[Code of Federal Regulations]
[Title 33, Volume 3]
[Revised as of July 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 33CFR240.9]

[Page 334-337]
 
                TITLE 33--NAVIGATION AND NAVIGABLE WATERS
 
 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 
                                 DEFENSE
 
PART 240_GENERAL CREDIT FOR FLOOD CONTROL--Table of Contents
 
Sec.  240.9  Procedures.

    (a) For non-Federal works undertaken prior to 17 November 1986, 
credit determinations (deferred until these guidelines became effective) 
will be made by the Secretary in response to the applications received 
prior to 31 March 1987. Future non-Federal works for which credit may be 
allowed under the provisions of section 104 of Pub. L. 99-662 are 
limited, basically, to local works undertaken while Federal 
preauthorizations studies of a Federal project for the locality are in 
progress. Credit consideration for such works will be governed by the 
procedures set forth here. Non-Federal entities desiring credit should 
confer with the District Engineer and submit a written application to 
him. The application will include a full description of planned work, 
plans, sketches, and similar engineering data and information sufficient 
to permit analysis of the local proposal.
    (b) The District Engineer shall review the engineering adequacy of 
the local proposal and its relation to the Federal Plan and determine 
what part of the proposed local improvement would be eligible for 
credit. The District Engineer will forward his recommendations through 
the Division Engineer and the Chief of Engineers to the Assistant 
Secretary of the Army

[[Page 335]]

(Civil Works) and provide information on:
    (1) Basis for concluding the local plan is appropriate in relation 
to the prospective Federal plan.
    (2) Total estimated cost and benefits of creditable work.
    (3) Environmental effects of the local work, including a brief 
statement of both beneficial and detrimental effects to significant 
resources.
    (4) The urgency for proceeding with the local plan.
    (c) Upon being informed of the Secretary's decision, the District 
Engineer shall reply by letter stating to the local applicant what local 
work and costs can reasonably be expected to be recommended for credit 
under the provisions of section 104 (assuming that the final plan for a 
Federal project, when it is ultimately recommended, remains such as to 
preserve the local work as a relevant element). If the improvement 
proposed by the non-Federal entity includes work that will not become a 
part of the Federal project, the means of determining the part eligible 
for credit shall be fully defined. This letter shall include the 
following conditions:
    (1) This shall not be interpreted as a Federal assurance regarding 
later approval of any project nor shall it commit the United States to 
any type of reimbursement if a Federal project is not undertaken.
    (2) This does not eliminate the need for compliance with other 
Federal, State, and local requirements, including any requirements for 
permits, Environmental Impact Statements, etc.
    (3) Upon authorization of the Federal project, approval shall be 
subject to rescission if the non-Federal work has not commenced and, as 
a consequence, Corps planning for orderly implementation of the project 
is being adversely affected.
    (d) The non-Federal entity will notify the District engineer when 
work commences. The District Engineer will conduct periodic and final 
inspections. Upon completion of local work, local interests shall 
provide the District Engineer details of the work accomplished and the 
actual costs directly associated therewith. The District Engineer shall 
audit claimed costs to ascertain and confirm those costs properly 
creditable and shall inform the non-Federal entity of the audit results.
    (e) During further Corps studies, the local work actually 
accomplished that would constitute a legitimate part of the overall 
recommended Federal project may be incorporated within any plan later 
recommended for implementation.
    (f) The District Engineer shall submit a copy of his letter and 
notification of creditable costs of completed work to the Secretary 
through the Division Engineer and the Chief of Engineers.
    (g) All justification sheets supporting new start recommendations 
for Preconstruction Engineering and Design or Construction of projects 
will include information on credits in the paragraph on local 
cooperation. The information should include but not be limited to date 
of the District Engineer's letter to the sponsor pursuant to Sec.  
240.9(c) of this regulation, status of the creditable work, estimated or 
actual cost of the work and the estimated amount of credit.

                    Appendix A to Part 240 [Reserved]

  Appendix B to Part 240--Formulas for Determining Amount of Allowable 
                                 Credit

    1. General. The amount of credit that non-Federal interests may 
receive under the provisions of section 104 of the Water Resources 
Development Act of 1986 depends first on the value of the compatible 
work they have accomplished and then on the value of the local 
cooperation against which they may receive credit. If the compatible 
work is for construction which was outside the scope of the project as 
authorized, the costs for the compatible work for which credit is 
desired are additive to the original estimate of total project cost. 
This increases the estimated cost of basic local cooperation 
requirements, thus enlarging the target against which credit may be 
given.
    2. The ``formulas'' for determining the amount of credit that may be 
allowed in the various cases are provided in the following paragraphs. 
TPC means the total estimate of project costs for the project as it was 
authorized. LERRD means the costs for lands, easements, rights-of-way, 
relocations and disposal areas as included in that estimate.
    3. Calculations for several hypothetical examples are provided to 
illustrate how crediting determinations would impact on

[[Page 336]]

project costs and on cost sharing. For each of these examples it is 
assumed that the estimated total project cost (TPC) of the project as 
authorized is $100.0 million. All of the elements of cost are given in 
millions of dollars.
    4. Integral Work. For compatible work that is integral with the 
project as authorized (240.7(a)(1)) or compatible work that constitutes 
an advantageous substitution for work integral with the authorized 
project (i.e., substitute work, 240.7(a)(3)):

a. LERRD <=20% TPC
    Credit = Value of compatible work up to 20% TPC
b. LERRD =20% TPC
    Credit = Value of compatible work up to LERRD

    Crediting non-Federal interests for constructing an integral part of 
the project or substitute work will not result in any increase in 
project costs. Ordinarily, the result will simply be a transfer of 
equivalent responsibilities between the Corps and non-Federal interests. 
If non-Federal interests should accomplish compatible integral or 
substitute work exceeding the possible credit, the Corps will be 
relieved of the expense of constructing an increment of the project. An 
example is provided below. In this example, non-Federal interests have 
accomplished integral project work amounting to 30.0 million. LERRD are 
less than 20% of TPC so that the maximum value of local cooperation 
against which they may receive credit is $20.0 million. Since the $10.0 
for which credit cannot be given nonetheless represents useful project 
work, in this example the Corps would be relieved of the costs for 
accomplishing that much construction.

------------------------------------------------------------------------
                                                                Credit
                                                     Basic    Example 1:
              Case: LERRD <= 20% TPC                project   Compatible
                                                              work, 30.0
------------------------------------------------------------------------
Non-Federal:
  5% Cash........................................       5.0          5.0
  LERRD..........................................      14.0          0.0
  Extra cash (toward constr.)....................       6.0          0.0
  Construction (actual)..........................  ........         30.0
                                                  ----------------------
      Subtotal...................................      25.0         35.0
                                                  ======================
Federal:
  Construction...................................      75.0         51.0
  LERRD..........................................  ........         14.0
                                                  ----------------------
      Subtotal...................................      75.0         65.0
                                                  ======================
      TPC........................................     100.0        100.0
Reduction in Federal costs.......................  ........     \1\ 10.0
------------------------------------------------------------------------
\1\ The amount by which the integral or substitute work actually
  accomplished by non-Federal interests exceeds the requirements of
  local cooperation against which credit may be given.

    5. External Work. For compatible work outside the scope of the 
project as authorized (i.e., external work, 240.7(a)(2)):
a. LERRD <=25% TPC

    Credit = Value of compatible work up to 25% TPC
b. LERRD =25% TPC
    Credit = Value of compatible work up to LERRD

    Crediting non-Federal interests for compatible work which was not 
part of the project as authorized (external work) will result in an 
increase in project costs and an increase in the net Federal costs. The 
costs for compatible external work for which non-Federal interests 
desire credit must be incorporated into the estimate of total project 
costs (but only to the extent that credit can actually be given). 
Assigned Federal and non-Federal project costs then making up the 
adjusted total project costs will both be greater than for the basic 
project. However, the net effect will be a savings to non-Federal 
interests in the further costs they will have for fulfilling local 
cooperation requirements. The maximum amount that can be credited for 
compatible external work (and thus added to project costs), where LERRD 
<=25% TPC, follows from Credit, C = 20% (TPC + C) which reduces to C = 
0.2TPC + 0.2C, then to 0.8C = 0.2TPC, and finally C = (0.2/0.8)TPC or 
0.25TPC as indicated in a, above. An example of crediting in a case 
involving external work is provided below. In this example, as in 
example 1, non-Federal interests have accomplished work amounting to 
$30.0 million. This work, however, was not intergral with the project as 
authorized (it has been determined to be compatible external work), so 
that any part of it for which credit is given must be added to TPC. 
Since, in this case LERRD are less than 25% of TPC, the maximum amount 
that can be credited is 25% of TPC, or $25.0 million. Adjusting TPC by 
this amount results in an added Federal cost of $18.75 million (75% of 
the $25.0 million increase).

------------------------------------------------------------------------
                                                               Credit
                                                    Basic    Example 2,
              Case: LERRD <=25% TPC                project   Compatible
                                                             work, 30.0
------------------------------------------------------------------------
Non-Federal:
  5% Cash.......................................       5.0          6.25
  LERRD.........................................      14.0          0.0
  Extra cash (toward constr.)...................       6.0          0.0
  Construction (actual).........................  ........         25.0
                                                 -----------------------
      Subtotal..................................      25.0         31.25
                                                 =======================
Federal:
  Construction..................................      75.0         79.75
  LERRD.........................................  ........         14.0
                                                 -----------------------
      Subtotal..................................      75.0         93.75
TPC.............................................     100.0  ............
Adjusted TPC....................................  ........        125.0
Excess of Compatible Work.......................  ........      \1\ 5.0

[[Page 337]]


Increase in Federal Costs.......................  ........     \2\ 18.75
------------------------------------------------------------------------
\1\ This portion of the compatible external work is not incorporated in
  the project costs because it would be a disadvantage to the project
  sponsor to do so (if included, the sponsor would become obligated for
  an additional 5% up-front cash contribution but without any savings in
  other local cooperation because there would be nothing left to give
  credit against).
\2\ This is also the measure of the net savings to non-Federal interests
  by virtue of crediting.

    6. Combined integral and external works. For cases where non-Federal 
interests have accomplished compatible work, some of which is integral 
with the project as authorized and some of which is outside the original 
scope (external), determination of the allowable credit is a two step 
process. Work that is integral to the project is credited first. This, 
C1, is accomplished in accordance with paragraph 4 above. If, after this 
step, there remain local cooperation requirements against which credit 
may be given, credit for compatible external work, C2, is determinable 
on the following basis.

a. LERRD <=20% (TPC+C2)
    C2=Value of compatible work up to 25% TPC-1.25C1
b. LERRD =20% (TPC+C2)
    C2=Value of compatible work up to remaining LERRD

    Note that total credit, C=C1+C2. Formula 6.a. is derived from 
C=C1+C2=20% (TPC+C2). An example of crediting in a case involving both 
kinds of compatible works is provided below. In this example non-Federal 
interests have accomplished $25.0 million in compatible work, $5.0 of 
which was integral with the project as authorized and $20.0 of which was 
external. The integral work is credited in the first step against the 
extra cash component of the original local cooperation requirements. TPC 
is unaffected; however, the target against which credit for the external 
work might be credited has been partially used up. The second step shows 
only the incremental effects of crediting external work. Using 6.a. the 
maximum credit that can be given for this work is $18.75 million. 
Although other non-Federal requirements are extinguished as a result of 
the credit for the external work, the non-Federal 5% cash contribution 
increases by $0.9375 million, say $0.94 (5% of $18.75). In the final 
step, the incremental effects of crediting the external work are added 
in with the values obtained in step 1.

----------------------------------------------------------------------------------------------------------------
                                                                          Credit Example 3: Compatible work, \1\
                                                               Basic                       25.0
                Case: LERRD <=20% (TPC+C2)                    project   ----------------------------------------
                                                                            Step 1       Step 2         Final
----------------------------------------------------------------------------------------------------------------
Non-Federal:
    5% Cash...............................................          5.0          5.0          0.94          5.94
    LERRD.................................................         14.0         14.0          0.0           0.0
    Extra cash (toward constr.)...........................          6.0          1.0          0.0           0.0
    Construction (actual).................................  ...........          5.0         18.75         23.75
                                                           -----------------------------------------------------
      Subtotal............................................         25.0         25.0  ............         29.69
                                                           =====================================================
Federal:
  Construction............................................         75.0         75.0          0.06         75.06
  LERRD...................................................  ...........  ...........         14.0          14.0
                                                           -----------------------------------------------------
      Subtotal............................................         75.0         75.0  ............         89.06
TPC.......................................................        100.0        100.0  ............  ............
Adjusted TPC..............................................  ...........  ...........  ............        118.75
Excess of Compatible Worth................................  ...........  ...........          1.25          1.25
Increase in Federal Costs.................................  ...........  ...........  ............         14.06
----------------------------------------------------------------------------------------------------------------
\1\ Compatible work consisting of 5.0 integral work credited in first step of calculations plus 20.0 external
  work credited, to the extent possible, in second step.