Entrances to intake structure should be examined for 
conditions such as silt or debris accumulation which may reduce the 
discharge capabilities of the outlet works.
    b. Operating and Emergency Control Gates. The structural members, 
connections, guides, hoists, cables and operating machinery including 
the adequacy of normal and emergency power supplies should be examined 
and tested to determine the structural integrity and verify the 
operational adequacy of the operating and emergency gates, valves, 
bulkheads, and other equipment.
    c. Conduits, Sluices, Water Passages, Etc. The interior surfaces of 
conduits should be examined for erosion, corrosion, cavitation, cracks, 
joint separation and leakage at cracks or joints.
    d. Stilling Basin (Energy Dissipator). The stilling basin or other 
energy dissipator should be examined for conditions which may impose any 
constraints on the ability of the stilling basin to prevent downstream 
scour or erosion which may create or present a potential hazard to the 
safety of the dam. The existing condition of the channel downstream of 
the stilling basin should be determined by soundings.
    e. Approach and Outlet Channels. The approach and outlet channels 
should be examined for any conditions which may impose constraints on 
the functioning of the discharge facilities of the outlet works, or 
present a hazard to the safety of the dam.
    f. Drawdown Facilities. Facilities provided for drawdown of the 
reservoir to avert impending failure of the dam or to facilitate repairs 
in the event of stability or foundation problems should be examined for 
any conditions which may impose constraints on their functioning as 
planned.
    5. Safety and Performance Instrumentation. Instruments which have 
been installed to measure behavior of the structures should be

[[Page 304]]

examined for proper functioning. The available records and readings of 
installed instruments should be reviewed to detect any unusual 
performance of the instruments or evidence of unusual performance or 
distress of the structure. The adequacy of the installed instrumentation 
to measure the performance and safety of the dam should be determined.
    a. Headwater and Tailwater Gages. The existing records of the 
headwater and tailwater gages should be examined to determine the 
relationship between other instrumentation measurements such as stream 
flow, uplift pressures, alignment, and drainage system discharge with 
the upper and lower water surface elevations.
    b. Horizontal and Vertical Alignment Instrumentation (Concrete 
Structures). The existing records of alignment and elevation surveys and 
measurements from inclinometers, inverted plumb bobs, gage points across 
cracks and joints, or other devices should be examined to determine any 
change from the original position of the structures.
    c. Horizontal and Vertical Movement, Consolidation, and Pore-Water 
Pressure Instrumentation (Embankment Structures). The existing records 
of measurements from settlement plates or gages, surface reference 
marks, slope indicators and other devices should be examined to 
determine the movement history of the embankment. Existing piezometer 
measurements should be examined to determine if the pore-water pressures 
in the embankment and foundation would under given conditions impair the 
safety of the dam.
    d. Uplift Instrumentation. The existing records of uplift 
measurements should be examined to determine if the uplift pressures for 
the maximum pool would impair the safety of the dam.
    e. Drainage System Instrumentation. The existing records of 
measurements of the drainage system flow should be examined to establish 
the normal relationship between pool elevations and discharge quantities 
and any changes that have occurred in this relationship during the 
history of the project.
    f. Seismic Instrumentation. The existing records of seismic 
instrumentation should be examined to determine the seismic activity in 
the area and the response of the structures of past earthquakes.
    6. Reservoir. The following features of the reservoir should be 
examined to determine to what extent the water impounded by the dam 
would constitute a danger to the safety of the dam or a hazard to human 
life or property.
    a. Shore line. The land forms around the reservoir should be 
examined for indications of major active or inactive landslide areas and 
to determine susceptibility of bedrock stratigraphy to massive 
landslides of sufficient magnitude to significantly reduce reservoir 
capacity or create waves that might overtop the dam.
    b. Sedimentation. The reservoir and drainage area should be examined 
for excessive sedimentation or recent developments in the drainage basin 
which could cause a sudden increase in sediment load thereby reducing 
the reservoir capacity with attendant increase in maximum outflow and 
maximum pool elevation.
    c. Potential Upstream Hazard Areas. The reservoir area should be 
examined for features subject to potential backwater flooding resulting 
in loss of human life or property at reservoir levels up to the maximum 
water storage capacity including any surcharge storage.
    d. Watershed Runoff Potential. The drainage basin should be examined 
for any extensive alterations to the surface of the drainage basin such 
as changed agriculture practices, timber clearing, railroad or highway 
construction or real estate developments that might extensively affect 
the runoff characteristics. Upstream projects that could have impact on 
the safety of the dam should be identified.
    7. Downstream Channel. The channel immediately downstream of the dam 
should be examined for conditions which might impose any constraints on 
the operation of the dam or present any hazards to the safety of the 
dam. Development of the potential flooded area downstream of the dam 
should be assessed for compatibility with the hazard classification.
    8. Operation and Maintenance Features.
    a. Reservoir Regulation Plan. The actual practices in regulating the 
reservoir and discharges under normal and emergency conditions should be 
examined to determine if they comply with the designed reservoir 
regulation plan and to assure that they do not constitute a danger to 
the safety of the dam or to human life or property.
    b. Maintenance. The maintenance of the operating facilities and 
features that pertain to the safety of the dam should be examined to 
determine the adequacy and quality of the maintenance procedures 
followed in maintaining the dam and facilities in safe operating 
condition.

          Appendix III to App. D to Sec.  222.6--Pub. L. 92-367

[[Page 305]]

[GRAPHIC] [TIFF OMITTED] TC31OC91.022


[[Page 306]]


[GRAPHIC] [TIFF OMITTED] TC31OC91.023

              Appendix E to Sec.  222.6--Suggested Outline

Inspection Report--National Dam Inspection Program (RCS-DAEN-CWE-17 and 
                            OMB No. 49-R0421)

Title Sheet

    Name of Dam
    ID Number from Inventory
    State, County and River or Stream where dam is located
    Owner
    Size and Hazard Classification
    Names of Inspectors
    Names of Review Board
    Approval Signature of District Engineer

                            Table of Contents

                           General Assessment

    Give brief assessment of general condition of dam with respect to 
safety, including a listing of deficiencies, and recommendations 
indicating degree of urgency.

                             1. Introduction

    a. Authority
    b. Purpose and Scope of Inspection

                         2. Project Information

    a. Site Information
    b. Description of Structures--Dam, Outlet, Spillway and other 
principal features.
    c. Purpose of Dam
    d. Design, Construction and Operating History

                           3. Field Inspection

    Briefly describe physical condition of the dam and appurtenant 
structures as they were observed during the field inspection. (If field 
inspection form is appended, only present summary.) Describe operational 
procedures, including any warning system, condition of operating 
equipment, and provision for emergency procedures. Describe any 
pertinent observations of the reservoir area and downstream channel 
adjacent to dam.

[[Page 307]]

                              4. Evaluation

    a. Structural and Geotechnical
    (1) General
    (2) Embankment and/or Foundation Condition
    (3) Stability--Briefly discuss pertinent information such as design, 
construction and operating records. Assess stability under maximum 
loading on basis of the record data, together with observations of field 
inspection and results of any additional, brief calculations performed 
by inspectors. If additional, detailed stability analyses are considered 
necessary, recommend that the owner engage a qualified engineer or firm 
to provide the analysis.
    b. Hydrologic and Hydraulic
    (1) Spillway Adequacy--Briefly describe pertinent record information 
such as hydrologic and hydraulic design data, flood of record, and 
previous analyses. Describe any hydraulic and hydrologic analyses made 
for this inspection. Present conclusion with respect to adequacy of 
spillway to pass the recommended spillway design flood without 
overtopping dam. If overtopping would occur, and if available from the 
type of analysis used, give maximum depth over top of dam and duration 
of overtopping, assuming the dam does not fail. Also indicate the 
largest flood, as a percentage of the probable maximum flood which can 
be passed without overtopping.
    (2) Effects of overtopping--If dam is overtopped by the recommended 
spillway design flood, provide assessment as to whether or not dam would 
likely fail, and if, in case of failure, the hazard to loss of life 
downstream of the dam would be substantially increased over that which 
would exist without failure. If information upon which to base a 
reasonable assessment is insufficient, so state and describe the needed 
data, and recommend that the necessary studies be performed by engineers 
engaged by the owner.
    c. Operation and Maintenance
    Assess operating equipment and procedures, emergency power for gate 
operation, and Emergency Action Plan. Assess quality of maintenance as 
it pertains to dam safety.

                             5. Conclusions

    Provide conclusions on condition of dam and list all deficiencies. 
If dam is considered unsafe, so state and give reason.

                           6. Recommendations

    List all recommended actions, including additional studies, 
installation of new surveillance procedures and devices, development of 
Emergency Action Plans, and remedial work. Recommend that a qualified 
engineering firm be retained to accomplish any recommended additional 
investigations and studies and also to design and supervise remedial 
works.

                               Appendixes

    a. Inspection Checklist (if available)
    b. Other Illustrations as follows:
    (1) Include a map showing location of the dam. Usually a portion of 
a USGS quadrangle sheet can be used which will show the topography of 
the area, location of the dam, exent of the lake and drainage basin, and 
perhaps indicate the downstream development.
    (2) If available, include a plan and section of the dam.
    (3) General photographs of the dam and downstream channel should be 
included.
    (4) Color photographs of deficiencies should be included. These 
should be held to the minimum required to illustrate the deficiencies.
    (5) Available engineering data including Hydrologic/Hydraulic 
calculation and physical test results that might be available.

                        Appendix F to Sec.  222.6

 Instructions for Unsafe Dam Data Sheet (RCS-DAEN-CWE-17 and OMB No. 49-
                                 R0421)

    The indicated information shall be provided in the format shown on 
Pg F-3 for each dam assessed to be unsafe during the reporting period. A 
separate data sheet should be provided for each unsafe dam. The 
information supplied should conform to the following.
    a. Name--Name of dam.
    b. Id. No.--Dam inventory identity number.
    c. Location--List state county, river or stream and nearest D/S city 
or town where the dam is located.
    d. Height--Maximum hydraulic height of dam.
    e. Maximum Impoundment Capacity--List the capacity of the reservior 
at maximum attainable water surface elevation including any surcharge 
loading.
    f. Type--Type of dam, i.e., earth, rockfill, gravity, combination 
earth-gravity, etc.
    g. Owner--Owner of dam.
    h. Date Governor Notified of Unsafe Condition--The date and method 
of notification, such as, by telegram, letter, report, etc.
    i. Condition of Dam Resulting in Unsafe Assessment--Brief 
description of the deficiencies discovered which resulted in the unsafe 
assessment.
    j. Description of Danger Involved--Downstream (D/S) hazard potential 
category and a brief description of the danger involved.
    k. Recommendations Given to Governor--Brief description of the 
actions recommended to Governor at time of notification of unsafe 
condition to eliminate or reduce the danger.
    l. Urgency Category--State whether the unsafe condition of the dam 
is an emergency or non-emergency situation. An emergency situation 
should be considered to exist if the failure of the dam is judged to be 
imminent

[[Page 308]]

and requires immediate action to eliminate or reduce the danger.
    m. Emergency Actions Taken--In case of an emergency situation, list 
the actions taken. For non-emergency situation, put NA for ``not 
applicable.''
    n. Remedial Action Taken--For non-emergency situations list remedial 
actions taken.
    o. Remarks--For other pertinent information.

 Format for Unsafe Dam Data Sheet (RCS-DAEN-CWE-17 and OMB No. 49-R0421

  National Program of Inspection of Non-Federal Dams--Unsafe Dam Data 
                                  Sheet

    a. Name:
    b. Type:
    c. Height:
    d. Id. No.
    e. Location:
     State: County:
     Nearest D/S City, Town or Village:
     River or Stream:
    f. Owner:
    g. Date Governor Notified of Unsafe Condition:
    h. Condition of Dam Resulting in Unsafe Assessment:
    i. Description of Danger Involved:
    j. Recommendations Given to Governor:
    k. Urgency Category:
    l. Emergency Actions Taken:
    m. Remarks:

                        Appendix G to Sec.  222.6

 National Program for Inspection of Non-Federal Dams--Monthly Progress 
                        Report (RCS-DAEN-CWE-19)

I. Instructions for Monthly Progress Report. The indicated information 
shall be provided in the format shown on page G-2.

    1. Division Reporting:
    2. Date:
    3. Information Required for Each State Regarding Total Number of 
Inspections Performed (AE Inspections included) (Cumulative):
    3.1. Number of Inspections Initiated by on-site inspection or the 
review of engineering data from project records. \1\
---------------------------------------------------------------------------

    \1\ Each of the initiated inspections reported should be planned for 
completion within a reasonable period of time (30 days.)
---------------------------------------------------------------------------

    3.2. Number of Inspections Competed (The number of inspection 
reports which have been submitted to the District Engineer for review 
and approval).
    3.3 Number of Dams Reported to the Governor as Unsafe. \2\
---------------------------------------------------------------------------

    \2\ An unsafe dam is defined as a dam with deficiencies of such a 
nature that if not corrected could result in the failure of the dam with 
subsequent loss of lives or substantial property damage.
---------------------------------------------------------------------------

    3.4. Number of Approved Inspection Reports Submitted to the 
Governor.
    4. Information Required for Each State Regarding Inspections 
Performed Under AE Contracts (Cumulative):
    4.1. Number of Dams Contracted for Inspection by AE's with State or 
Corps.
    4.2. Number of Inspections Initiated by AE's by on-site inspection 
or the review of engineering data from project records. \1\
---------------------------------------------------------------------------

    \1\ See footnote on previous page.
---------------------------------------------------------------------------

    4.3. Number of Inspections Completed by AE's (The number of 
inspection reports which have been submitted to the District Engineer 
for review and approval).
    4.4. Number of Approved Inspection Reports Prepared by AE's 
Submitted to the Governor.

II. Formation for Monthly Progress Report.

 National Program for Inspection of Non-Federal Dams--Monthly Progress 
                                 Report

    1. Division Reporting:
    2. Date:
    3. Information Required for Each State Regarding Total Number of 
Inspections Performed (Cumulative):

------------------------------------------------------------------------
                                                       Unsafe
                              Inspection  Inspection    Dams    Approved
            State              Initiated   Completed  Reported   Reports
                                 (3.1)       (3.2)      (3.3)     (3.4)
------------------------------------------------------------------------



                             ===========================================
Total.......................
------------------------------------------------------------------------

    4. Information Required for Each State Regarding Inspections 
Performed Under A/E Contracts (Cumulative):

----------------------------------------------------------------------------------------------------------------
                                                                      Dams
                                                                    Under A/      A/E          A/E         A/E
                               State                                    E     Inspections  Inspections   Reports
                                                                    Contract   Initiated    Completed   Approved
                                                                      (4.1)      (4.2)        (4.3)       (4.4)
----------------------------------------------------------------------------------------------------------------



                                                                   =============================================
Totals............................................................
----------------------------------------------------------------------------------------------------------------

                        Appendix H to Sec.  222.6

  Suggested Scope of Work Contract for Architect-Engineer Services for 
         Safety Inspection of Dams Within the State of --------

    1. General Description of Scope of Work. The services to be rendered 
by the Architect-Engineer (AE) under the proposed contract

[[Page 309]]

shall include all engineering functions, hereinafter described, as 
needed to inspect the dams listed in Appendix A of this contract for the 
purpose of evaluating their risk of failure. A report which (a) 
describes the assessed condition of the dam, (b) provides conclusions as 
to which particular conditions could cause failure, (c) makes 
recommendations on remedial measures believed necessary, and (d) makes 
recommendations on whether and what type of future investigation should 
be conducted shall be provided for each inspected dam. The work shall 
proceed in accordance with Phase I of the Recommended Guidelines for 
Safety Inspection of Dams established by the Office of the Chief of 
Engineers (OCE) and the supplemented requirements listed in paragraph 3 
below. The OCE guidelines are listed in Appendix B of this contract.
    2. Information and Services To Be Furnished by the Government. The 
Contracting Officer will furnish the following information and services 
to the AE:
    a. All information pertaining to each dam to be inspected as 
contained in the National Inventory of Dams.
    b. Copies of recommended format for preparation of inspection 
report, engineering data check list and visual inspection check list.
    c. All available pertinent information pertaining to the Dam 
Inspection Program and previous investigations having a bearing on 
inspections to be performed under this contract.
    d. Right-of-entry for access to each dam site.
    3. Services To Be Rendered by the Architect-Engineer. The principal 
services, subject to the optional provisions of the contract, to be 
rendered by the AE are itemized below:
    a. Technical Investigations.
    (1) Engineering Data Collection. To the extent feasible, the 
engineering data listed in Appendix I of the OCE guidelines relating to 
the design, construction and operation of the dam and appurtenant 
structures, should be collected from existing records and reviewed to 
aid in evaluating the general condition of each dam, including an 
assessment of the hydraulic and hydrologic features and structural 
stability of the dam. Where the necessary engineering data are 
unavailable, inadequate or invalid, a listing shall be made of those 
specific additional data deemed necessary by the engineer in charge of 
the investigation and included in the inspection report. The engineering 
data checklist provided by the Contracting Officer shall be used as a 
guide to compile this data.
    (2) Field Inspections. The field inspection of each dam shall 
include examination of the items listed in Appendix II of the OCE 
guidelines, electrical and mechanical equipment for operation of the 
control facilities, reservoir area, downstream channel in the vicinity 
of the dam and any other significant feature to determine how these 
features affect the risk of failure of the dam. The inspection shall be 
conducted in a systematic manner to minimize the possibility of any 
significant feature being overlooked. The visual inspection checklist 
provided by the Contracting Officer shall be used as a guide to document 
the examination of each significant feature.
    Particular attention shall be given to detecting evidence of 
leakage, erosion, seepage, slope instability, undue settlement, 
displacement, tilting, cracking, deterioration, and improper functioning 
of drains and relief wells. The degree and quality of maintenance and 
regulating procedures for operation of the control facilities shall be 
assessed. The design and existing condition of such control facilities 
(i.e., spillway, outlet works, etc.) shall be evaluated. An assessment 
of the degree of siltation that is evident and its effect on the dam's 
reservoir shall be performed. Photographs and drawings should be used to 
record conditions in order to minimize written descriptions.
    (3) Engineering Analyses.
    (a) Evaluation of Hydraulic and Hydrologic (H&H) Features. 
Evaluation of the hydraulic and hydrological features of each dam shall 
be based on criteria set forth in the OCE guidelines. If it is 
determined that the available H&H data are insufficient, the Contracting 
Officer must be so informed and may exercise an option of requiring the 
AE to perform an overtopping analysis at additional agreed-upon 
compensation. The methodology to be used by the AE for this analysis 
will be based on the OCE guidelines and subject to the approval of the 
Contracting Officer.
    (b) Evaluation of Structural Stability. The evaluation of structural 
stability of each dam is to be based principally on existing conditions 
as revealed by the visual inspection, available design and construction 
information, and records of performance. The objectives are to determine 
the existence of conditions, identifiable by visual inspection or from 
records, which may pose a high risk of failure and to formulate 
recommendations pertaining to the need for any remedial improvements, 
additional studies, investigations, or analysis. The results of this 
phase of the inspection must rely substantially upon the experience and 
judgment of the inspecting engineer. Should it be determined that 
sufficient data are not available for a reasonable evaluation of the 
structural stability of a dam and appurtenances, the Contracting Officer 
should be informed which information is required prior to attempting to 
evaluate the risk of failure of the dam.
    (c) Evaluation of Operational Features. Where critical mechanical/
electrical operating equipment is used in controlling the

[[Page 310]]

reservoir of a dam, an evaluation of the operational characteristics of 
this equipment from the standpoint of risk of failure must be performed.
    (d) Evaluation of Reservoir Regulation Plan and Warning System. The 
operational characteristics of each dam's existing reservoir regulation 
plan and warning system in event of a threatened failure shall be 
investigated.
    b. Emergency Situations. The Contracting Officer must be immediately 
notified of any observed condition which is deemed to require immediate 
remedial action. After being notified, the Contracting Officer will 
contact the appropriate State personnel and will meet the AE at the site 
to determine the appropriate course of action. This will not relieve the 
AE of his responsibility to prepare a comprehensive inspection report at 
the earliest practicable date.
    c. Qualifications of Investigators. The technical investigations 
shall be conducted by licensed professional engineers with a minimum of 
five years experience after licensing in the investigation, design and 
contruction of earthfill, rockfill and concrete dams and/or in making 
risk of failure evaluations of completed dams. These engineers must be 
knowledgeable in the disciplines of hydrology, hydraulics, geotechnical, 
electrical, mechanical and structural engineering, as necessary. All 
field inspections should be conducted by engineers, engineering 
geologists and other specialists who are knowledgeable in the 
investigation, design, construction and operation of dams, including 
experts on mechanical and electrical operation of gates and controls, 
where needed.
    d. Preparation of Report. A formal report shall be prepared for each 
dam inspected for submission to the Contracting Officer. Each report 
should contain the information specified in OCE guidelines and any other 
pertinent information. The recommended format provided by the 
Contracting Officer shall be used to document each report. The signature 
and registration identification of the professional engineer who 
directed the investigation and who was responsible for evaluation of the 
dam should be included in the report.
    4. Supervision and Approval of Work. All work performed under this 
contract shall be subject to the review and approval of the Contracting 
Officer or his designee. Meetings will be held on a regular basis in the 
District office, during which the progress of inspections will be 
discussed and questions relating to inspection reports previously 
received by the Contracting Officer will be addressed. Reports will be 
revised as necessary when required by the Contracting Officer.
    5. Coordination. During the progress of work, the AE shall maintain 
liaison with the *-------- and other local authorities through the 
Contracting Officer as required to assure the orderly progression of the 
inspection. Copies of all correspondence with such authorities shall be 
provided to the Contracting Officer.
---------------------------------------------------------------------------

    * Note: Write in the designated State Authority.
---------------------------------------------------------------------------

    6. Submission of Report.
    a. Each inspection report will be submitted for review to the 
Contracting Officer. Reports will be revised as required by the 
Contracting Officer. After all revisions have been made, the original 
and ---- copies of each inspection report shall be submitted to the 
Contracting Officer.
    b. Text of all reports shall be typewritten and printed on both 
sides of 8x10\1/2\ paper. All notes, inspection 
forms, sketches or similar matter shall be legible, distinct and 
suitable for reproduction.
    7. Period of Services.
    a. All inspections and reports included under this contract shall be 
completed within ---- days from date of Notice to Proceed.
    b. If the option for performing an H&H analysis for any particular 
site is exercised, the AE shall complete such analysis within ---- days 
from date of Notice to Proceed. However, the overall completion time 
stated in paragraph 7a above shall not change.

                        Appendix I to Sec.  222.6

 Procedure for Using NASA Land Satellite Multispectral Scanner Data for 
        Verification and Updating the National Inventory of Dams

    1. Purpose. This appendix states the objective, defines the scope, 
prescribes procedures, and assigns responsibilities for using NASA Land 
Satellite (LANDSAT) Multispectral Scanner data along with NASA's Surface 
Water Detection And Mapping (DAM) Computer program to assist in 
verification and updating the National Inventory of Dams.
    2. Applicability. This appendix is applicable to all divisions and 
districts having Civil Works responsibilities except POD.
    3. Reference. NASA, DETECTION AND MAPPING PACKAGE, Users Manuals, 
Volumes 1, 2a, 2b, and 3 dated June 1976, published by the Johnson Space 
Center, Houston, Texas.
    4. Objectives. Provide a uniform method, nation-wide, to help insure 
that all dams subject to Public Law 92-367, 8 August 1972 are properly 
identified and located in the National Inventory of Dams.
    5. Scope. The computer printer overlay maps produced by the 
procedure described in reference 3b will be used by district and/or 
state or contractor personnel as a tool to assist in verification and 
updating of the National Inventory of Dams.

[[Page 311]]

    6. Exceptions. a. If a Division/District attempts the use of the 
procedure for a given region within their area of responsibility and 
finds the overlay maps cannot be used to assist in verification and 
updating the National Inventory of Dams, they may request an exception 
for a selected region. A selected region may include areas where 
conditions can reasonably be assumed to be the same as the region where 
the procedure was tried.
    b. Request for exceptions should be documented to include firm 
boundary definitions and appropriate justification to demonstrate why 
the procedure cannot be used. This request should be submitted to WRSC 
WASH DC 20314, through the normal engineering chain of command.
    c. Map overlays will be produced for all areas of the Continental 
United States even if they are not used in a few selected regions. This 
processing is required for a future Computer Water Body Change Detection 
system.
    7. Procedures. Acquisition of LANDSAT data, registration of 
satellite coordinates to earth latitude and longitude and computer 
processing to produce overlay maps will be accomplished by two Regional 
Centers. Nashville District and Seattle District have been designated as 
the Regional Centers, with each responsible for processing maps by state 
based on Divisional assignments in Appendix A. Regional Centers will 
support divisions as follows:

------------------------------------------------------------------------
              Regional Center                         Division
------------------------------------------------------------------------
Nashville District                          New England
                                            North Atlantic
                                            South Atlantic
                                            Ohio River
                                            Lower Mississippi Valley
                                            North Central

Seattle District                            Southwestern
                                            Missouri River
                                            North Pacific
                                            South Pacific
------------------------------------------------------------------------

    8. Responsibilities. a. The Water Resources Support Center at Fort 
Belvoir has overall responsibility for coordination and monitoring of 
this activity between NASA, Division Offices, and Regional Centers, and 
for providing Regional Center funding.
    b. Regional Centers are responsible for:
    (1) Acquiring proper LANDSAT data tape from EROS Data Center (Sioux 
Falls, South Dakota). Actual data scene selection will be coordinated 
with Division and/or District to insure proper consideration is given to 
local priorities and seasonal coverage.
    (2) Arranging computer processing support using NASA's DAM package.
    (3) Establishing proper control between satellite scanner-oriented 
coordinates and earth latitude/longitude.
    (4) Producing total coverage of map overlays at a scale of 1:24,000 
and/or smaller scales as required by Divisions and/or Districts.
    (5) Instructing District, State, or contractor personnel in the 
assembly and use of map overlays.
    c. Divisions/Districts are responsible for:
    (1) Designating one person from each Division and District as the 
point of contact with the Regional Center and provide this person's name 
and phone number to the Regional Center.
    (2) Providing the Regional Center with map coverage of their area of 
responsibility. This will include state indexes and 7\1/2\ minute 
quadrangle sheets (scale 1:24,000) where available.
    (3) Coordinating with the Regional Center in selecting LANDSAT data 
tapes.
    (4) Providing information to Regional Center on scale and priorities 
of desired computer produced map overlays.
    (5) Assembling computer print-outs into overlay maps, and using as 
appropriate to assist in verification and updating the National 
Inventory of Dams.
    9. Points of Contact. The points of contact in the Regional Centers 
for this program are as follows:

                   Name, Office Symbol, and Telephone

Jim Cook--DAEN-ORNED, (615) 251-7366; FTS 852-7366.
Jack Erlandson--DAEN-NPSEN, (206) 764-3535; FTS 399-3535.

[44 FR 55336, Sept. 26, 1979, as amended at 45 FR 18925, Mar. 24, 1980. 
Redesignated at 60 FR 19851, Apr. 21, 1995]